Construction unit costs in St. Louis County, MO

Median awarded unit prices for 80 items on public projects in St. Louis County, from winning bids in agency bid tabulations. Each item page lists its source documents.

Cost by state › Missouri › St. Louis County

ItemPerMedianMiddle halfWinning bidsLatest source document
Substructure Repair (Unformed)square foot$176.12$160.00 – $240.0058Dec 12, 2025, Open the source page, contract 251212-F01
Half-sole Repairsquare foot$158.00$112.75 – $175.0054Oct 17, 2025, Open the source page, contract 251017-F05
Silt Fencelinear foot$3.05$2.85 – $3.7545Jun 18, 2026, Open the source page, contract 260618-F01
Truck or Trailer Mounted Attenuator (Tma)each$2,500$1,650 – $5,00045Mar 15, 2024, Open the source page, contract 240315-F03
Bridge Approach Slab (Major)square yard$335.00$320.00 – $475.5044Jun 18, 2026, Open the source page, contract 260618-F01
Preformed Thermoplastic Pavement Marking, 24 in. Whitelinear foot$19.90$18.00 – $25.0044Jun 18, 2026, Open the source page, contract 260618-F01
Preformed Thermoplastic Pavement Marking, Left/Right Arroweach$280.00$280.00 – $300.0041Jun 18, 2026, Open the source page, contract 260618-F01
Sh-flat Sheetsquare foot$36.00$29.57 – $40.0040Jun 18, 2026, Open the source page, contract 260618-F01
Shf-flat Sheet Fluorescentsquare foot$38.12$35.00 – $44.0037Jun 18, 2026, Open the source page, contract 260618-F01
Pull Box, Preformed Class 1each$1,610$1,540 – $1,70137Jun 18, 2026, Open the source page, contract 260618-F01
Coldmilling asphalt pavement for remove of surfacing (3 in. thick or less)square yard$3.25$2.75 – $4.5835Jun 18, 2026, Open the source page, contract 260618-F01
Type 5 Aggregate for Base (4 in. Thick)square yard$12.00$10.00 – $15.0035Jun 18, 2026, Open the source page, contract 260618-F01
Substructure Repair (Formed)square foot$210.00$168.00 – $281.9935Nov 14, 2025, Open the source page, contract 251114-F08
Concrete Sidewalk, 4 in.square yard$77.10$58.00 – $101.2234Jun 18, 2026, Open the source page, contract 260618-F01
Truncated Domessquare foot$27.05$22.12 – $30.0034Jun 18, 2026, Open the source page, contract 260618-F01
Type A Crashworthy End Terminal (Mash)each$3,900$3,800 – $3,99434Jun 18, 2026, Open the source page, contract 260618-F01
Pull Box, Preformed Class 2each$2,330$2,200 – $2,50033Jun 18, 2026, Open the source page, contract 260618-F01
Base, Concretecubic yard$2,480$1,958 – $2,86033Jun 18, 2026, Open the source page, contract 260618-F01
Changeable message sign without communication interface, con tractor furnish, contractor retainedeach$2,500$2,000 – $3,25033Apr 18, 2025, Open the source page, contract 250418-F02
Cable, 16 AWG 2 Conductorlinear foot$1.34$1.10 – $1.7732Jun 18, 2026, Open the source page, contract 260618-F01
Cable, 10 AWG 1 Conductor, Pole and Bracketlinear foot$1.05$0.788 – $1.2532Jun 18, 2026, Open the source page, contract 260618-F01
Reinforced steel (epoxy coated)pound$3.00$2.00 – $4.0532Nov 14, 2025, Open the source page, contract 251114-F08
Cable, 16 AWG 5 Conductorlinear foot$1.75$1.50 – $1.9031Jun 18, 2026, Open the source page, contract 260618-F01
Signal Sign, Mounting Hardwareeach$250.00$202.50 – $317.5030Jun 18, 2026, Open the source page, contract 260618-F01
Sh-flat Sheet - Signal Signsquare foot$38.00$36.04 – $43.9630Jun 18, 2026, Open the source page, contract 260618-F01
