Skip to content
Hubstake

Structures · awarded bid prices · Hidalgo County

Downstream Anchor Terminal Section: cost per each in Hidalgo County, TX

The median awarded price is $1,515 per each, from 15 winning bids on 14 public projects in Hidalgo County, TX (2024–2026). Half of the awarded prices fall between $1,400 and $1,975.

Cost by state › Texas › Hidalgo County › Downstream Anchor Terminal Section

$1,515median per each
$1,400 – $1,975middle half (25th–75th percentile)
15winning bids, 14 source documents
2024–2026lettings covered (last 3 years)

Winning bids only, as printed in the agencies' bid tabulations (TxDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.

Trend

The median awarded price went from $1,800 in 2024 to $1,483 in 2025 (-18%).

YearMedian per eachWinning bids
2024$1,8005
2025$1,4837

Most recent source documents

LettingAgencyQuantityAwarded unit priceSource
May 7, 2026TxDOT6 EA$1,480line 109 ↗
May 7, 2026TxDOT1 EA$1,510line 115 ↗
Apr 7, 2026TxDOT1 EA$1,665line 16 ↗
Dec 2, 2025TxDOT10 EA$1,515line 18 ↗
Sep 5, 2025TxDOT6 EA$1,483line 16 ↗

The same item across Texas: statewide figures. See every awarded price for this item on the Downstream Anchor Terminal Section item page.

Related items in Hidalgo County