Earthwork · awarded bid prices · Travis County
Embankment (final)(ord comp)(type b): cost per cubic yard in Travis County, TX
Listed by the agency as “Embankment (final)(ord Comp)(ty B)”.
The median awarded price is $30.00 per cubic yard, from 23 winning bids on 23 public projects in Travis County, TX (2022–2024). Half of the awarded prices fall between $15.50 and $63.50.
Cost by state › Texas › Travis County › Embankment (final)(ord Comp)(ty B)
Winning bids only, as printed in the agencies' bid tabulations (TxDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $28.88 in 2019 to $72.50 in 2024 (+151%).
| Year | Median per cubic yard | Winning bids |
|---|---|---|
| 2019 | $28.88 | 8 |
| 2022 | $24.00 | 11 |
| 2023 | $37.25 | 6 |
| 2024 | $72.50 | 6 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Aug 1, 2024 | TxDOT | 824 CY | $30.00 | TxDOT request R075975-102926 · Bid_Tab_FY24 · let 2024-08-01 ↗ |
| Jul 10, 2024 | TxDOT | 20 CY | $200.00 | TxDOT request R075975-102926 · Bid_Tab_FY24 · let 2024-07-10 ↗ |
| Jul 10, 2024 | TxDOT | 70 CY | $115.00 | TxDOT request R075975-102926 · Bid_Tab_FY24 · let 2024-07-10 ↗ |
| May 2, 2024 | TxDOT | 1829 CY | $15.00 | Open bid tab, 05243005 ↗ |
| May 2, 2024 | TxDOT | 1829 CY | $15.00 | TxDOT request R075975-102926 · Bid_Tab_FY24 · let 2024-05-02 ↗ |
See every awarded price for this item on the Embankment (final)(ord Comp)(ty B) item page.