Pavement marking removelinear foot$1.00$0.85 – $2.2430Jun 18, 2026, Open the source page, contract 260618-F01
MGS Guardraillinear foot$28.75$28.00 – $34.7530Jun 18, 2026, Open the source page, contract 260618-F01
Conduit, 3 in., Trench with Tracer Wirelinear foot$17.25$16.00 – $19.0029Jun 18, 2026, Open the source page, contract 260618-F01
Post, Signal 8 FT.each$1,233$1,140 – $1,32629Jun 18, 2026, Open the source page, contract 260618-F01
6 In. White High Build Waterborne Pavement Marking Paint, Type L Beadslinear foot$0.32$0.28 – $0.429Apr 18, 2025, Open the source page, contract 250418-F02
Type D Barrierlinear foot$157.00$115.00 – $211.0029Jun 18, 2026, Open the source page, contract 260618-F01
Curb Inlet Checkeach$120.17$50.00 – $133.7529Jun 18, 2026, Open the source page, contract 260618-F01
Preformed Thermoplastic Pavement Marking, Combination Str/Lt/Rteach$450.00$393.75 – $500.0028Jun 18, 2026, Open the source page, contract 260618-F01
Full deep pavement repair saw cut (for perimeter and internal saw cuts)linear foot$10.00$6.88 – $11.9328Jun 18, 2026, Open the source page, contract 260618-F01
Concrete Curb (6 in. Height and Under) Type Slinear foot$52.00$41.00 – $89.5028May 15, 2026, Open the source page, contract 260515-F02
Turf Type Tall Fescue Soddingsquare yard$13.00$12.00 – $16.7728Jun 18, 2026, Open the source page, contract 260618-F01
MGS End Anchoreach$2,000$1,800 – $2,12828Jun 18, 2026, Open the source page, contract 260618-F01
Conduit, 3 in., Pushed with Tracer Wirelinear foot$33.00$24.95 – $40.3127May 15, 2026, Open the source page, contract 260515-F02
Cable, 16 AWG 7 Conductorlinear foot$2.15$2.00 – $2.5027Jun 18, 2026, Open the source page, contract 260618-F01
Concrete Footings, Embeddedcubic yard$3,200$2,800 – $3,60027Jun 18, 2026, Open the source page, contract 260618-F01
6 In. Concrete Median Stripsquare yard$140.00$123.75 – $168.5027Jun 18, 2026, Open the source page, contract 260618-F01
2 In. Psst Post - 12 GA.linear foot$30.00$27.00 – $32.0027Apr 17, 2026, Open the source page, contract 260417-F02
Mgs guardrail, 8 ft. post, 6 ft. - 3 in. spacinglinear foot$36.00$32.50 – $38.0027Nov 14, 2025, Open the source page, contract 251114-F05
Dowel bar (drilling, furnishing and install) for full deep pavement repaireach$8.50$5.19 – $15.0026Jun 18, 2026, Open the source page, contract 260618-F01
Pull Box, Preformed Class 3each$3,151$2,838 – $3,38626Jun 18, 2026, Open the source page, contract 260618-F01
Furnishing and placing concrete material for full deep pavement repairsquare yard$357.50$282.75 – $418.7526Jun 18, 2026, Open the source page, contract 260618-F01
Clean and epoxy coatingsquare foot$14.00$7.25 – $25.0025Aug 15, 2025, Open the source page, contract 250815-F01
Misc.countdown Pedestrian Signal Head, Type 1Seach$661.00$643.00 – $713.6925Jun 18, 2026, Open the source page, contract 260618-F01
Pipe postpound$8.00$6.00 – $10.0025Jun 18, 2026, Open the source page, contract 260618-F01
Signal Head, Type 3Beach$1,257$1,190 – $1,39625Jun 18, 2026, Open the source page, contract 260618-F01
Paved Approach, 8 in.square yard$115.00$105.00 – $128.0025May 15, 2026, Open the source page, contract 260515-F02
Signal Head, Type 4Beach$1,482$1,395 – $1,57525Jun 18, 2026, Open the source page, contract 260618-F01
Silicone expansion joint seallinear foot$42.00$42.00 – $63.0025Nov 15, 2024, Open the source page, contract 241115-F03
