Construction unit costs in Will County, IL

Median awarded unit prices for 80 items on public projects in Will County, from winning bids in agency bid tabulations. Each item page lists its source documents.

Cost by state › Illinois › Will County

ItemPerMedianMiddle halfWinning bidsLatest source document
Temporary info signingsquare foot$25.00$20.00 – $30.0075Sep 18, 2026, Open bid tab, 80C95 ↗
Bit Matls Tack Ctpound$0.01$0.01 – $0.0163Sep 18, 2026, Open bid tab, 80C95 ↗
Protective Coatsquare yard$1.50$1.00 – $2.1862Sep 18, 2026, Open bid tab, 80C95 ↗
Thpl Pvt Mk Line 4linear foot$0.92$0.775 – $1.6156Sep 18, 2026, Open bid tab, 80C95 ↗
Earth Excavationcubic yard$37.00$25.00 – $72.5055Sep 18, 2026, Open bid tab, 80C95 ↗
Non Spl Waste Disposlcubic yard$78.00$66.50 – $90.0051Sep 18, 2026, Open bid tab, 80C95 ↗
Soil Disposal Analyeach$1,600$1,461 – $1,78850Sep 18, 2026, Open bid tab, 80C95 ↗
Raised reflective pavement mkreach$53.45$44.89 – $77.1548Sep 18, 2026, Open bid tab, 80C95 ↗
Thpl Pvt Mk Line 24linear foot$6.00$5.50 – $8.4448Sep 18, 2026, Open bid tab, 80C95 ↗
Sidewalk removesquare foot$3.00$2.50 – $4.6244Sep 18, 2026, Open bid tab, 80C95 ↗
Long joint seallinear foot$3.70$3.08 – $5.7244Sep 18, 2026, Open bid tab, 80C95 ↗
Thpl Pvt Mk Line 6linear foot$1.50$1.10 – $1.9643Sep 18, 2026, Open bid tab, 80C95 ↗
Thpl Pvt Mk Line 12linear foot$3.25$3.00 – $3.6543Sep 18, 2026, Open bid tab, 80C95 ↗
Nitrogen Fert Nutrpound$3.00$3.00 – $3.3041Jun 12, 2026, Open bid tab, 62X28 ↗
Thpl pvt mk ltr & symbolsquare foot$5.75$5.25 – $7.0041Sep 18, 2026, Open bid tab, 80C95 ↗
Potassium Fert Nutrpound$3.00$3.00 – $3.3040Jun 12, 2026, Open bid tab, 62X28 ↗
Topsoil F & P 4square yard$6.60$5.45 – $14.0039Sep 18, 2026, Open bid tab, 80C95 ↗
Pc concrete sidewalk 5square foot$10.00$9.00 – $11.9538Sep 18, 2026, Open bid tab, 80C95 ↗
Pavement removesquare yard$15.00$13.00 – $22.7536Apr 24, 2026, Open bid tab, 80B05 ↗
Detectable Warningssquare foot$35.00$25.25 – $40.0034Sep 18, 2026, Open bid tab, 80C95 ↗
Pvt marking remove water blastsquare foot$2.35$1.15 – $4.3834Apr 24, 2026, Open bid tab, 80B05 ↗
Perimeter erosion barlinear foot$2.85$2.05 – $3.2534Jun 12, 2026, Open bid tab, 62X37 ↗
Hot mix asphalt sc il-9.5 d n70ton$90.00$83.75 – $126.0031Sep 18, 2026, Open bid tab, 80C95 ↗
Guardrail removelinear foot$9.64$8.28 – $11.5031Jun 12, 2026, Open bid tab, 62X28 ↗
Undrgrd C Galvs 2linear foot$45.00$36.15 – $59.3631Sep 18, 2026, Open bid tab, 80C95 ↗
Pavement marking remove water blsquare foot$2.48$1.10 – $3.1731Sep 22, 2023, Open bid tab, 62R27 ↗
Aggregate subgrade impr 12square yard$20.00$15.00 – $27.6830Apr 24, 2026, Open bid tab, 80B31 ↗
Aggregate subgrade improvecubic yard$47.00$40.00 – $53.7530Apr 24, 2026, Open bid tab, 80B31 ↗
Combination curb gutter removelinear foot$10.00$8.00 – $14.5029Apr 24, 2026, Open bid tab, 62V71 ↗
Reinforced bars, epoxy ctdpound$2.25$1.85 – $3.0529Jun 12, 2026, Open bid tab, 62X28 ↗
Geotech fabric f/gr stabilizedsquare yard$3.00$2.25 – $4.0029Apr 24, 2026, Open bid tab, 80B31 ↗
Drive pavement removesquare yard$14.00$10.00 – $23.5029Sep 18, 2026, Open bid tab, 80C95 ↗
Temporary pvt mk line 4 - paintlinear foot$0.01$0.01 – $0.0129Sep 18, 2026, Open bid tab, 80C95 ↗
Barrier wall ref type ceach$10.00$7.92 – $15.0028Jan 16, 2026, Open bid tab, 62F94 ↗
Remove & disp uns materialcubic yard$28.75$24.25 – $48.1228Apr 24, 2026, Open bid tab, 80B31 ↗
Inlet Filterseach$146.50$127.75 – $241.5228Feb 27, 2026, Open bid tab, 62R23 ↗
Drainage Str Cleanedeach$462.00$397.50 – $1,00027Sep 18, 2026, Open bid tab, 80C95 ↗
Cc&g rmvl replace > 10ftlinear foot$65.00$50.19 – $78.7526Sep 18, 2026, Open bid tab, 80C95 ↗
