| Biodegradable erosion control logs (remove) | linear foot | $1.33 | $1.00 – $2.84 | 36 | Nov 4, 2026, line 86 ↗ |
| Reflective pavement marker type ii-a-a | each | $5.75 | $4.03 – $9.50 | 35 | Nov 4, 2026, line 165 ↗ |
| Excavation (Roadway) | cubic yard | $17.20 | $10.00 – $30.00 | 29 | Aug 2, 2024, TxDOT request R075975-102926 · Bid_Tab_FY24 · let 2024-08-02 ↗ |
| Reflective pavement marking type i (w)8 inch(solid)(100mil) | linear foot | $1.20 | $0.97 – $1.75 | 27 | Nov 4, 2026, line 146 ↗ |
| Reflective pavement marking type i (w)24 inch(solid)(100mil) | linear foot | $7.00 | $6.72 – $10.00 | 27 | Nov 4, 2026, line 148 ↗ |
| Biodegradable erosion control logs (install) (12 inch) | linear foot | $5.12 | $4.70 – $6.00 | 26 | Nov 4, 2026, line 85 ↗ |
| In small road sign support&assembly type10bwg(1)sa(p) | each | $668.00 | $650.00 – $800.00 | 25 | Nov 4, 2026, line 128 ↗ |
| Elim ext pavement marking & mrks (4 inch) | linear foot | $1.00 | $0.55 – $1.20 | 25 | Aug 2, 2024, TxDOT request R075975-102926 · Bid_Tab_FY24 · let 2024-08-02 ↗ |
| Elim ext pavement marking & mrks (24 inch) | linear foot | $4.00 | $3.04 – $6.11 | 24 | Aug 2, 2024, TxDOT request R075975-102926 · Bid_Tab_FY24 · let 2024-08-02 ↗ |
| Rock Filter Dams (Remove) | linear foot | $12.00 | $10.00 – $16.50 | 24 | Nov 4, 2026, line 80 ↗ |
| Temporary sediment control fence (remove) | linear foot | $1.00 | $0.825 – $1.02 | 24 | Nov 4, 2026, line 84 ↗ |
| Drill seed (temporary)(warm or cool) | square yard | $0.205 | $0.107 – $0.458 | 24 | Aug 2, 2024, TxDOT request R075975-102926 · Bid_Tab_FY24 · let 2024-08-02 ↗ |
| Temporary sediment control fence (install) | linear foot | $4.00 | $3.95 – $4.50 | 23 | Nov 4, 2026, line 83 ↗ |
| Portable Changeable Message Sign | each | $18,000 | $10,375 – $21,000 | 23 | Nov 4, 2026, line 215 ↗ |
| Pavement Sealer (arrow) | each | $47.99 | $22.00 – $74.78 | 23 | Aug 2, 2024, TxDOT request R075975-102926 · Bid_Tab_FY24 · let 2024-08-02 ↗ |
| Pedestrian signal section (led)(countdown) | each | $875.50 | $736.07 – $1,365 | 22 | Nov 4, 2026, line 188 ↗ |
| Reflective pavement marking type i (w)12 inch(solid)(100mil) | linear foot | $4.58 | $3.81 – $5.25 | 22 | Nov 4, 2026, line 147 ↗ |
| Reflective pavement marking type i (y)6 inch(solid)(100mil) | linear foot | $0.6 | $0.515 – $0.8 | 22 | Nov 4, 2026, line 159 ↗ |
| Elim ext pavement marking & mrks (arrow) | each | $65.00 | $41.25 – $105.25 | 22 | Aug 2, 2024, TxDOT request R075975-102926 · Bid_Tab_FY24 · let 2024-08-02 ↗ |
| Guardrail End Treatment (Remove) | each | $250.00 | $206.25 – $343.25 | 22 | Jul 2, 2026, line 91 ↗ |
| Reflective pavement marking type i (w)6 inch(solid)(100mil) | linear foot | $0.6 | $0.51 – $0.8 | 21 | Nov 4, 2026, line 158 ↗ |
| Drill shaft (trf signal pole) (36 in) | linear foot | $550.00 | $401.00 – $700.00 | 21 | Nov 4, 2026, line 28 ↗ |
| Drill shaft (trf signal pole) (48 in) | linear foot | $710.00 | $545.00 – $850.00 | 21 | Nov 4, 2026, line 29 ↗ |
| Pedestrian pole assembly | each | $4,000 | $3,000 – $4,500 | 21 | Nov 4, 2026, line 205 ↗ |
