| Item | Per | Median | Middle half | Winning bids |
|---|---|---|---|---|
| Traf Ctrl Mgmt | day | $1,500 | $1,200 – $1,760 | 290 |
| Const Traf Sign (A) | each | $55.00 | $34.00 – $88.00 | 289 |
| Traffic Cone | each | $12.00 | $7.50 – $18.35 | 281 |
| Const Traf Sign (B) | each | $70.75 | $42.88 – $110.00 | 280 |
| Flagging | hour | $46.00 | $38.44 – $52.00 | 276 |
| Traf Ctrl Inspection | day | $345.00 | $228.57 – $440.50 | 271 |
| Port Mesg Panel | each | $7,140 | $3,935 – $10,910 | 259 |
| Drum Channel DEV | each | $43.58 | $25.02 – $59.52 | 250 |
| Sanitary Facility | each | $4,272 | $1,973 – $7,125 | 247 |
| Sweeping (Sediment Removal) | hour | $189.95 | $140.34 – $226.53 | 224 |
| Aggregate Bag | linear foot | $12.00 | $9.00 – $16.00 | 206 |
| Removal and Disposal of Sediment (Labor) | hour | $75.00 | $53.75 – $100.00 | 204 |
| Potholing | hour | $350.00 | $276.16 – $453.72 | 203 |
| Removal and Disposal of Sediment (Equip) | hour | $150.00 | $120.00 – $180.75 | 183 |
| REM Trash | hour | $100.00 | $69.25 – $144.06 | 180 |
| REM Pavement Marking | square foot | $2.00 | $0.827 – $4.00 | 174 |
| Erosion Log Type 1 (12 in) | linear foot | $6.80 | $5.60 – $9.00 | 168 |
| Flash Arrow Panel (C TY) | each | $1,800 | $1,000 – $2,896 | 159 |
| Pre-fab Conc Washout Str (Type 1) | each | $2,778 | $1,700 – $4,575 | 158 |
| REM Asphalt Mat (Planing) | square yard | $4.85 | $3.00 – $10.00 | 157 |
| Mycorrhizae | pound | $18.72 | $12.00 – $35.00 | 157 |
| MOD Epoxy Pvmt MKG | gallon | $170.50 | $139.98 – $229.76 | 156 |
| HMA (Patching) (ASPH) | ton | $300.00 | $239.47 – $415.50 | 155 |
| Pre-fab Vehicle Track Pad | each | $5,000 | $3,047 – $12,258 | 155 |
| Sign Panel (CL I) | square foot | $30.00 | $26.15 – $39.00 | 151 |
| Vert Panel | each | $37.00 | $22.76 – $50.72 | 149 |
| REM Asphalt Mat | square yard | $20.00 | $11.45 – $38.59 | 145 |
| REM Ground Sign | each | $188.84 | $127.29 – $275.00 | 138 |
| Barricade (3 M-a) (Temp) | each | $207.50 | $101.39 – $379.77 | 138 |
| Wildlife Biologist | hour | $201.00 | $156.00 – $265.00 | 133 |
| Sign Panel (CL II) | square foot | $40.00 | $34.99 – $47.09 | 132 |
| Fence (Plastic) | linear foot | $4.50 | $3.30 – $6.06 | 132 |
| Impact Atten (Temp) | each | $8,758 | $5,164 – $11,407 | 131 |
| Erosion Control Management | day | $400.00 | $272.00 – $686.50 | 128 |
| Field Lab (CL 2) | each | $46,000 | $33,000 – $64,020 | 121 |
| Const Traf Sign (C) | each | $83.10 | $43.99 – $132.98 | 120 |
| Organic Fertilizer | pound | $2.30 | $1.14 – $5.00 | 119 |
| Emul Asph (Ss) | gallon | $5.50 | $4.05 – $7.13 | 119 |
| Pvmt MKG Paint (High Build) | gallon | $89.25 | $65.00 – $123.50 | 115 |
| Mobile Attenuator | each | $31,000 | $21,760 – $54,000 | 81 |
| Humate | pound | $2.70 | $1.15 – $5.00 | 81 |
| Silt Fence | linear foot | $2.90 | $1.81 – $4.09 | 78 |
| Stackable Vertical Panels | each | $35.00 | $21.00 – $46.36 | 41 |
| Detectable Warnings | square foot | $80.90 | $60.78 – $115.50 | 29 |
| Rumble Strip | linear foot | $0.45 | $0.25 – $0.75 | 29 |
| Topsoil | cubic yard | $69.50 | $29.50 – $90.00 | 18 |
Prices by county in Colorado
- Denver County: 6 items
Agencies in Colorado
- CDOT: 329,448 winning prices
- City and County of Denver: 5,346 winning prices