Construction unit costs in Kentucky

Median awarded unit prices for the 49 most-bid items on Kentucky public projects, from winning bids in agency bid tabulations.

Cost by state › Kentucky

ItemPerMedianMiddle halfWinning bids
Leveling & Wedging PG64-22ton$112.50$95.00 – $126.001,022
CL2 Asph Surf 0.38D PG64-22ton$116.20$97.50 – $131.50941
Pave Marking-thermo Stop BAR-24INlinear foot$13.50$10.00 – $15.00789
Portable Changeable Message Signeach$1,500$800.00 – $3,710623
Pave Striping-perm PAINT-4 inlinear foot$0.26$0.2 – $0.33606
DGA Baseton$50.00$42.14 – $60.00590
Edgeline Rumble Stripslinear foot$0.26$0.2 – $0.39537
Pave Marking-thermo Curv Arroweach$120.00$110.00 – $135.00479
Pave STRIPING-THERMO-6 in Wlinear foot$1.25$1.10 – $1.35448
Pave STRIPING-THERMO-6 in Ylinear foot$1.21$1.08 – $1.35428
Pave Striping-perm PAINT-6 inlinear foot$0.3$0.26 – $0.34420
Concrete-class acubic yard$1,153$940.28 – $1,700382
Arrow Paneleach$550.00$300.00 – $1,199358
Asphalt Seal Aggregateton$225.25$130.00 – $526.50309
Steel Reinforcementpound$2.00$1.73 – $2.80302
Asphalt Seal Coatton$1,208$975.02 – $1,945302
Base Failure Repairsquare yard$93.69$66.45 – $135.00302
CL2 Asph Base 1.00D PG64-22ton$136.50$108.53 – $179.89276
Edge Keylinear foot$50.00$28.75 – $69.17269
Pave Marking-thermo Cross-hatchsquare foot$5.95$4.95 – $7.00251
Armored Edge for Concretelinear foot$109.00$90.00 – $150.00226
Guardrail-steel W Beam-s Facelinear foot$35.42$31.00 – $43.47213
Delineator for Guardrail BI Directional Whiteeach$15.46$14.87 – $17.00209
Trenching and Backfillinglinear foot$12.32$8.16 – $15.14191
Roadway Excavationcubic yard$33.80$19.38 – $56.91188
Guardrail Terminal Section NO 1each$92.94$85.00 – $101.57184
Seeding and Protectionsquare yard$0.75$0.54 – $1.05181
Maintenance Fertilizerton$1,500$1,250 – $1,800178
Erosion Control Blanketsquare yard$2.90$2.05 – $4.02177
Temp. Silt Fencelinear foot$3.00$2.02 – $4.00177
Silt Trap Type Beach$227.50$136.96 – $350.00176
Initial Fertilizerton$1,500$1,237 – $1,800176
Silt Trap Type Ceach$219.04$125.00 – $311.46173
Temp Seeding and Protectionsquare yard$0.39$0.31 – $0.48170
Detectable Warningssquare foot$50.00$44.05 – $64.59167
Agricultural Limestoneton$94.00$85.00 – $119.34165
Remove Guardraillinear foot$4.18$3.21 – $5.00159
Loop Wirelinear foot$0.315$0.3 – $1.06118
Embankment in Placecubic yard$30.78$15.25 – $62.4894
Remove Pavement Markereach$9.72$6.60 – $15.0091
Remove Signeach$103.09$89.38 – $243.4981
Remove Pipelinear foot$29.00$16.86 – $54.2879
Pavement Marking Removalsquare foot$6.86$3.04 – $10.5030
Remove Curb and Gutterlinear foot$16.36$14.83 – $25.0029
Temporary Silt Fencelinear foot$2.79$2.10 – $3.2723
Tubular Markerseach$109.61$87.43 – $146.5018
Remove Fencelinear foot$9.67$6.69 – $20.0018
Cementton$247.50$227.50 – $261.2516
Topsoil Furnished and Placedcubic yard$99.82$79.63 – $137.5014