Skip to content
Hubstake

Structures · awarded bid prices · Harris County

Downstream Anchor Terminal Section: cost per each in Harris County, TX

The median awarded price is $1,426 per each, from 34 winning bids on 34 public projects in Harris County, TX (2023–2026). Half of the awarded prices fall between $1,250 and $1,598.

Cost by state › Texas › Harris County › Downstream Anchor Terminal Section

$1,426median per each
$1,250 – $1,598middle half (25th–75th percentile)
34winning bids, 34 source documents
2023–2026lettings covered (last 3 years)

Winning bids only, as printed in the agencies' bid tabulations (TxDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.

Trend

The median awarded price went from $1,285 in 2019 to $1,300 in 2026 (+1%).

YearMedian per eachWinning bids
2019$1,2859
2021$1,8006
2023$1,5009
2024$1,50013
2025$1,25011
2026$1,3009

Most recent source documents

LettingAgencyQuantityAwarded unit priceSource
Aug 6, 2026TxDOT27 EA$1,700line 22 ↗
Jun 9, 2026TxDOT12 EA$1,250line 11 ↗
Jun 2, 2026TxDOT12 EA$1,325line 13 ↗
May 7, 2026TxDOT1 EA$1,003line 12 ↗
May 7, 2026TxDOT5 EA$1,300line 25 ↗

The same item across Texas: statewide figures. See every awarded price for this item on the Downstream Anchor Terminal Section item page.

Related items in Harris County