Construction unit costs in Greene County, MO

Median awarded unit prices for 40 items on public projects in Greene County, from winning bids in agency bid tabulations. Each item page lists its source documents.

Cost by state › Missouri › Greene County

ItemPerMedianMiddle halfWinning bidsLatest source document
4 In. Yellow Standard Waterborne Pavement Marking Paint, Type P Beadslinear foot$0.475$0.19 – $0.728Mar 14, 2025, Open the source page, contract 250314-G03
Preformed Thermoplastic Pavement Marking, Left/Right Arroweach$274.72$249.84 – $322.7028Oct 17, 2025, Open the source page, contract 251017-G02
Tack Coatgallon$2.87$2.74 – $3.2426Mar 20, 2026, Open the source page, contract 260320-G01
Type 5 Aggregate for Base (4 in. Thick)square yard$16.95$13.56 – $20.0026Mar 20, 2026, Open the source page, contract 260320-G01
Truncated Domessquare foot$40.00$33.27 – $43.2026Mar 20, 2026, Open the source page, contract 260320-G01
Rock Ditch Checklinear foot$17.23$13.28 – $25.4326Oct 17, 2025, Open the source page, contract 251017-G02
Curb Inlet Checkeach$150.00$150.00 – $180.3226Mar 20, 2026, Open the source page, contract 260320-G01
4 In. White Standard Waterborne Pavement Marking Paint, Type P Beadslinear foot$0.5$0.19 – $0.825Mar 14, 2025, Open the source page, contract 250314-G03
Construction signsquare foot$7.75$7.00 – $8.7025Mar 20, 2026, Open the source page, contract 260320-G01
Breakaway Assembly (Perforated Square Steel Tube)each$255.00$183.00 – $293.0025Mar 20, 2026, Open the source page, contract 260320-G01
Seeding - Cool Season Grassesacre$4,017$2,500 – $5,33824Mar 20, 2026, Open the source page, contract 260320-G01
Pavement marking remove (symbols)each$102.10$53.80 – $165.6823Mar 20, 2026, Open the source page, contract 260320-G01
Concrete Curb Rampsquare yard$172.00$140.50 – $176.7523Mar 20, 2026, Open the source page, contract 260320-G01
Unclassified Excavationcubic yard$11.91$7.70 – $26.4922Oct 17, 2025, Open the source page, contract 251017-G02
Compacting Embankmentcubic yard$6.00$4.59 – $8.4022Oct 17, 2025, Open the source page, contract 251017-G02
Channelizer (Trim Line)each$20.45$20.00 – $24.7522Mar 20, 2026, Open the source page, contract 260320-G01
6 In. Yellow High Build Waterborne Pavement Marking Paint, Type L Beadslinear foot$0.31$0.263 – $0.62522Dec 13, 2024, Open the source page, contract 241213-G02
2 In. Psst Post - 12 GA.linear foot$13.50$12.08 – $25.8422Oct 17, 2025, Open the source page, contract 251017-G02
Type 5 Aggregate for Base (6 in. Thick)square yard$12.71$10.10 – $14.0821Mar 20, 2026, Open the source page, contract 260320-G01
Preformed Thermoplastic Pavement Marking, 30 in White Midblockeach$180.00$178.75 – $209.3220May 16, 2025, Open the source page, contract 250516-G03
Paved Approach, 8 in.square yard$122.00$93.90 – $128.0020Mar 20, 2026, Open the source page, contract 260320-G01
Turf Type Tall Fescue Soddingsquare yard$10.00$8.25 – $16.6220Mar 20, 2026, Open the source page, contract 260320-G01
Type A Crashworthy End Terminal (Mash)each$3,306$3,175 – $3,88520Oct 17, 2025, Open the source page, contract 251017-G02
Advanced Warning Rail Systemeach$60.00$45.00 – $107.0017May 16, 2025, Open the source page, contract 250516-G03
Flashing Arrow Paneleach$1,350$546.69 – $2,15117Oct 17, 2025, Open the source page, contract 251017-G02
2.5 In. Psst Post - 12 GA.linear foot$13.52$13.27 – $16.2316Mar 20, 2026, Open the source page, contract 260320-G01
Pull Box, Concrete, Standardeach$3,240$2,945 – $3,52516Oct 17, 2025, Open the source page, contract 251017-G02
Concrete Post Anchor for 2.5 in. Psst. - 7 GA.each$342.89$275.00 – $382.0016Mar 20, 2026, Open the source page, contract 260320-G01
Changeable message sign with communication interface, contra ctor furnish, contractor retainedeach$4,875$2,342 – $7,98916Mar 14, 2025, Open the source page, contract 250314-G03
Sediment removecubic yard$24.17$11.86 – $37.5015Mar 20, 2026, Open the source page, contract 260320-G01
Preformed Thermoplastic Pavement Marking, 24 in. Whitelinear foot$20.25$18.41 – $26.1215Mar 20, 2026, Open the source page, contract 260320-G01
Silt Fencelinear foot$3.15$3.00 – $3.7114Mar 20, 2026, Open the source page, contract 260320-G01
Pavement marking removelinear foot$1.03$0.778 – $1.8814Mar 20, 2026, Open the source page, contract 260320-G01
Sh-flat Sheetsquare foot$21.00$19.39 – $22.7513Oct 17, 2025, Open the source page, contract 251017-G04
Concrete Sidewalk, 4 in.square yard$70.00$59.00 – $75.0013Mar 20, 2026, Open the source page, contract 260320-G01
Type III Moveable Barricadeeach$160.00$153.05 – $200.0013Mar 14, 2025, Open the source page, contract 250314-G03
Mulchingacre$2,403$1,500 – $5,95012Mar 20, 2026, Open the source page, contract 260320-G01
Class 3 Excavationcubic yard$50.50$32.40 – $93.0012Mar 20, 2026, Open the source page, contract 260320-G01
Type 1 Aggregate for Base (4 in. Thick)square yard$14.55$12.68 – $18.9312Mar 20, 2026, Open the source page, contract 260320-G01
6 In. White High Build Waterborne Pavement Marking Paint, Type L Beadslinear foot$0.525$0.34 – $0.7112Dec 13, 2024, Open the source page, contract 241213-G02