| Asphalt Material for Tack | ton | $0.01 | $0.01 – $0.01 | 31 | Sep 3, 2026, Open bid tab, contract 26-2186 |
| Pavement stripe-temporary paint-4 in | linear foot | $0.24 | $0.22 – $0.24 | 31 | Mar 26, 2026, Open bid tab, contract 26-2083 |
| Loop Saw Slot and Fill | linear foot | $15.00 | $12.00 – $18.00 | 28 | Sep 3, 2026, Open bid tab, contract 26-2185 |
| Loop Wire | linear foot | $0.27 | $0.25 – $1.00 | 27 | Sep 3, 2026, Open bid tab, contract 26-2185 |
| Remove Signal Equipment | each | $2,371 | $1,888 – $2,927 | 24 | May 22, 2025, Open bid tab, contract 25-4301 |
| CONDUIT-1 1/4 in | linear foot | $9.71 | $7.07 – $16.71 | 24 | Sep 3, 2026, Open bid tab, contract 26-2185 |
| CONDUIT-2 in | linear foot | $11.13 | $9.33 – $20.95 | 23 | Feb 19, 2026, Open bid tab, contract 26-2114 |
| Temporary sign | square foot | $12.72 | $12.25 – $12.72 | 23 | Sep 3, 2026, Open bid tab, contract 26-2186 |
| Pavement marking-thermoplastic x-walk-12 in | linear foot | $6.30 | $5.58 – $6.50 | 22 | Sep 3, 2026, Open bid tab, contract 26-2185 |
| Concrete-class a | cubic yard | $1,315 | $922.64 – $2,400 | 21 | Apr 23, 2026, Open bid tab, contract 26-4200 |
| Electrical Junction Box Type A | each | $2,100 | $1,637 – $2,625 | 21 | Feb 19, 2026, Open bid tab, contract 26-2114 |
| Pavement marking-thermoplastic cross-hatch | square foot | $6.40 | $5.38 – $7.00 | 20 | Sep 3, 2026, Open bid tab, contract 26-2185 |
| Pavement marking-thermoplastic combination arrow | each | $143.50 | $140.00 – $159.50 | 20 | Feb 19, 2026, Open bid tab, contract 26-4204 |
| Portable Changeable Message Sign | each | $1,500 | $850.00 – $2,160 | 19 | Sep 3, 2026, Open bid tab, contract 26-2185 |
| Leveling & Wedging PG64-22 | ton | $110.00 | $105.12 – $125.50 | 19 | Sep 3, 2026, Open bid tab, contract 26-2186 |
| Asphalt pavement milling & texturing | ton | $21.50 | $18.50 – $26.75 | 18 | Sep 3, 2026, Open bid tab, contract 26-2186 |
| Pavement marking-thermoplastic stop bar-24in | linear foot | $9.60 | $8.50 – $12.00 | 17 | Sep 3, 2026, Open bid tab, contract 26-2185 |
| Arrow Panel | each | $535.00 | $417.50 – $1,216 | 15 | Sep 3, 2026, Open bid tab, contract 26-2185 |
| Pavement stripe-thermoplastic-6 in w | linear foot | $1.20 | $1.10 – $1.30 | 13 | Sep 3, 2026, Open bid tab, contract 26-2185 |
| Pavement marking-thermoplastic curv arrow | each | $115.00 | $115.00 – $120.75 | 13 | Sep 3, 2026, Open bid tab, contract 26-2185 |
| Pavement stripe-thermoplastic-6 in y | linear foot | $1.20 | $1.10 – $1.30 | 13 | Sep 3, 2026, Open bid tab, contract 26-2185 |
| Trench and backfilling | linear foot | $15.20 | $10.80 – $19.96 | 12 | Sep 3, 2026, Open bid tab, contract 26-2185 |
| Pavement stripe-thermoplastic-12 in w | linear foot | $3.00 | $2.48 – $6.00 | 12 | Aug 20, 2026, Open bid tab, contract 26-2196 |