Construction unit costs in Madison County, IL

Median awarded unit prices for 61 items on public projects in Madison County, from winning bids in agency bid tabulations. Each item page lists its source documents.

Cost by state › Illinois › Madison County

ItemPerMedianMiddle halfWinning bidsLatest source document
Bit Matls Tack Ctpound$2.25$1.51 – $3.0049Jun 12, 2026, Open bid tab, 76R32 ↗
Raised reflective pavement mkreach$60.00$46.10 – $103.7041Jul 31, 2026, Open bid tab, 76V11 ↗
Earth Excavationcubic yard$50.00$31.00 – $72.0037Jun 12, 2026, Open bid tab, 76R32 ↗
Short terminal pavement mkinglinear foot$2.35$1.25 – $3.1437Jul 31, 2026, Open bid tab, 76V11 ↗
Sign Panel T1square foot$33.50$28.33 – $50.0036Jun 12, 2026, Open bid tab, 76R32 ↗
Nitrogen Fert Nutrpound$5.38$2.62 – $10.1534Jun 12, 2026, Open bid tab, 76R32 ↗
Phosphorus Fert Nutrpound$5.38$2.62 – $10.1534Jun 12, 2026, Open bid tab, 76R32 ↗
Potassium Fert Nutrpound$5.38$2.62 – $10.1534Jun 12, 2026, Open bid tab, 76R32 ↗
Pavement removesquare yard$17.75$12.06 – $38.7534Jun 12, 2026, Open bid tab, 76R32 ↗
Combination curb gutter removelinear foot$16.00$11.75 – $23.7531Jun 12, 2026, Open bid tab, 76R32 ↗
Long joint seallinear foot$4.43$3.65 – $6.7531Jun 12, 2026, Open bid tab, 76V17 ↗
Detectable Warningssquare foot$45.95$34.25 – $62.5430Jun 12, 2026, Open bid tab, 97884 ↗
Drive pavement removesquare yard$24.27$17.69 – $30.1130Jun 12, 2026, Open bid tab, 97884 ↗
Inlet & Pipe Protecteach$170.19$86.56 – $290.0029Jun 12, 2026, Open bid tab, 76R32 ↗
Sidewalk removesquare foot$3.25$2.15 – $5.0029Jun 12, 2026, Open bid tab, 76U38 ↗
Protective Coatsquare yard$2.00$1.00 – $4.0029Jun 12, 2026, Open bid tab, 76R32 ↗
Teles steel sin supportlinear foot$19.00$16.25 – $25.2029Jun 12, 2026, Open bid tab, 76R32 ↗
Combination cc&g type b-6.24linear foot$68.50$44.85 – $86.2528Feb 27, 2026, Open bid tab, 97882 ↗
Mulching method 2acre$5,400$3,610 – $7,60027Jun 12, 2026, Open bid tab, 76R32 ↗
Pc concrete sidewalk 4square foot$13.00$9.00 – $19.5027Jun 12, 2026, Open bid tab, 97896 ↗
Trench Backfillcubic yard$60.00$53.88 – $70.7526Apr 24, 2026, Open bid tab, 97840 ↗
Temporary erosion control seedpound$6.00$5.00 – $8.1826Feb 27, 2026, Open bid tab, 97882 ↗
Thpl Pvt Mk Line 24linear foot$15.00$12.27 – $19.0025Jun 12, 2026, Open bid tab, 97884 ↗
Thpl pvt mk ltr & symbolsquare foot$12.68$10.95 – $15.0024Jun 12, 2026, Open bid tab, 76R32 ↗
Thpl Pvt Mk Line 12linear foot$9.70$8.14 – $10.1024Jun 12, 2026, Open bid tab, 97884 ↗
Dowel Bars 1 1/2each$30.00$25.00 – $37.2524Jul 31, 2026, Open bid tab, 76V11 ↗
Thpl Pvt Mk Line 6linear foot$1.80$0.82 – $3.1223Jun 12, 2026, Open bid tab, 76R32 ↗
Non Spl Waste Disposlcubic yard$120.00$64.92 – $177.9823Jun 12, 2026, Open bid tab, 76U38 ↗
Soil Disposal Analyeach$1,428$1,388 – $1,58823Jun 12, 2026, Open bid tab, 76U38 ↗
