| Temporary info signing | square foot | $20.00 | $16.00 – $26.00 | 265 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Protective Coat | square yard | $1.00 | $0.995 – $2.00 | 223 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Sidewalk remove | square foot | $3.00 | $2.00 – $4.00 | 222 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Thpl Pvt Mk Line 4 | linear foot | $0.94 | $0.75 – $1.40 | 222 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Earth Excavation | cubic yard | $62.00 | $45.00 – $90.00 | 217 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Non Spl Waste Disposl | cubic yard | $95.00 | $75.00 – $120.00 | 214 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Soil Disposal Analy | each | $1,450 | $1,150 – $1,675 | 214 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Pc concrete sidewalk 5 | square foot | $10.86 | $9.25 – $14.03 | 207 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Thpl Pvt Mk Line 12 | linear foot | $3.05 | $2.50 – $4.25 | 207 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Thpl Pvt Mk Line 24 | linear foot | $6.00 | $5.50 – $8.00 | 200 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Thpl Pvt Mk Line 6 | linear foot | $1.35 | $1.10 – $1.90 | 194 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Topsoil F & P 4 | square yard | $6.60 | $5.95 – $12.03 | 187 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Thpl pvt mk ltr & symbol | square foot | $5.85 | $5.25 – $6.59 | 178 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Long joint seal | linear foot | $3.48 | $2.87 – $5.00 | 168 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Pvt marking remove water blast | square foot | $1.85 | $1.20 – $4.00 | 167 | Sep 18, 2026, Open bid tab, 62V85 ↗ |
| Detectable Warnings | square foot | $39.81 | $30.00 – $44.71 | 166 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Raised ref pvt mk remove | each | $15.00 | $10.00 – $23.16 | 163 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Sodding Salt Tolerant | square yard | $21.00 | $14.00 – $35.00 | 157 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Inlet Filters | each | $200.00 | $150.00 – $250.00 | 150 | Sep 18, 2026, Open bid tab, 62V85 ↗ |
| Raised reflective pavement mkr | each | $48.92 | $38.00 – $75.00 | 148 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Combination curb gutter remove | linear foot | $10.00 | $8.00 – $14.00 | 143 | Sep 18, 2026, Open bid tab, 62V85 ↗ |
| Drive pavement remove | square yard | $20.00 | $15.00 – $29.05 | 140 | Sep 18, 2026, Open bid tab, 62W73 ↗ |
| Nitrogen Fert Nutr | pound | $3.00 | $2.75 – $5.00 | 135 | Sep 18, 2026, Open bid tab, 62V85 ↗ |
| Potassium Fert Nutr | pound | $3.00 | $2.75 – $5.00 | 135 | Sep 18, 2026, Open bid tab, 62V85 ↗ |
| Main ex tr signal instal | each | $5,000 | $1,978 – $8,158 | 132 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Undrgrd C Galvs 2 | linear foot | $53.75 | $38.70 – $77.00 | 129 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Drainage Str Cleaned | each | $393.00 | $350.00 – $500.00 | 124 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Fr & Lids Adjust Spl | each | $1,200 | $1,000 – $1,318 | 118 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Hot mix asphalt sc il-9.5 d n50 | ton | $129.27 | $95.00 – $230.00 | 117 | Sep 18, 2026, Open bid tab, 62W73 ↗ |
| Remove & disp uns material | cubic yard | $50.00 | $30.00 – $72.00 | 116 | Sep 18, 2026, Open bid tab, 62V90 ↗ |
| Accessible pedestrian signal | each | $2,175 | $1,760 – $2,584 | 115 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Sign Panel T1 | square foot | $35.00 | $27.50 – $46.42 | 114 | Sep 18, 2026, Open bid tab, 62W73 ↗ |
| Det Loop T1 | linear foot | $30.80 | $24.80 – $39.70 | 112 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Aggregate subgrade improve | cubic yard | $65.00 | $50.00 – $80.00 | 111 | Jul 31, 2026, Open bid tab, 61K19 ↗ |
| Cc&g rmvl replace > 10ft | linear foot | $61.00 | $50.00 – $75.00 | 110 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Hot mix asphalt sc il-9.5 d n70 | ton | $115.00 | $94.34 – $246.00 | 109 | Sep 18, 2026, Open bid tab, 62W73 ↗ |
| Remove elcbl fr con | linear foot | $1.00 | $0.65 – $2.28 | 109 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Drill Ex Handhole | each | $587.00 | $423.25 – $848.50 | 107 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Pavement remove | square yard | $20.00 | $13.50 – $34.96 | 105 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Elcbl C Signal 14 2C | linear foot | $2.65 | $1.90 – $3.89 | 105 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Concrete fdn type a 12d | linear foot | $350.00 | $307.73 – $456.26 | 104 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Elcbl C Egrdc 6 1C | linear foot | $3.49 | $2.82 – $5.06 | 103 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Trench Backfill | cubic yard | $58.50 | $35.00 – $84.00 | 102 | Sep 18, 2026, Open bid tab, 62V90 ↗ |
