ItemPerMedianMiddle halfWinning bids
Unclassified Excavationcubic yard$9.00$7.00 – $15.39284
Reinforcing Steelpound$1.60$1.35 – $2.23275
Class AA Concretecubic yard$716.00$575.00 – $937.20253
Temporary Silt Fencelinear foot$3.12$2.57 – $4.99212
Traffic Bound Surface Course Type Eton$45.00$35.50 – $57.15192
Class C Concretecubic yard$440.96$375.00 – $738.91192
Sealer Crack Preparationlinear foot$4.30$3.52 – $5.00192
Solid Slab Soddingsquare yard$3.30$2.65 – $5.00185
Temporary Silt Dikelinear foot$15.88$11.95 – $25.00167
Unclassified Borrowcubic yard$10.75$8.62 – $17.66166
Traffic Stripe(MULTI-POLY.)(6" Wide)linear foot$0.9$0.663 – $1.65166
Cold Milling Pavementsquare yard$4.00$2.24 – $7.24160
Vegetative Mulchingacre$1,100$756.62 – $3,500157
Aggregate Base Type Acubic yard$75.11$61.75 – $83.00157
Water Repellent (Visually Inspected)square yard$4.65$4.00 – $5.64145
Clsm Backfillcubic yard$220.00$181.37 – $297.00141
Sheet Aluminum Signssquare foot$36.88$30.00 – $50.06137
Tack Coatgallon$3.70$3.02 – $5.00135
Class A Concretecubic yard$775.97$628.71 – $1,005135
Superpave, Type S4(PG 64-22 OK)ton$132.51$113.06 – $161.97134
Pavement Mrkng.removal(traf.strp)linear foot$0.58$0.32 – $1.40129
Superpave, Type S3(PG 64-22 OK)ton$113.72$100.12 – $138.00125
Traffic Stripe(MULTI-POLY.)(24" Wide)linear foot$11.75$5.92 – $20.00123
Type I-A Plain Riprapton$62.00$52.00 – $65.00121
Substructure Excavation Commoncubic yard$20.00$12.00 – $30.00118
Removal of Asphalt Pavementsquare yard$7.90$5.25 – $10.54116
Epoxy Coated Reinforcing Steelpound$1.70$1.50 – $1.85110
Structural Excavation Unclassifiedcubic yard$33.47$26.54 – $44.01102
Traffic STRIPE(MULTI-POLY.)(4" Wide)linear foot$0.7$0.492 – $1.90102
Structural Steelpound$4.20$3.00 – $6.00101
Sawing Pavementlinear foot$4.00$3.00 – $7.31101
6" Perforated Pipe Underdrain Roundlinear foot$32.74$27.09 – $43.6699
Saw-cut Groovingsquare yard$5.10$4.55 – $6.0499
Deliver Portable Longitudinal Barrierlinear foot$25.00$18.31 – $34.5099
Sealed Expansion Jointslinear foot$372.50$339.39 – $448.2596
6" Non-perf.Pipe Underdrain Rnd.linear foot$30.00$24.51 – $40.4095
Rapid Cure Joint Sealantlinear foot$30.00$22.70 – $35.0093
Beam Guardrail W-beam Singlelinear foot$32.04$28.75 – $39.2591
Elastomeric Coatingsquare foot$19.25$16.00 – $22.0089
Removal of Guardraillinear foot$5.00$4.00 – $6.0379
Mowingacre$300.00$195.00 – $420.0077
Structural Concretecubic yard$1,100$570.73 – $1,72558
Removal of Fencelinear foot$2.50$1.75 – $5.4025