Street Lighting · awarded bid prices · Dallas County
Electrical conductor (no.8) bare: cost per linear foot in Dallas County, TX
Listed by the agency as “Elec Condr (NO.8) Bare”.
The median awarded price is $2.65 per linear foot, from 23 winning bids on 23 public projects in Dallas County, TX (2024–2026). Half of the awarded prices fall between $1.96 and $3.10.
Cost by state › Texas › Dallas County › Elec Condr (NO.8) Bare
Winning bids only, as printed in the agencies' bid tabulations (TxDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $2.70 in 2024 to $2.45 in 2026 (-9%).
| Year | Median per linear foot | Winning bids |
|---|---|---|
| 2024 | $2.70 | 6 |
| 2025 | $3.09 | 6 |
| 2026 | $2.45 | 11 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Nov 12, 2026 | TxDOT | 2000 LF | $3.03 | line 37 ↗ |
| Oct 7, 2026 | TxDOT | 1030 LF | $4.00 | line 37 ↗ |
| Oct 7, 2026 | TxDOT | 3715 LF | $1.16 | line 30 ↗ |
| Sep 3, 2026 | TxDOT | 5000 LF | $2.00 | line 68 ↗ |
| Aug 6, 2026 | TxDOT | 133 LF | $15.26 | line 22 ↗ |
The same item across Texas: statewide figures. See every awarded price for this item on the Elec Condr (NO.8) Bare item page.
Related items in Dallas County
- Elec Condr (NO.6) Bare: $2.75 per linear foot
- Elec Condr (NO.6) Insulated: $2.98 per linear foot
- Elec Condr (NO.8) Insulated: $2.75 per linear foot
- Condt (PVC) (Sch 80) (2"): $24.00 per linear foot
- PED Pole Assembly: $3,290 per each
- Ground Box (Prepare): $400.00 per each
- Ground Box TY D (162922)W/Apron: $2,400 per each
- VEH Sig Sec (12")LED(YEL): $368.80 per each