Construction unit costs in Missouri

Median awarded unit prices for the 50 most-bid items on Missouri public projects, from winning bids in agency bid tabulations.

Cost by state › Missouri

ItemPerMedianMiddle halfWinning bids
Construction Signssquare foot$7.00$6.25 – $8.30625
Channelizer (Trim Line)each$18.00$10.00 – $22.00520
Silt Fencelinear foot$3.48$3.00 – $4.39445
Tack Coatgallon$3.00$2.68 – $3.58422
4 In. Yellow Standard Waterborne Pavement Marking Paint, Type P Beadslinear foot$0.18$0.13 – $0.61419
Preformed Thermoplastic Pavement Marking, 24 in. Whitelinear foot$24.00$20.00 – $28.00377
4 In. White Standard Waterborne Pavement Marking Paint, Type P Beadslinear foot$0.2$0.14 – $0.605375
Type A Crashworthy End Terminal (Mash)each$3,575$3,200 – $3,875375
Coldmilling Bituminous Pavement for Removal of Surfacing (3 in. Thick or Less)square yard$3.83$2.24 – $8.91358
Seeding - Cool Season Grassesacre$3,450$2,350 – $5,181326
Gravel (A) or Crushed Stone (B)ton$50.35$38.50 – $85.80321
Modified Coldmilling (Depth Transitions)square yard$10.50$6.50 – $18.01319
Changeable Message Sign Without Communication Interface, CON Tractor Furnished, Contractor Retainedeach$2,900$2,000 – $3,500317
MGS Guardraillinear foot$28.50$26.00 – $33.00311
Mulchingacre$2,180$1,525 – $3,774295
Misc.Permanent Aggregate Edge Treatmentton$44.64$34.23 – $54.77278
Pavement Marking Removallinear foot$1.05$0.65 – $2.02275
Rock Ditch Checklinear foot$17.12$13.20 – $31.59268
Flashing Arrow Paneleach$1,000$550.00 – $1,585265
MGS Bridge Approach Transition Section (Regular/No Curb)each$4,000$3,600 – $4,200265
Permanent Erosion Control Geotextilesquare yard$4.00$3.00 – $5.50264
Preformed Thermoplastic Pavement Marking, Left/Right Arroweach$300.00$270.00 – $341.50254
Bituminous Pavement Mixture PG64-22 (Surface Leveling)ton$85.70$78.75 – $93.80253
Sh-flat Sheetsquare foot$28.00$22.58 – $36.00252
Shf-flat Sheet Fluorescentsquare foot$33.16$26.19 – $40.45236
Compacting Embankmentcubic yard$8.15$5.00 – $14.49233
Advanced Warning Rail Systemeach$50.00$45.00 – $80.00217
Vertical Drain at End Bentseach$3,000$2,000 – $4,612214
Class 3 Excavationcubic yard$26.40$15.00 – $55.00213
Placing Type 2 Rock Blanketcubic yard$26.43$20.00 – $37.00206
Furnishing Type 2 Rock Blanketcubic yard$56.00$44.95 – $67.35203
Class A Excavationcubic yard$20.80$14.00 – $35.00201
Type III Moveable Barricadeeach$155.00$125.00 – $185.00197
Clearing AND Grubbingacre$7,228$4,026 – $12,471190
2 In. Psst Post - 12 GA.linear foot$25.00$16.77 – $30.19190
6 In. White High Build Waterborne Pavement Marking Paint, Type L Beadslinear foot$0.31$0.26 – $0.7189
Bituminous Shoulder Rumble Stripstation$20.00$12.00 – $35.95189
Type 5 Aggregate for Base (4 in. Thick)square yard$13.73$10.00 – $18.00177
Temporary Seedingacre$1,910$1,000 – $3,210171
Class 1 Excavationcubic yard$50.00$30.00 – $81.72166
Truncated Domessquare foot$31.50$26.00 – $40.00148
Embankment in Placecubic yard$26.75$17.35 – $40.00134
6 In. Yellow High Build Waterborne Pavement Marking Paint, Type L Beadslinear foot$0.3$0.26 – $0.5134
Truck or Trailer Mounted Attenuator (Tma)each$1,500$750.00 – $3,17691
Unclassified Excavationcubic yard$20.00$12.00 – $30.6879
Reinforcing Steel (Epoxy Coated)pound$3.00$2.00 – $4.5065
Curb and Gutter Type Alinear foot$55.00$45.50 – $75.5632
Flowable Backfillcubic yard$450.00$267.38 – $847.0027
Guardrail Type Alinear foot$29.90$25.50 – $34.1719
Reinforcing Steelpound$5.00$3.00 – $6.0017