| Milling Existing Asphalt | square yard | $5.21 | $3.44 – $9.93 | 76 | Jul 29, 2026, Open bid tab, T7619 ↗ |
| Paint pavement marking | linear foot | $1.73 | $1.38 – $2.10 | 60 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Thermoplastic, Standard, White | linear foot | $6.00 | $4.87 – $6.96 | 60 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Conduit, Furnish & Install | linear foot | $44.05 | $38.25 – $57.45 | 50 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Pipe Culvert,Optional | linear foot | $300.00 | $183.00 – $445.00 | 49 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Conduit, Furnish & Install, Open | linear foot | $25.50 | $19.75 – $39.42 | 43 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Thermoplastic, Preformed | each | $317.00 | $204.53 – $593.43 | 41 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Pull & splice box, f&i, 13 inch x 24 inch | each | $1,600 | $1,493 – $1,810 | 39 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Raised Pavement Marker, Type B | each | $4.63 | $4.00 – $5.66 | 39 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Concrete Sidewalk and | square yard | $98.00 | $82.00 – $127.00 | 37 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Paint pavement marking | each | $39.93 | $37.00 – $46.27 | 36 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Thermoplastic, Standard, White | each | $104.84 | $74.91 – $181.25 | 36 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Asphalt Concrete Friction | ton | $250.00 | $203.40 – $280.00 | 33 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Vehicle Detection System | each | $10,000 | $2,761 – $13,403 | 33 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Steel Mast Arm Assembly, Furnish | each | $92,000 | $83,781 – $104,500 | 32 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Inlet Protection System | each | $150.00 | $112.11 – $198.95 | 31 | Jul 29, 2026, Open bid tab, T7619 ↗ |
| Embankment | cubic yard | $46.66 | $15.31 – $71.12 | 29 | Jul 29, 2026, Open bid tab, T7619 ↗ |
| Remove of existing concrete | square yard | $50.00 | $33.97 – $80.28 | 27 | Jul 29, 2026, Open bid tab, T7619 ↗ |
| Litter remove | acre | $75.00 | $50.00 – $141.20 | 27 | Jul 29, 2026, Open bid tab, T7619 ↗ |
| Performance Turf, Sod | square yard | $7.33 | $5.34 – $9.62 | 26 | Jul 29, 2026, Open bid tab, T7619 ↗ |
| Detectable Warnings | square foot | $31.94 | $28.00 – $44.00 | 25 | Aug 18, 2026, Open bid tab, contract 26-c-00023-iitemized-bidtabu ↗ |
| Sediment Barrier | linear foot | $2.50 | $1.50 – $4.40 | 25 | Jul 29, 2026, Open bid tab, T7619 ↗ |
| Regular Excavation | cubic yard | $49.27 | $28.73 – $72.67 | 25 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Fiber Optic Connection, Install | each | $68.37 | $60.34 – $114.01 | 24 | May 20, 2026, Open bid tab, T7595 ↗ |
| Superpave asphalt concrete | ton | $202.00 | $156.15 – $220.00 | 23 | Jul 29, 2026, Open bid tab, T7619 ↗ |
| Retroreflective Sign Strip | each | $105.70 | $85.85 – $136.83 | 23 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Prestressed Concrete Pole, F&I | each | $2,663 | $2,302 – $3,130 | 23 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Traffic Control Officer | hour | $91.50 | $85.57 – $95.08 | 23 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Fiber Optic Cable Locator | day | $276.75 | $188.70 – $337.50 | 22 | Jul 29, 2026, Open bid tab, T7619 ↗ |
| Thermoplastic, Preformed | linear foot | $16.50 | $15.85 – $18.27 | 21 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Mitered End Section, Optional | each | $2,609 | $1,950 – $3,142 | 21 | May 20, 2026, Open bid tab, T7595 ↗ |
| Vehicle Detection System- Video | each | $11,000 | $6,223 – $28,100 | 21 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Pipe Culvert, Opt Material | linear foot | $489.50 | $322.25 – $960.79 | 20 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Type B Stabilization | square yard | $41.25 | $30.58 – $60.00 | 20 | Jul 29, 2026, Open bid tab, T7619 ↗ |
| Guardrail End Treatment | each | $3,064 | $2,090 – $3,698 | 19 | Jul 29, 2026, Open bid tab, T7619 ↗ |
| Concrete Curb & Gutter, Type F | linear foot | $53.68 | $46.58 – $60.50 | 19 | Aug 18, 2026, Open bid tab, contract 26-c-00023-iitemized-bidtabu ↗ |
| Sign Panel, Remove, up to 12 SF | each | $45.00 | $28.63 – $56.83 | 18 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Lighting Conductors, F&I | linear foot | $2.90 | $2.58 – $4.00 | 18 | May 20, 2026, Open bid tab, T7595 ↗ |
| Electrical Service Wire, Furnish | linear foot | $10.75 | $8.73 – $13.00 | 18 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Itsfm Location Documentation | each | $2,662 | $2,318 – $3,425 | 18 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Paint pavement marking | square foot | $5.10 | $4.40 – $5.66 | 17 | May 20, 2026, Open bid tab, T7587 ↗ |
| Electrical Service Disconnect | each | $1,550 | $1,150 – $1,798 | 17 | May 20, 2026, Open bid tab, T7595 ↗ |
| Pedestrian Detector, Furnish & | each | $440.92 | $352.92 – $569.76 | 17 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Managed Field Ethernet Switch | each | $5,000 | $2,700 – $5,804 | 17 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Uninterruptible Power Supply | each | $11,600 | $5,800 – $14,500 | 17 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Traffic Monitoring Site | each | $2,510 | $1,939 – $2,956 | 16 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Itsfm Subsurface | mile | $3,920 | $3,484 – $4,558 | 15 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Aluminum signal pole, pedestal | each | $2,798 | $2,335 – $2,941 | 14 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Thermoplastic, Standard | linear foot | $5.36 | $4.53 – $7.53 | 14 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Superpave asphalt concrete | ton | $195.22 | $162.58 – $251.50 | 14 | Jun 10, 2026, Open bid tab, T7534 ↗ |
| Pipe Culvert, Optional Material | linear foot | $251.82 | $175.00 – $809.04 | 13 | May 20, 2026, Open bid tab, T7595 ↗ |