ItemPerMedianMiddle halfWinning bids
Refl PAV Mrkr TY Ii-a-aeach$5.51$4.50 – $7.701,561
Portable Changeable Message Signday$100.00$45.00 – $150.001,458
Temp Sedmt Cont Fence (Remove)linear foot$1.00$1.00 – $1.851,303
Biodeg Erosn Cont Logs (Remove)linear foot$1.40$1.00 – $2.501,298
Temp Sedmt Cont Fence (Install)linear foot$4.25$3.49 – $5.171,294
Refl PAV Mrkr TY I-Ceach$5.50$4.50 – $7.501,105
Remove SM RD SN Sup&Ameach$114.74$100.00 – $160.001,091
Guardrail End Treatment (Install)each$3,355$3,050 – $3,7001,085
Refl PAV MRK TY I (W)8"(SLD)(100MIL)linear foot$1.20$0.95 – $2.001,002
Riprap (Mow Strip)(4 in)cubic yard$675.00$580.00 – $800.00953
Refl PAV Mrkr TY Ii-c-reach$5.30$4.48 – $7.00946
Tack Coatgallon$4.50$3.50 – $6.50932
In SM RD SN Sup&Am TY10BWG(1)SA(P)each$750.00$650.00 – $901.49926
Refl PAV MRK TY I (W)24"(SLD)(100MIL)linear foot$8.59$6.99 – $12.10896
Remove Metal Beam Guard Fencelinear foot$3.00$2.30 – $5.00880
MTL W-beam GD Fen (Tim Post)linear foot$28.00$25.00 – $32.00795
WK ZN PAV MRK SHT Term (Tab)Ty Weach$1.50$1.00 – $2.20781
Rock Filter Dams (Remove)linear foot$13.00$10.00 – $20.00770
WK ZN PAV MRK SHT Term (Tab)Ty Y-2each$1.50$1.00 – $2.10753
Biodeg Erosn Cont Logs (Instl) (12")linear foot$6.10$4.82 – $9.00752
CEM Stabil Bkflcubic yard$203.10$149.69 – $285.00720
In SM RD SN Sup&Am TY10BWG(1)SA(T)each$850.00$750.00 – $1,000704
MTL Beam GD Fen Trans (Thrie-beam)each$2,271$1,900 – $2,700691
Guardrail End Treatment (Remove)each$275.00$220.00 – $400.00656
Refl PAV MRK TY I (Y)6"(SLD)(100MIL)linear foot$0.75$0.57 – $1.27642
Construction Exits (Remove)square yard$10.00$5.30 – $15.00600
Refl PAV MRK TY I (W)6"(SLD)(100MIL)linear foot$0.745$0.56 – $1.22598
Excav (Roadway)cubic yard$18.91$12.50 – $30.00593
Downstream Anchor Terminal Sectioneach$1,500$1,251 – $1,750590
TMA (Mobile Operation)hour$75.00$25.00 – $100.00565
Remov Str (Pipe)linear foot$25.00$15.00 – $40.00560
RC Pipe (CL III)(24 in)linear foot$116.60$95.10 – $150.00550
Flowable Backfillcubic yard$350.00$250.00 – $510.23537
Riprap (CONC)(4 in)cubic yard$723.00$560.00 – $1,000532
Construction Exits (Install) (TY 1)square yard$31.25$20.00 – $40.16517
Instl Del Assm (D-sw)Sz 1(BRF)GF2(BI)each$35.00$27.25 – $47.75515
Refl PAV MRK TY I (W)(Arrow)(100MIL)each$180.00$150.00 – $231.75502
WK ZN PAV MRK Non-remov (Y)6"(SLD)linear foot$0.4$0.27 – $0.55502
PAV Surf Prep for MRK (24")linear foot$1.00$0.495 – $2.45500
Refl PAV MRK TY I (W)(Word)(100MIL)each$211.75$175.00 – $270.00500
Rock Filter Dams (Install) (TY 2)linear foot$46.00$38.00 – $55.95499
RC Pipe (CL III)(18 in)linear foot$88.00$70.00 – $110.00486
Temporary SPL Shoringsquare foot$33.39$20.00 – $55.00481
