| Thermoplastic, Standard, White | linear foot | $6.15 | $4.70 – $7.79 | 38 | Mar 25, 2026, Open bid tab, T1928 ↗ |
| Milling Existing Asphalt | square yard | $5.17 | $2.97 – $10.04 | 34 | Mar 25, 2026, Open bid tab, T1928 ↗ |
| Paint pavement marking | linear foot | $1.86 | $1.65 – $2.53 | 29 | Aug 27, 2025, Open bid tab, T1918 ↗ |
| Raised Pavement Marker, Type B | each | $5.01 | $4.08 – $5.35 | 24 | Mar 25, 2026, Open bid tab, T1928 ↗ |
| Concrete Sidewalk and | square yard | $90.00 | $78.47 – $108.02 | 23 | Mar 25, 2026, Open bid tab, T1928 ↗ |
| Multi-column Ground Sign | each | $6,170 | $2,018 – $8,405 | 23 | Aug 27, 2025, Open bid tab, T1918 ↗ |
| Conduit, Furnish & Install, Open | linear foot | $23.83 | $17.00 – $28.75 | 21 | Mar 25, 2026, Open bid tab, T1928 ↗ |
| Conduit, Furnish & Install | linear foot | $37.20 | $30.76 – $44.69 | 20 | Mar 25, 2026, Open bid tab, T1928 ↗ |
| Pull & splice box, f&i, 13 inch x 24 inch | each | $1,871 | $1,604 – $1,979 | 20 | Mar 25, 2026, Open bid tab, T1928 ↗ |
| Asphalt Concrete Friction | ton | $203.90 | $193.34 – $217.22 | 17 | Mar 25, 2026, Open bid tab, T1928 ↗ |
| Pipe Culvert,Optional | linear foot | $191.50 | $144.52 – $247.11 | 16 | Aug 27, 2025, Open bid tab, T1918 ↗ |
| Thermoplastic, Preformed | each | $247.91 | $137.61 – $350.00 | 16 | Aug 27, 2025, Open bid tab, T1918 ↗ |
| Thermoplastic, Standard, White | each | $92.50 | $77.91 – $150.61 | 16 | Mar 25, 2026, Open bid tab, T1928 ↗ |
| Embankment | cubic yard | $58.12 | $41.63 – $92.90 | 14 | Mar 25, 2026, Open bid tab, T1928 ↗ |
| Sediment Barrier | linear foot | $1.56 | $1.25 – $1.98 | 14 | Mar 25, 2026, Open bid tab, T1928 ↗ |
| Regular Excavation | cubic yard | $62.09 | $42.50 – $140.15 | 14 | Mar 25, 2026, Open bid tab, T1928 ↗ |
| Performance Turf, Sod | square yard | $5.30 | $4.72 – $6.87 | 14 | Mar 25, 2026, Open bid tab, T1928 ↗ |
| Paint pavement marking | each | $38.50 | $32.30 – $50.55 | 13 | Aug 27, 2025, Open bid tab, T1918 ↗ |
| Remove of existing concrete | square yard | $40.74 | $30.80 – $76.93 | 13 | Mar 25, 2026, Open bid tab, T1928 ↗ |
| Inlet Protection System | each | $180.54 | $121.56 – $238.00 | 12 | Mar 25, 2026, Open bid tab, T1928 ↗ |
| Mowing | acre | $85.00 | $73.50 – $273.26 | 12 | Mar 25, 2026, Open bid tab, T1928 ↗ |
| Guardrail End Treatment | each | $3,277 | $1,506 – $3,686 | 12 | Jul 30, 2025, Open bid tab, T1921 ↗ |
| Litter remove | acre | $60.00 | $47.00 – $153.68 | 12 | Mar 25, 2026, Open bid tab, T1928 ↗ |