Riprap Medium: cost per cubic yard in Outagamie County, WI
The median awarded price is $90.00 per cubic yard, from 21 winning bids on 21 public projects in Outagamie County, WI (2024–2026). Half of the awarded prices fall between $79.40 and $100.00.
Cost by state › Wisconsin › Outagamie County › Riprap Medium
$90.00median per cubic yard
$79.40 – $100.00middle half (25th–75th percentile)
21winning bids, 21 source documents
2024–2026lettings covered (last 3 years)
Winning bids only, as printed in the agencies' bid tabulations (WisDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $70.00 in 2023 to $92.69 in 2025 (+32%).
| Year | Median per cubic yard | Winning bids |
|---|---|---|
| 2023 | $70.00 | 5 |
| 2024 | $85.00 | 7 |
| 2025 | $92.69 | 10 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Aug 11, 2026 | WisDOT | 47 CY | $100.00 | Open bid tab, letting 20260811, call 013 |
| Jul 14, 2026 | WisDOT | 1290 CY | $87.10 | Open bid tab, letting 20260714, call 005 |
| Mar 10, 2026 | WisDOT | 71 CY | $70.00 | Open bid tab, letting 20260310, call 045 |
| Feb 10, 2026 | WisDOT | 1240 CY | $108.00 | Open bid tab, letting 20260210, call 022 |
| Nov 11, 2025 | WisDOT | 366 CY | $88.79 | Open bid tab, letting 20251111, call 014 |
See every awarded price for this item on the Riprap Medium item page.
Related items in Outagamie County
- Culvert Pipe Checks: $15.00 per each
- Inlet Protection Type C: $70.00 per each
- Markers Culvert End: $75.00 per each
- Removing Inlets: $384.00 per each
- Removing Small Pipe Culverts: $535.00 per each
- Inlet Covers Type H: $740.19 per each
- Inlets 2x3-FT: $2,674 per each
- Inlets 4-FT Diameter: $3,348 per each