Pcc driveway pavement 6square yard$140.00$110.65 – $151.5023Jun 12, 2026, Open bid tab, 97884 ↗
Aggregate-temporary accesston$45.00$36.94 – $55.6222Jun 12, 2026, Open bid tab, 97896 ↗
Material transfer deviceton$5.61$5.00 – $6.5622Jun 12, 2026, Open bid tab, 76V17 ↗
Remove inleteach$600.00$480.00 – $1,06521Apr 24, 2026, Open bid tab, 97840 ↗
Concrete curb tblinear foot$67.00$54.00 – $85.0021Apr 24, 2026, Open bid tab, 97840 ↗
Hot mix asphalt shoulderton$140.57$124.71 – $155.8021Jun 12, 2026, Open bid tab, 76V17 ↗
Grdrail Ref Type Aeach$10.50$10.19 – $11.0020Jun 12, 2026, Open bid tab, 76R32 ↗
Incidental hot mix asphalt surfaceton$320.24$293.28 – $427.7120Apr 24, 2026, Open bid tab, 97840 ↗
Saw Cutslinear foot$8.00$5.00 – $9.0020Jul 31, 2026, Open bid tab, 76V11 ↗
Terminal Marker - Daeach$42.00$27.00 – $45.2519Jun 12, 2026, Open bid tab, 76R32 ↗
Thpl Pvt Mk Line 4linear foot$1.30$1.04 – $1.9019Jun 12, 2026, Open bid tab, 97884 ↗
Perimeter erosion barlinear foot$4.25$3.39 – $6.0018Jun 12, 2026, Open bid tab, 76R32 ↗
Storm sew class a 1 12linear foot$100.05$68.80 – $128.3818Apr 24, 2026, Open bid tab, 97840 ↗
Tr Bar Trm T1 Spl Taneach$3,350$3,166 – $3,71218Jun 12, 2026, Open bid tab, 76R32 ↗
Guardrail removelinear foot$6.80$5.38 – $7.5418Jun 12, 2026, Open bid tab, 76R32 ↗
Bit Matls Pr Ctpound$2.48$1.11 – $4.2218Feb 27, 2026, Open bid tab, 97882 ↗
Filter Fabricsquare yard$5.20$4.50 – $8.6017Jun 12, 2026, Open bid tab, 76V17 ↗
Temporary pvt mk line 4 - paintlinear foot$0.01$0.01 – $0.0117Apr 24, 2026, Open bid tab, 97840 ↗
Pcc driveway pavement 8square yard$147.00$142.00 – $158.0017Jun 12, 2026, Open bid tab, 97884 ↗
Hot mix asphalt sc il-9.5 d n70ton$166.50$160.19 – $175.2516Jun 12, 2026, Open bid tab, 97884 ↗
Spbgr type a 6ft postlinear foot$32.00$27.12 – $35.4515Jun 12, 2026, Open bid tab, 76R32 ↗
Traffic bar terminal t6each$4,050$3,731 – $4,55015Jun 12, 2026, Open bid tab, 76R32 ↗
Welded wire reinforcedsquare yard$19.80$11.30 – $21.0015Jul 31, 2026, Open bid tab, 76V11 ↗
Curb, removelinear foot$17.95$12.00 – $22.2014Apr 24, 2026, Open bid tab, 97840 ↗
Reinforced bars, epoxy ctdpound$2.28$1.76 – $4.2414Jun 12, 2026, Open bid tab, 76R32 ↗
Storm sew class a 1 15linear foot$82.25$68.00 – $105.5014Apr 24, 2026, Open bid tab, 97840 ↗
Furnish excavationcubic yard$39.50$18.77 – $50.0014Jan 16, 2026, Open bid tab, 76A46 ↗
Temporary ditch checkslinear foot$21.00$14.55 – $23.6014Jan 16, 2026, Open bid tab, 76A46 ↗
Concrete fdn type alinear foot$557.00$349.00 – $690.0013Jun 12, 2026, Open bid tab, 76U38 ↗
Elcbl C Signal 14 2Clinear foot$2.52$2.00 – $4.8013Jun 12, 2026, Open bid tab, 76U38 ↗
Tie Bars 3/4each$22.00$20.00 – $30.0013Jul 31, 2026, Open bid tab, 76V11 ↗
Concrete median surface 4square foot$28.30$14.35 – $30.0013Apr 24, 2026, Open bid tab, 97840 ↗