Skip to content
Hubstake

Structures · awarded bid prices · Hidalgo County

Remove str (pipe): cost per linear foot in Hidalgo County, TX

Listed by the agency as “Remov Str (Pipe)”.

The median awarded price is $10.00 per linear foot, from 18 winning bids on 18 public projects in Hidalgo County, TX (2024–2026). Half of the awarded prices fall between $8.62 and $16.50.

Cost by state › Texas › Hidalgo County › Remov Str (Pipe)

$10.00median per linear foot
$8.62 – $16.50middle half (25th–75th percentile)
18winning bids, 18 source documents
2024–2026lettings covered (last 3 years)

Winning bids only, as printed in the agencies' bid tabulations (TxDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.

Trend

The median awarded price went from $9.00 in 2019 to $18.00 in 2026 (+100%).

YearMedian per linear footWinning bids
2019$9.005
2022$6.005
2025$10.506
2026$18.009

Most recent source documents

LettingAgencyQuantityAwarded unit priceSource
Oct 7, 2026TxDOT105 LF$50.00line 28 ↗
Aug 5, 2026TxDOT104 LF$25.00line 21 ↗
Aug 5, 2026TxDOT2164 LF$10.00line 50 ↗
Jun 4, 2026TxDOT32 LF$18.00line 15 ↗
Jun 2, 2026TxDOT960 LF$30.30line 56 ↗