| Mobilization | ls | 4,880 | — | $71,701 | $0.01 – $36,481,382 | Oct 22, 2026, CDOT cost lookup · contract C24185 ↗ |
| Construction traffic sign (b) | each | 4,537 | $72.00 | $5.00 | $0.26 – $4,590 | Oct 22, 2026, CDOT cost lookup · contract C24185 ↗ |
| Traffic Cone | each | 4,312 | $10.00 | $10.00 | $0.01 – $100.00 | Oct 22, 2026, CDOT cost lookup · contract C24185 ↗ |
| Flagging | hour | 4,312 | $22.05 | $5.00 | $0.01 – $150.00 | Oct 22, 2026, CDOT cost lookup · contract C24185 ↗ |
| Construction traffic sign (a) | each | 4,027 | $50.00 | $5.00 | $0.01 – $2,100 | Oct 22, 2026, CDOT cost lookup · contract C24185 ↗ |
| Sanitary Facility | each | 3,702 | $1,050 | $3,399 | $1.00 – $69,425 | Oct 22, 2026, CDOT cost lookup · contract C25453 ↗ |
| Traffic control inspection | day | 3,389 | $125.00 | $750.00 | $0.01 – $2,029 | Oct 22, 2026, CDOT cost lookup · contract C24185 ↗ |
| Drum Channel DEV | each | 3,289 | $36.00 | $50.00 | $0.1 – $6,600 | Oct 22, 2026, CDOT cost lookup · contract C24185 ↗ |
| Traffic control mgmt | day | 3,189 | $575.00 | $3,000 | $0.01 – $8,134 | Oct 22, 2026, CDOT cost lookup · contract C24185 ↗ |
| Construction surveying | ls | 2,787 | — | $8,800 | $250.00 – $5,789,566 | Oct 22, 2026, CDOT cost lookup · contract C24185 ↗ |
| Construction traffic sign (c) | each | 2,534 | $84.95 | $5.00 | $0.26 – $1,711 | Oct 22, 2026, CDOT cost lookup · contract C24185 ↗ |
| Field lab (class 2) | each | 2,336 | $12,000 | $23,307 | $1.00 – $220,000 | Oct 22, 2026, CDOT cost lookup · contract C25780 ↗ |
| Flash arrow panel (c type) | each | 2,274 | $1,123 | $1,500 | $1.00 – $16,800 | Oct 22, 2026, CDOT cost lookup · contract C24185 ↗ |
| Potholing | hour | 2,170 | $200.00 | $455.00 | $1.00 – $2,300 | Oct 22, 2026, CDOT cost lookup · contract C24185 ↗ |
| Seeding (Native) | acre | 2,169 | $783.50 | $2,062 | $0.01 – $104,830 | Aug 27, 2026, CDOT cost lookup · contract C26972 ↗ |
| Port Mesg Panel | each | 2,079 | $5,000 | $10,000 | $1.00 – $48,000 | Oct 22, 2026, CDOT cost lookup · contract C24185 ↗ |
| Emul asphalt (ss) | gallon | 2,050 | $2.00 | $4.20 | $0.01 – $240.00 | Oct 22, 2026, CDOT cost lookup · contract C25780 ↗ |
| Remove ground sign | each | 1,958 | $75.00 | $109.00 | $2.00 – $4,623 | Oct 22, 2026, CDOT cost lookup · contract C25453 ↗ |
| Sign panel (class i) | square foot | 1,895 | $20.00 | $26.00 | $2.00 – $550.00 | Oct 22, 2026, CDOT cost lookup · contract C25453 ↗ |
| Remove asphalt mat (milling) | square yard | 1,880 | $3.00 | $44.34 | $0.18 – $620.00 | Oct 22, 2026, CDOT cost lookup · contract C25780 ↗ |
| Blading | hour | 1,874 | $115.00 | $10.00 | $1.00 – $615.35 | Oct 22, 2026, CDOT cost lookup · contract C24185 ↗ |
| Epoxy pavement marking | gallon | 1,811 | $75.30 | $300.00 | $24.50 – $3,450 | Oct 2, 2026, CDOT cost lookup · contract C27827 ↗ |
| Remove pavement marking | square foot | 1,797 | $1.65 | $3.00 | $0.01 – $60.00 | Oct 22, 2026, CDOT cost lookup · contract C25453 ↗ |
| Remove asphalt mat | square yard | 1,788 | — | $18.50 | $0.2 – $317.33 | Oct 22, 2026, CDOT cost lookup · contract C25453 ↗ |
| Field office (class 2) | each | 1,760 | $17,303 | $22,342 | $1.00 – $337,269 | Oct 22, 2026, CDOT cost lookup · contract C25780 ↗ |
| Mulching tackifier | pound | 1,744 | $3.00 | $57.00 | $0.01 – $530.00 | Oct 22, 2026, CDOT cost lookup · contract C25453 ↗ |
| Delineator (type i) | each | 1,606 | $19.00 | $33.75 | $2.00 – $315.00 | Oct 22, 2026, CDOT cost lookup · contract C25780 ↗ |
| Sign panel (class ii) | square foot | 1,585 | $22.00 | $36.00 | $1.18 – $158.00 | Oct 22, 2026, CDOT cost lookup · contract C24185 ↗ |
| Gdrail type 3 (6-3) | linear foot | 1,576 | $16.00 | $32.10 | $6.06 – $165.00 | May 7, 2026, CDOT cost lookup · contract C27298 ↗ |
| Drum Channel DEV (Light) (F) | each | 1,571 | $51.00 | $10.00 | $1.00 – $2,000 | Oct 22, 2026, CDOT cost lookup · contract C24185 ↗ |
| Remove and disposal of sediment (labor) | hour | 1,554 | $50.00 | $10.00 | $0.01 – $470.00 | Oct 22, 2026, CDOT cost lookup · contract C24185 ↗ |
| RES Ground Sign | each | 1,548 | $195.00 | $450.00 | $12.80 – $6,000 | Oct 8, 2026, CDOT cost lookup · contract C24946 ↗ |
| Remove delineator | each | 1,545 | $7.00 | $5.63 | $0.9 – $500.00 | Oct 22, 2026, CDOT cost lookup · contract C25780 ↗ |
| Remove gdrail type 3 | linear foot | 1,461 | $3.35 | $4.50 | $0.75 – $142.73 | Oct 22, 2026, CDOT cost lookup · contract C25780 ↗ |
| Concrete washout str | each | 1,459 | $851.32 | $5,000 | $0.1 – $81,929 | Oct 9, 2026, CDOT cost lookup · contract C27751 ↗ |
| Hot mix asphalt (patch) (asphalt) | ton | 1,423 | $184.35 | $225.00 | $10.00 – $4,000 | Oct 22, 2026, CDOT cost lookup · contract C25780 ↗ |
| Erosion Log Type 1 (12 in) | linear foot | 1,422 | $5.02 | $5.00 | $0.01 – $533.50 | Oct 22, 2026, CDOT cost lookup · contract C24185 ↗ |
| Delineator (type iii) | each | 1,366 | $22.58 | $38.25 | $4.50 – $420.00 | Oct 22, 2026, CDOT cost lookup · contract C25780 ↗ |
| Construction traffic sign (spec) | square foot | 1,352 | $19.00 | $48.00 | $1.00 – $320.00 | Oct 2, 2026, CDOT cost lookup · contract C27827 ↗ |
| Remove and disposal of sediment (equip) | hour | 1,326 | $105.00 | $10.00 | $0.01 – $841.52 | Oct 22, 2026, CDOT cost lookup · contract C24185 ↗ |