Erosion control blanketsquare yard$1.36$1.10 – $4.6726Jun 12, 2026, Open bid tab, 62X28 ↗
Tr Bar Trm T1 Spl Taneach$3,980$3,846 – $4,19926Jun 12, 2026, Open bid tab, 62X28 ↗
Thpl Pvt Mk Line 8linear foot$2.02$1.69 – $2.1926Sep 18, 2026, Open bid tab, 80C95 ↗
Pin temporary concrete barriereach$20.00$15.00 – $25.0025Feb 27, 2026, Open bid tab, 62R23 ↗
Temporary erosion control seedpound$3.10$1.50 – $6.0025Jun 12, 2026, Open bid tab, 80B77 ↗
Sign Panel T1square foot$30.80$27.50 – $41.8025Feb 27, 2026, Open bid tab, 62R23 ↗
Hot mix asphalt sc il-9.5 d n50ton$102.50$88.75 – $176.7524Sep 18, 2026, Open bid tab, 80C95 ↗
Trench Backfillcubic yard$50.00$40.00 – $60.0024Apr 24, 2026, Open bid tab, 62V71 ↗
Spbgr type a 6ft postlinear foot$35.60$32.63 – $41.5324Jun 12, 2026, Open bid tab, 62X28 ↗
Main ex tr signal instaleach$2,520$1,772 – $4,40024Sep 18, 2026, Open bid tab, 80C95 ↗
Sodding Salt Tolerantsquare yard$32.50$14.41 – $61.5024Sep 18, 2026, Open bid tab, 80C95 ↗
Temporary ditch checkslinear foot$9.90$6.43 – $11.0024Feb 27, 2026, Open bid tab, 61M25 ↗
Elcbl C Egrdc 6 1Clinear foot$3.92$3.50 – $6.1224Sep 18, 2026, Open bid tab, 80C95 ↗
Fr & Lids Adjust Spleach$1,225$997.50 – $1,40024Sep 18, 2026, Open bid tab, 80C95 ↗
Seeding class 4acre$2,600$2,106 – $3,25723Jun 12, 2026, Open bid tab, 62X37 ↗
Temporary tr signal timingeach$770.00$550.00 – $1,31023Apr 24, 2026, Open bid tab, 80B46 ↗
Seeding class 2aacre$2,662$2,281 – $4,85023Jun 12, 2026, Open bid tab, 80B77 ↗
Concrete structurecubic yard$1,343$1,100 – $2,10023Jun 12, 2026, Open bid tab, 62X28 ↗
Combination cc&g tb6.12linear foot$42.00$30.00 – $50.3023Apr 24, 2026, Open bid tab, 62V71 ↗
Det Loop T1linear foot$31.00$24.83 – $35.6223Sep 18, 2026, Open bid tab, 80C95 ↗
Bar Splicerseach$50.00$47.96 – $55.0023Feb 27, 2026, Open bid tab, 62R23 ↗
Modified ureth pm line 12linear foot$4.72$3.68 – $10.6523Jul 31, 2026, Open bid tab, 62V46 ↗
Cc&g rmvl replace < = 10linear foot$70.00$59.00 – $104.6922Sep 18, 2026, Open bid tab, 80C95 ↗
Fence removelinear foot$8.11$6.58 – $11.0822Feb 27, 2026, Open bid tab, 62R23 ↗
Tree Trunk Protectioneach$137.50$113.75 – $159.7522Feb 27, 2026, Open bid tab, 62P01 ↗
Structure Excavationcubic yard$38.00$35.00 – $45.0021Jun 12, 2026, Open bid tab, 62X28 ↗
Teles steel sin supportlinear foot$18.70$16.00 – $26.4021Apr 24, 2026, Open bid tab, 80B76 ↗
Furnish excavationcubic yard$28.00$17.00 – $35.0021Jun 12, 2026, Open bid tab, 80B77 ↗
Ss Cleaned 12linear foot$4.00$2.25 – $7.0021Sep 18, 2026, Open bid tab, 80C95 ↗
Electrical service installeach$3,120$2,205 – $5,80821Feb 27, 2026, Open bid tab, 62R23 ↗
Det loop replacelinear foot$27.00$20.00 – $30.0021Feb 27, 2026, Open bid tab, 80B13 ↗
Hot mix asphalt bc il-19.0 n50ton$80.00$78.00 – $100.0021Feb 27, 2026, Open bid tab, 61M25 ↗
Concrete support-strcubic yard$1,400$1,200 – $2,50021Feb 27, 2026, Open bid tab, 61M25 ↗
Temporary soil reten systmsquare foot$50.00$45.00 – $55.0021Feb 27, 2026, Open bid tab, 62R23 ↗
Modified ureth pm line 6linear foot$2.47$1.50 – $5.5021Jul 31, 2026, Open bid tab, 62V46 ↗
Topsoil excavation & placcubic yard$22.25$20.00 – $35.2520Jun 12, 2026, Open bid tab, 80B77 ↗
Concrete removecubic yard$2,250$1,500 – $3,00020Jun 12, 2026, Open bid tab, 62X28 ↗
Remove elcbl fr conlinear foot$1.59$1.00 – $2.2320Sep 18, 2026, Open bid tab, 80C95 ↗
Hot mix asphalt bc il-19.0 n70ton$83.50$75.00 – $102.5020Feb 27, 2026, Open bid tab, 62R23 ↗
Rebuild Ex Handholeeach$2,325$2,075 – $3,14620Sep 18, 2026, Open bid tab, 80C95 ↗
Bit Matls Pr Ctpound$0.01$0.01 – $0.0120Apr 24, 2026, Open bid tab, 80B31 ↗
Welded wire reinforcedsquare yard$25.00$12.75 – $30.0020Jun 12, 2026, Open bid tab, 80B77 ↗