Skip to content
Hubstake

Other · awarded bid prices · Cook County

Raised reflective pavement mkr: cost per each in Cook County, IL

Listed by the agency as “Raised Refl Pavt Mkr”.

The median awarded price is $48.92 per each, from 148 winning bids on 148 public projects in Cook County, IL (2024–2026). Half of the awarded prices fall between $38.00 and $75.00.

Cost by state › Illinois › Cook County › Raised Refl Pavt Mkr

$48.92median per each
$38.00 – $75.00middle half (25th–75th percentile)
148winning bids, 148 source documents
2024–2026lettings covered (last 3 years)

Winning bids only, as printed in the agencies' bid tabulations (IDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.

Trend

The median awarded price went from $29.00 in 2021 to $45.00 in 2026 (+55%).

YearMedian per eachWinning bids
2021$29.0060
2022$39.0052
2023$43.0044
2024$52.2551
2025$48.1752
2026$45.0045

Most recent source documents

LettingAgencyQuantityAwarded unit priceSource
Sep 18, 2026IDOT1385 EACH$36.00Open bid tab, 62V55 ↗
Sep 18, 2026IDOT1135 EACH$38.00Open bid tab, 62V85 ↗
Sep 18, 2026IDOT1224 EACH$36.00Open bid tab, 62W73 ↗
Sep 18, 2026IDOT464 EACH$40.75Open bid tab, 62V90 ↗
Sep 18, 2026IDOT937 EACH$36.00Open bid tab, 62X84 ↗