Crash Cush Atten (Remove)each$1,000$775.00 – $1,500479
Block Soddingsquare yard$7.48$5.04 – $10.00468
Driveways (ACP)square yard$65.00$48.24 – $88.31460
Vegetative Wateringthousand gallons$35.00$15.00 – $70.20443
Remove Terminal Anchor Sectioneach$226.60$150.00 – $364.85443
Driveways (CONC)square yard$120.00$100.00 – $145.00441
Conc Str Repair (Vertical & Overhead)square foot$200.00$130.00 – $282.00435
Condt (PVC) (Sch 40) (2")linear foot$15.25$11.42 – $22.94434
Elec Condr (NO.6) Barelinear foot$2.37$2.00 – $3.00432
Elec Condr (NO.6) Insulatedlinear foot$2.64$2.25 – $3.13428
Elec Condr (NO.8) Insulatedlinear foot$2.20$1.85 – $2.75423
Elec Condr (NO.8) Barelinear foot$2.00$1.71 – $2.50419
Riprap (CONC)(5 in)cubic yard$650.00$550.00 – $800.00412
Refl PAV MRK TY I (W)12"(SLD)(100MIL)linear foot$4.00$3.00 – $5.00412
PAV Surf Prep for MRK (Arrow)each$20.00$10.00 – $45.38410
Aluminum Signs (TY A)square foot$37.10$30.00 – $50.00404
Ground Box TY D (162922)W/Aproneach$1,636$1,340 – $2,028400
VEH Sig Sec (12")LED(YEL)each$336.39$285.00 – $390.57399
In SM RD SN Sup&Am TYS80(1)SA(T)each$1,040$900.00 – $1,200399
PAV Surf Prep for MRK (Word)each$20.00$10.00 – $50.00398
Clean Exist Culvertseach$2,800$1,600 – $5,000395
MTL W-beam GD Fen (Steel Post)linear foot$33.00$30.00 – $40.00394
VEH Sig Sec (12")LED(Red)each$331.13$280.25 – $390.00393
Remov Str (Set)each$511.88$350.00 – $850.00389
Riprap (Stone Protection)(18 in)cubic yard$200.00$165.00 – $250.00388
Crash Cush Atten (Move & Reset)each$1,588$1,023 – $2,500384
Set (TY II) (24 in) (RCP) (6: 1) (P)each$2,120$1,619 – $2,650384
Set (TY II) (18 in) (RCP) (6: 1) (P)each$1,425$1,045 – $1,985379
Bonding Coursegallon$4.00$3.25 – $5.65372
In SM RD SN Sup&Am TYS80(1)SA(U)each$1,145$1,000 – $1,313371
Condt (PVC) (Sch 80) (2") (Bore)linear foot$27.00$20.00 – $35.00359
Cementton$250.00$216.75 – $300.00352
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)linear foot$0.83$0.66 – $1.16352
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)linear foot$0.8$0.66 – $1.10341
Crash Cush Atten (INSTL)(S)(N)(TL3)each$9,150$8,000 – $10,800339
Excavation (Roadway)cubic yard$20.32$15.00 – $32.60314
Elim EXT PAV MRK & Mrks (4")linear foot$0.71$0.45 – $1.13273
8" Gate Valveeach$2,597$2,300 – $3,200235
Litter Removalacre$20.00$15.00 – $25.00223
Prefab PAV MRK TY C (W) (arrow)each$250.00$213.15 – $298.45218
Elim EXT PAV MRK & Mrks (24")linear foot$4.00$2.69 – $6.00213
Removing Conc (riprap)square yard$30.00$15.36 – $50.00197
Topsoilcubic yard$36.40$28.00 – $61.0586
Concrete Collareach$898.62$512.50 – $1,00070
Hydrated Limeton$320.00$252.62 – $370.0028
Inlet Protectioneach$225.00$150.00 – $250.0024
Concrete Curblinear foot$35.98$35.00 – $53.0021