Construction unit costs in Bay County, FL

Median awarded unit prices for 16 items on public projects in Bay County, from winning bids in agency bid tabulations. Each item page lists its source documents.

Cost by state › Florida › Bay County

ItemPerMedianMiddle halfWinning bidsLatest source document
Pipe Culvert,Optionallinear foot$208.50$133.81 – $300.0037Sep 30, 2026, Open bid tab, T3908 ↗
Paint pavement markinglinear foot$2.58$2.08 – $3.8036Mar 31, 2026, Open bid tab, T3845 ↗
Steel Mast Arm Assembly, Furnisheach$107,310$90,891 – $129,57633Mar 31, 2026, Open bid tab, T3845 ↗
Concrete Sidewalk andsquare yard$131.71$94.69 – $162.4128Sep 30, 2026, Open bid tab, T3908 ↗
Pipe Culvert, Opt Materiallinear foot$351.23$258.50 – $478.2826Mar 31, 2026, Open bid tab, T3845 ↗
Thermoplastic, Standard, Whiteeach$189.35$126.79 – $250.0025Mar 31, 2026, Open bid tab, T3845 ↗
Conduit, Furnish & Installlinear foot$34.72$25.81 – $40.9324Mar 31, 2026, Open bid tab, T3845 ↗
Milling Existing Asphaltsquare yard$4.15$2.62 – $6.5124Mar 31, 2026, Open bid tab, T3845 ↗
Performance Turf, Sodsquare yard$5.87$4.32 – $9.5524Sep 30, 2026, Open bid tab, T3908 ↗
Pipe Culvert, Optional Materiallinear foot$183.00$159.50 – $227.2223Mar 31, 2026, Open bid tab, T3845 ↗
Sediment Barrierlinear foot$5.36$3.86 – $9.7222Sep 30, 2026, Open bid tab, T3908 ↗
Pull & splice box, f&i, 13 inch x 24 incheach$1,100$1,052 – $1,28121Mar 31, 2026, Open bid tab, T3845 ↗
Litter removeacre$100.00$74.20 – $270.6020Mar 31, 2026, Open bid tab, T3845 ↗
Thermoplastic, Standard, Whitelinear foot$7.50$6.27 – $11.9119Mar 31, 2026, Open bid tab, T3845 ↗
Mitered End Section, Optionaleach$3,900$3,000 – $5,40017Mar 31, 2026, Open bid tab, T3845 ↗
Raised Pavement Marker, Type Beach$5.80$4.58 – $7.4714Sep 30, 2026, Open bid tab, T3908 ↗