Construction unit costs in Wisconsin

Median awarded unit prices for the 54 most-bid items on Wisconsin public projects, from winning bids in agency bid tabulations.

Cost by state › Wisconsin

ItemPerMedianMiddle halfWinning bids
Traffic Control Signsday$0.4$0.268 – $0.65920
Traffic Control Barricades Type IIIday$0.6$0.47 – $1.00853
Tack Coatgallon$3.60$2.88 – $5.95817
Traffic Control Warning Lights Type Aday$0.13$0.1 – $0.22817
Sawing Asphaltlinear foot$1.96$1.67 – $2.95810
Base Aggregate Dense 1 1/4-Inchton$21.18$16.55 – $26.00804
Silt Fencelinear foot$2.25$2.00 – $3.00784
Excavation Commoncubic yard$17.00$12.10 – $22.67780
Base Aggregate Dense 3/4-Inchton$29.74$24.00 – $40.32777
On-the-Job Training Graduate at $5.00/HRhour$5.00$5.00 – $5.00707
On-the-Job Training Apprentice at $5.00/HRhour$5.00$5.00 – $5.00703
Traffic Control Drumsday$0.25$0.19 – $0.5658
Construction Staking Slope Stakeslinear foot$0.98$0.75 – $1.50638
Geotextile Type HRsquare yard$5.05$3.80 – $7.00591
Removing Small Sign Supportseach$30.00$21.50 – $35.00588
Asphaltic Surfaceton$148.60$119.55 – $195.07566
Removing Signs Type IIeach$30.00$21.19 – $36.18564
Construction Staking Subgradelinear foot$0.01$0.01 – $0.01563
Traffic Control Signs Pcmsday$44.44$30.00 – $58.52540
Topsoilsquare yard$5.53$3.50 – $8.84522
Signs Type II Reflective Fsquare foot$25.00$23.00 – $30.00522
Sawing Concretelinear foot$2.58$2.30 – $3.25508
Seeding Temporarypound$4.81$3.50 – $7.00492
Moving Signs Type IIeach$110.00$75.00 – $150.00471
Removing Curb & Gutterlinear foot$7.75$5.00 – $11.71460
Construction Staking Curb Gutter and Curb & Gutterlinear foot$1.50$0.95 – $2.50455
Temporary Ditch Checkslinear foot$8.50$7.50 – $10.00453
Traffic Control Covering Signs Type IIeach$45.00$30.00 – $85.00438
Erosion Mat Urban Class I Type Bsquare yard$2.05$1.80 – $2.66435
Culvert Pipe Checkseach$20.00$15.00 – $25.00428
Grubbingstation$430.00$238.44 – $750.00417
Bar Steel Reinforcement HS Coated Structurespound$1.47$1.30 – $1.70409
Traffic Control Warning Lights Type Cday$0.15$0.1 – $0.25408
Removing Guardraillinear foot$3.00$2.50 – $4.00404
Marking Stop Line Epoxy 18-Inchlinear foot$15.27$13.44 – $18.00404
Removing Asphaltic Surface Millingsquare yard$2.61$1.46 – $5.00403
MGS Guardrail Terminal Eateach$3,750$3,450 – $4,000399
Removing Asphaltic Surfacesquare yard$6.95$4.50 – $12.45387
Signs Type II Reflective Hsquare foot$22.90$20.05 – $29.00387
Removing Asphaltic Surface Butt Jointssquare yard$11.58$5.75 – $20.71385
Inlet Protection Type Ceach$68.00$60.00 – $75.00384
Riprap Heavycubic yard$83.71$73.30 – $105.00383
Removing Concrete Pavementsquare yard$9.00$5.00 – $16.81376
Salvaged Topsoilsquare yard$2.75$1.54 – $4.00375
Asphaltic Surface Driveways and Field Entranceston$189.16$146.20 – $240.00373
Rubberized Membrane Waterproofingsquare yard$50.00$30.00 – $60.00371
Construction Staking Resurfacing Referencelinear foot$0.12$0.09 – $0.2357
Mulchingsquare yard$0.5$0.33 – $1.00342
Removing Concrete Sidewalksquare yard$10.00$6.58 – $15.97339
Inlet Protection Type Aeach$106.00$75.00 – $140.00306
Marking Line Epoxy 4-Inchlinear foot$1.00$0.6 – $3.00270
Clearingstation$641.50$318.75 – $1,175232
Inlet Protection Type Beach$62.00$50.00 – $75.00215
Topsoilcubic yard$49.00$32.00 – $68.4515