Earthwork · awarded bid prices
Clsm Backfill: cost per cubic yard in Oklahoma
The median awarded price is $220.00 per cubic yard, from 141 winning bids on 93 public projects in Oklahoma (2022–2023). Half of the awarded prices fall between $181.37 and $297.00.
Cost by state › Oklahoma › Clsm Backfill
$220.00median per cubic yard
$181.37 – $297.00middle half (25th–75th percentile)
141winning bids, 93 source documents
2022–2023lettings covered (last 5 years)
Winning bids only, as printed in the agencies' bid tabulations (Oklahoma DOT). These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $182.03 in 2019 to $245.00 in 2023 (+35%).
| Year | Median per cubic yard | Winning bids |
|---|---|---|
| 2019 | $182.03 | 110 |
| 2020 | $180.00 | 127 |
| 2021 | $180.00 | 88 |
| 2022 | $218.12 | 136 |
| 2023 | $245.00 | 5 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Jan 12, 2023 | Oklahoma DOT | 46 CY | $267.50 | contract 230003 ↗ |
| Jan 12, 2023 | Oklahoma DOT | 76 CY | $245.00 | contract 230014 ↗ |
| Jan 12, 2023 | Oklahoma DOT | 37.1 CY | $425.00 | contract 230021 ↗ |
| Jan 12, 2023 | Oklahoma DOT | 121.8 CY | $200.00 | contract 230023 ↗ |
| Dec 22, 2022 | Oklahoma DOT | 211.9 CY | $200.00 | contract 220339 ↗ |
See every awarded price for this item, in all states, on the Clsm Backfill item page.
Related items in Oklahoma
- Unclassified Excavation: $9.00 per cubic yard
- Unclassified Borrow: $10.75 per cubic yard
- Substructure Excavation Common: $20.00 per cubic yard
- Structural Excavation Unclassified: $33.47 per cubic yard
Free account: new awarded prices for this item show on your watchlist.