Mulchingacre$2,631$1,800 – $5,08824Jun 18, 2026, Open the source page, contract 260618-F01
Preformed Thermoplastic Pavement Marking, Straight Arroweach$250.00$200.00 – $250.0024May 15, 2026, Open the source page, contract 260515-F02
Slope Protectionsquare yard$116.50$98.00 – $197.7524Jun 18, 2026, Open the source page, contract 260618-F01
Temporary traffic barrier, contractor furnish / retainedlinear foot$25.23$20.75 – $32.3624Jun 18, 2026, Open the source page, contract 260618-F01
Cable-conduit, 1 in., 2 Conductors and 1 Bare Neutral, 8 AWGlinear foot$5.60$4.57 – $6.0924Jun 18, 2026, Open the source page, contract 260618-F01
2.5 In. Psst Post - 12 GA.linear foot$34.00$30.00 – $38.0023Apr 17, 2026, Open the source page, contract 260417-F02
Open Cell Foam Joint Seallinear foot$110.00$100.00 – $132.0023Nov 14, 2025, Open the source page, contract 251114-F08
Misc.epoxy Urethane Polymer Wearing Surface With Healer/sealersquare yard$41.00$38.67 – $44.0023May 16, 2025, Open the source page, contract 250516-F01
Asphalt pavement mixture pg64-22, (bp-1)ton$135.00$105.65 – $175.0023Jun 18, 2026, Open the source page, contract 260618-F01
Class B-2 Concretecubic yard$4,500$4,500 – $5,12523Nov 14, 2025, Open the source page, contract 251114-F08
Trench type ilinear foot$6.42$6.00 – $7.9423Jun 18, 2026, Open the source page, contract 260618-F01
Seeding - Cool Season Grassesacre$4,500$2,900 – $6,45023Jun 18, 2026, Open the source page, contract 260618-F01
Controller Assembly Housing, Nema TS2 Controllereach$20,862$19,562 – $22,81823Jun 18, 2026, Open the source page, contract 260618-F01
Culvert Cleanouteach$2,000$1,440 – $4,40923May 15, 2026, Open the source page, contract 260515-F02
6 In. Yellow High Build Waterborne Pavement Marking Paint, Type L Beadslinear foot$0.32$0.28 – $0.37523Apr 18, 2025, Open the source page, contract 250418-F03
Misc.atc Traffic Signal Controllereach$5,494$5,262 – $5,77922Jun 18, 2026, Open the source page, contract 260618-F01
Impact Attenuator (Relocation)each$1,000$745.50 – $1,07922Jun 18, 2026, Open the source page, contract 260618-F01
Field Application of Inorganic Zinc Primersquare foot$3.00$2.00 – $4.0022Nov 14, 2025, Open the source page, contract 251114-F08
Misc.fiber Optic Fusion Spliceeach$87.50$65.96 – $112.0022Jun 18, 2026, Open the source page, contract 260618-F01
Type 5 Aggregate for Base (6 in. Thick)square yard$16.00$11.38 – $20.0022Jun 18, 2026, Open the source page, contract 260618-F01
St-structuresquare foot$36.00$36.00 – $42.0021Jun 18, 2026, Open the source page, contract 260618-F01
Preformed Thermoplastic Pavement Marking, 12 in White, Yield Line Triangleseach$60.00$20.00 – $65.0021May 16, 2025, Open the source page, contract 250516-F01
Remove of existing deck repairsquare foot$22.00$22.00 – $46.8021Nov 14, 2025, Open the source page, contract 251114-F08
Diamond Grindingsquare yard$11.00$10.30 – $11.5021Nov 14, 2025, Open the source page, contract 251114-F08
Misc.sl District Traffic Signal Detection Systemeach$36,268$34,000 – $43,06821May 15, 2026, Open the source page, contract 260515-F02
Driven Post Anchor for 2 in. Psst - 12 GA.each$267.37$225.00 – $325.0021May 15, 2026, Open the source page, contract 260515-F02
Driven Post Anchor for 2.5 in. Psst - 7 GA.each$324.45$273.44 – $400.0021Apr 17, 2026, Open the source page, contract 260417-F02