Skip to content
Hubstake

Street Lighting · awarded bid prices · Hillsborough County

Prestressed Concrete Pole, F&I: cost per each in Hillsborough County, FL

The median awarded price is $2,663 per each, from 23 winning bids on 14 public projects in Hillsborough County, FL (2024–2026). Half of the awarded prices fall between $2,302 and $3,130.

Cost by state › Florida › Hillsborough County › Prestressed Concrete Pole, F&I

$2,663median per each
$2,302 – $3,130middle half (25th–75th percentile)
23winning bids, 14 source documents
2024–2026lettings covered (last 3 years)

Winning bids only, as printed in the agencies' bid tabulations (FDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.

Trend

The median awarded price went from $1,609 in 2021 to $4,940 in 2026 (+207%).

YearMedian per eachWinning bids
2021$1,6096
2024$2,45014
2026$4,9405

Most recent source documents

LettingAgencyQuantityAwarded unit priceSource
Jun 10, 2026FDOT13 EA$4,940Open bid tab, T7534 ↗
May 20, 2026FDOT1 EA$3,194Open bid tab, T7595 ↗
Apr 29, 2026FDOT4 EA$3,065Open bid tab, T7611 ↗
Dec 3, 2025FDOT2 EA$21,300Open bid tab, T7559 ↗
Jul 30, 2025FDOT16 EA$1,584Open bid tab, T7574 ↗

The same item across Florida: statewide figures. See every awarded price for this item on the Prestressed Concrete Pole, F&I item page.

Related items in Hillsborough County