Cost by state
Construction unit costs in Florida
Median awarded unit prices for the 36 most-bid items on Florida public projects, from winning bids in agency bid tabulations.
| Item | Per | Median | Middle half | Winning bids |
|---|---|---|---|---|
| Thermoplastic, Standard, White | linear foot | $6.21 | $4.71 – $8.58 | 1,200 |
| Milling Existing Asphalt | square yard | $4.00 | $2.72 – $7.00 | 1,191 |
| Painted Pavement Markings | linear foot | $2.20 | $1.70 – $3.30 | 1,081 |
| Raised Pavement Marker, Type B | each | $5.10 | $4.50 – $6.15 | 787 |
| Conduit, Furnish & Install | linear foot | $40.00 | $31.00 – $50.02 | 787 |
| Thermoplastic, Standard, White | each | $120.00 | $88.00 – $200.00 | 701 |
| Concrete Sidewalk and | square yard | $96.47 | $75.83 – $131.36 | 685 |
| Pull & Splice Box, F&I, 13" x 24" | each | $1,700 | $1,439 – $1,949 | 648 |
| Asphalt Concrete Friction | ton | $201.57 | $176.37 – $250.00 | 586 |
| Conduit, Furnish & Install, Open | linear foot | $21.90 | $16.75 – $29.00 | 557 |
| Pipe Culvert,Optional | linear foot | $250.00 | $167.00 – $400.00 | 549 |
| Painted Pavement Markings | each | $52.00 | $42.00 – $77.00 | 547 |
| Thermoplastic, Preformed | each | $225.00 | $159.37 – $350.00 | 536 |
| Performance Turf, Sod | square yard | $6.10 | $4.00 – $10.00 | 469 |
| Litter Removal | acre | $67.00 | $39.19 – $142.42 | 456 |
| Mowing | acre | $95.10 | $50.00 – $200.00 | 450 |
| Inlet Protection System | each | $180.90 | $137.42 – $250.00 | 448 |
| Removal of Existing Concrete | square yard | $43.19 | $30.00 – $70.00 | 430 |
| Steel Mast Arm Assembly, Furnish | each | $90,000 | $75,000 – $116,907 | 415 |
| Sediment Barrier | linear foot | $3.32 | $2.00 – $5.45 | 407 |
| Traffic Control Officer | hour | $95.00 | $81.25 – $110.00 | 389 |
| Detectable Warnings | square foot | $40.23 | $32.00 – $49.93 | 368 |
| Mitered End Section, Optional | each | $3,536 | $2,800 – $5,300 | 366 |
| Thermoplastic, Preformed | linear foot | $17.43 | $15.40 – $20.00 | 358 |
| Prestressed Concrete Pole, F&I | each | $2,702 | $2,342 – $3,311 | 352 |
| Regular Excavation | cubic yard | $38.75 | $20.00 – $75.00 | 332 |
| Concrete Curb & Gutter, Type F | linear foot | $53.59 | $42.44 – $71.51 | 330 |
| Thermoplastic, Standard | linear foot | $5.83 | $4.80 – $7.50 | 328 |
| Guardrail End Treatment | each | $3,270 | $2,000 – $3,860 | 321 |
| Type B Stabilization | square yard | $22.51 | $9.78 – $37.25 | 315 |
| Superpave Asphaltic Concrete | ton | $170.93 | $148.32 – $216.93 | 307 |
| Electrical Service Wire, Furnish | linear foot | $10.22 | $7.95 – $13.46 | 300 |
| Painted Pavement Markings | square foot | $5.40 | $4.24 – $7.64 | 300 |
| Pedestrian Detector, Furnish & | each | $533.09 | $401.25 – $1,077 | 299 |
| Superpave Asphaltic Conc | ton | $201.00 | $150.00 – $298.87 | 284 |
| Embankment | cubic yard | $42.00 | $20.11 – $75.11 | 282 |
Prices by county in Florida
- Alachua County: 12 items
- Bay County: 16 items
- Brevard County: 41 items
- Broward County: 73 items
- Clay County: 4 items
- Columbia County: 2 items
- Duval County: 70 items
- Escambia County: 32 items
- Flagler County: 1 items
- Hillsborough County: 51 items
- Indian River County: 2 items
- Jackson County: 3 items
- Lake County: 5 items
- Lee County: 13 items
- Leon County: 14 items
- Levy County: 2 items
- Manatee County: 10 items
- Marion County: 8 items
- Miami-dade County: 72 items
- Monroe County: 2 items
- Nassau County: 3 items
- Okaloosa County: 6 items
- Orange County: 38 items
- Palm Beach County: 43 items
- Pasco County: 9 items
- Pinellas County: 25 items
- Polk County: 23 items
- Sarasota County: 4 items
- St. Johns County: 3 items
- St. Lucie County: 3 items
- Suwannee County: 1 items
- Volusia County: 22 items
- Walton County: 1 items
Agencies in Florida
- City of Tampa: 6,221 winning prices
- FDOT: 329,989 winning prices