| Ss Cleaned 12 | linear foot | $3.00 | $2.00 – $5.88 | 102 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Geotech fabric f/gr stabilized | square yard | $3.00 | $2.00 – $4.13 | 100 | Jul 31, 2026, Open bid tab, 61K19 ↗ |
| Elcbl C Signal 14 3C | linear foot | $2.75 | $2.10 – $3.87 | 99 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Combination cc&g tb6.12 | linear foot | $43.30 | $35.00 – $55.27 | 97 | Jul 31, 2026, Open bid tab, 61K19 ↗ |
| Cc&g rmvl replace < = 10 | linear foot | $72.50 | $58.00 – $88.00 | 96 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Temporary erosion control seed | pound | $4.45 | $2.15 – $7.24 | 96 | Sep 18, 2026, Open bid tab, 62V85 ↗ |
| Perimeter erosion bar | linear foot | $3.20 | $2.16 – $4.50 | 92 | Jul 31, 2026, Open bid tab, 61K19 ↗ |
| Pavement marking remove water bl | square foot | $1.35 | $0.875 – $3.60 | 91 | Sep 22, 2023, Open bid tab, 61H30 ↗ |
| Temporary tr signal timing | each | $1,063 | $660.00 – $1,770 | 89 | Jul 31, 2026, Open bid tab, 62X43 ↗ |
| Elcbl C Lead 14 1Pr | linear foot | $2.50 | $1.94 – $3.96 | 89 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Fr & lids t1 class | each | $457.50 | $450.00 – $517.50 | 88 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| P hot mix asphalt bc il-4.75 n50 | ton | $125.00 | $110.00 – $140.00 | 87 | Sep 18, 2026, Open bid tab, 62W73 ↗ |
| Pedestrian sh led 1f bm cdt | each | $754.00 | $653.25 – $945.75 | 86 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Pedestrian signal post 10 ft | each | $1,576 | $1,350 – $1,800 | 85 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Tree Root Pruning | each | $125.00 | $90.00 – $200.00 | 85 | Jul 31, 2026, Open bid tab, 61K85 ↗ |
| Thpl Pvt Mk Line 8 | linear foot | $2.00 | $1.65 – $2.35 | 84 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Fr & Lids Adjust | each | $600.00 | $451.25 – $800.00 | 82 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Man Adjust | each | $660.00 | $550.00 – $900.00 | 81 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Temporary concrete barrier | linear foot | $32.00 | $28.00 – $40.00 | 80 | Jul 31, 2026, Open bid tab, 62T84 ↗ |
| Aggregate subgrade impr 12 | square yard | $21.30 | $17.92 – $30.00 | 78 | Jul 31, 2026, Open bid tab, 61K19 ↗ |
| Reinforced bars, epoxy ctd | pound | $2.58 | $1.80 – $4.00 | 78 | Jul 31, 2026, Open bid tab, 62X43 ↗ |
| Fr & Lids T1 Ol | each | $455.00 | $450.00 – $500.00 | 77 | Sep 18, 2026, Open bid tab, 62V85 ↗ |
| Remove ex handhole | each | $740.00 | $582.54 – $1,311 | 76 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Modified ureth pm line 12 | linear foot | $5.74 | $3.41 – $13.38 | 76 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Pcc driveway pavement 8 | square yard | $105.00 | $92.90 – $126.65 | 75 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Undrgrd C Galvs 4 | linear foot | $89.58 | $71.06 – $110.75 | 74 | Sep 18, 2026, Open bid tab, 62V90 ↗ |
| Cb Adjust | each | $617.50 | $463.06 – $830.00 | 74 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Rebuild Ex Handhole | each | $2,680 | $2,332 – $3,636 | 74 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Phosphorus Fert Nutr | pound | $3.30 | $3.00 – $5.00 | 71 | Sep 18, 2026, Open bid tab, 62V85 ↗ |
| Tree Trunk Protection | each | $150.00 | $100.00 – $200.00 | 71 | Sep 18, 2026, Open bid tab, 62V90 ↗ |
| Pedestrian signal post 5 ft | each | $1,290 | $1,113 – $1,636 | 70 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Hd Handhole | each | $4,910 | $4,081 – $5,941 | 70 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Modified ureth pm line 6 | linear foot | $2.49 | $1.50 – $5.89 | 68 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| Teles steel sin support | linear foot | $20.00 | $17.00 – $22.00 | 67 | Jul 31, 2026, Open bid tab, 62J64 ↗ |
| Concrete fdn type a | linear foot | $375.00 | $336.72 – $441.55 | 67 | Sep 18, 2026, Open bid tab, 62W73 ↗ |
| Remove ex concrete fdn | each | $677.00 | $500.00 – $839.79 | 67 | Sep 18, 2026, Open bid tab, 62V55 ↗ |
| P hot mix asphalt sc sma 9.5 f n80 | ton | $138.62 | $123.88 – $155.75 | 66 | Sep 18, 2026, Open bid tab, 62V55 ↗ |