| Reflective pavement marking type i (w)(arrow)(100mil) | each | $185.00 | $130.00 – $215.70 | 21 | Oct 6, 2026, line 85 ↗ |
| Reflective pavement marking type i (w)(word)(100mil) | each | $230.00 | $160.00 – $275.00 | 21 | Oct 6, 2026, line 86 ↗ |
| Compost manuf topsoil (4 inch) | square yard | $2.00 | $1.29 – $4.00 | 21 | Nov 4, 2026, line 14 ↗ |
| Construction exits (install) (type 1) | square yard | $33.00 | $25.00 – $35.00 | 21 | Nov 4, 2026, line 81 ↗ |
| Construction Exits (Remove) | square yard | $10.00 | $7.00 – $10.00 | 21 | Nov 4, 2026, line 82 ↗ |
| Trf signal cbl (type c)(12 awg)(2 conductor) | linear foot | $2.55 | $2.00 – $3.30 | 21 | Nov 4, 2026, line 195 ↗ |
| Ground box type c (162911)w/apron | each | $2,045 | $1,731 – $2,213 | 20 | Nov 4, 2026, line 124 ↗ |
| Excavation (roadway) | cubic yard | $19.50 | $17.24 – $29.50 | 20 | Nov 4, 2026, line 12 ↗ |
| Remove str (inlet) | each | $1,000 | $665.00 – $1,049 | 20 | Oct 6, 2026, line 49 ↗ |
| Remove str (set) | each | $158.50 | $100.00 – $462.50 | 20 | Nov 4, 2026, line 67 ↗ |
| Pavement sealer 24 inch | linear foot | $2.00 | $1.21 – $4.00 | 20 | Aug 2, 2024, TxDOT request R075975-102926 · Bid_Tab_FY24 · let 2024-08-02 ↗ |
| Tack Coat | gallon | $5.12 | $2.38 – $11.00 | 20 | Nov 4, 2026, line 21 ↗ |
| Pavement sealer 8 inch | linear foot | $0.54 | $0.28 – $1.00 | 20 | Aug 2, 2024, TxDOT request R075975-102926 · Bid_Tab_FY24 · let 2024-08-02 ↗ |
| Pavement Sealer (word) | each | $57.50 | $27.95 – $86.93 | 20 | Aug 2, 2024, TxDOT request R075975-102926 · Bid_Tab_FY24 · let 2024-08-02 ↗ |
| Elim ext pavement marking & mrks (8 inch) | linear foot | $1.30 | $0.742 – $2.04 | 20 | Aug 2, 2024, TxDOT request R075975-102926 · Bid_Tab_FY24 · let 2024-08-02 ↗ |
| Port ctb (fur & install)(f-shape)(type 1) | linear foot | $39.00 | $18.00 – $53.94 | 20 | Nov 4, 2026, line 88 ↗ |
| Rc pipe (class iii)(24 in) | linear foot | $95.50 | $80.00 – $125.00 | 19 | Nov 4, 2026, line 39 ↗ |
| Set (type ii) (24 in) (reinforced concrete pipe) (6: 1) (p) | each | $1,720 | $1,425 – $2,600 | 19 | Nov 4, 2026, line 66 ↗ |
| Reflective pavement marker type ii-c-r | each | $6.75 | $5.00 – $10.08 | 19 | Nov 4, 2026, line 166 ↗ |
| TMA (Mobile Operation) | hour | $75.00 | $42.50 – $150.00 | 19 | Nov 4, 2026, line 76 ↗ |
| SP Mixes Sp-c Sac-b PG64-22 | ton | $139.00 | $126.70 – $160.00 | 19 | Oct 6, 2026, line 23 ↗ |
| Reflective pavement marker type i-c | each | $4.50 | $4.00 – $6.03 | 19 | Nov 4, 2026, line 164 ↗ |
| Rock filter dams (install) (type 3) | linear foot | $65.00 | $55.00 – $79.50 | 19 | Nov 4, 2026, line 79 ↗ |
| In small road sign support&assembly type10bwg(1)sa(t) | each | $795.00 | $706.50 – $840.50 | 18 | Nov 4, 2026, line 129 ↗ |
| Wk zn pavement marking sht terminal (tab)type y-2 | each | $2.00 | $1.52 – $2.45 | 18 | Oct 6, 2026, line 81 ↗ |
| Trench Excavation Protection | linear foot | $8.68 | $5.00 – $14.56 | 18 | Nov 4, 2026, line 26 ↗ |
| Cement stabilized backfill | cubic yard | $245.00 | $203.75 – $265.00 | 18 | Oct 6, 2026, line 26 ↗ |
| Riprap (Stone Protection)(12 in) | cubic yard | $265.00 | $180.00 – $300.00 | 17 | Oct 6, 2026, line 31 ↗ |
| Electrical conductor (no.8) insulated | linear foot | $2.15 | $1.86 – $2.81 | 16 | Nov 4, 2026, line 119 ↗ |
| Rc pipe (class iii)(18 in) | linear foot | $64.00 | $50.00 – $92.75 | 16 | Nov 4, 2026, line 38 ↗ |
| Electrical conductor (no.6) bare | linear foot | $2.90 | $1.90 – $3.04 | 16 | Nov 4, 2026, line 120 ↗ |
| Pavement surface preparation for marking (8 inch) | linear foot | $0.37 | $0.175 – $0.868 | 16 | Nov 4, 2026, line 173 ↗ |
| Electrical conductor (no.6) insulated | linear foot | $3.00 | $2.34 – $3.58 | 16 | Nov 4, 2026, line 121 ↗ |
| Rock filter dams (install) (type 2) | linear foot | $40.00 | $36.00 – $50.00 | 16 | Nov 4, 2026, line 78 ↗ |
| Riprap (Mow Strip)(4 in) | cubic yard | $707.50 | $659.00 – $784.41 | 16 | Sep 3, 2026, line 3 ↗ |
| Guardrail End Treatment (Install) | each | $3,025 | $2,975 – $3,110 | 15 | Jul 2, 2026, line 90 ↗ |
| Remove str (headwall) | each | $1,000 | $800.00 – $2,065 | 15 | Nov 4, 2026, line 69 ↗ |
| Cut & restoring pavement | square yard | $150.00 | $82.50 – $200.00 | 15 | Oct 6, 2026, line 25 ↗ |
| Reflective pavement marking type i (w)6 inch(dot)(100mil) | linear foot | $1.80 | $1.00 – $2.15 | 15 | Nov 4, 2026, line 145 ↗ |
| Driveway (acp) | square yard | $69.00 | $62.50 – $84.84 | 15 | Oct 6, 2026, line 69 ↗ |
| Riprap (concrete)(4 in) | cubic yard | $800.00 | $594.33 – $982.00 | 15 | Oct 6, 2026, line 29 ↗ |
| Conduit (pvc) (sch 40) (2 inch) | linear foot | $19.50 | $14.78 – $21.82 | 14 | Nov 4, 2026, line 112 ↗ |
| Flowable Backfill | cubic yard | $272.50 | $250.00 – $375.00 | 14 | Oct 6, 2026, line 27 ↗ |
| Remove Metal Beam Guard Fence | linear foot | $2.50 | $2.00 – $3.81 | 14 | Oct 6, 2026, line 72 ↗ |
| Conduit (pvc) (sch 80) (2 inch) | linear foot | $22.70 | $19.21 – $24.91 | 14 | Nov 4, 2026, line 116 ↗ |
| Backfill (type a or b) | station | $300.00 | $262.00 – $411.50 | 14 | Oct 6, 2026, line 7 ↗ |
| Blading | station | $300.00 | $132.50 – $345.50 | 14 | Oct 6, 2026, line 8 ↗ |
| Biodegradable erosion control logs (install) (18 inch) | linear foot | $7.25 | $6.17 – $11.72 | 14 | Nov 3, 2026, line 8 ↗ |
| Mailbox install-s (tww-post) type 4 | each | $235.00 | $226.25 – $305.00 | 14 | Oct 6, 2026, line 73 ↗ |
| In small road sign support&assembly tys80(1)sa(u-bm) | each | $1,269 | $1,000 – $1,500 | 13 | Nov 4, 2026, line 131 ↗ |
| Rc pipe (class iii)(30 in) | linear foot | $120.00 | $115.00 – $140.00 | 13 | Nov 4, 2026, line 40 ↗ |
| Rc pipe (class iii)(36 in) | linear foot | $175.00 | $160.00 – $195.00 | 13 | Nov 4, 2026, line 41 ↗ |
| Set (type ii) (18 in) (reinforced concrete pipe) (6: 1) (p) | each | $900.00 | $762.00 – $1,500 | 13 | Oct 6, 2026, line 46 ↗ |
| Vehicle signal section (12 inch)led(grn) | each | $365.00 | $335.00 – $391.76 | 13 | Nov 4, 2026, line 182 ↗ |
| Vehicle signal section (12 inch)led(yellow) | each | $365.00 | $335.00 – $391.76 | 13 | Nov 4, 2026, line 184 ↗ |
| Vehicle signal section (12 inch)led(red) | each | $365.00 | $335.00 – $391.76 | 13 | Nov 4, 2026, line 186 ↗ |