Cost by state
Construction unit costs in Oklahoma
Median awarded unit prices for the 43 most-bid items on Oklahoma public projects, from winning bids in agency bid tabulations.
| Item | Per | Median | Middle half | Winning bids |
|---|---|---|---|---|
| Unclassified Excavation | cubic yard | $9.00 | $7.00 – $15.39 | 284 |
| Reinforcing Steel | pound | $1.60 | $1.35 – $2.23 | 275 |
| Class AA Concrete | cubic yard | $716.00 | $575.00 – $937.20 | 253 |
| Temporary Silt Fence | linear foot | $3.12 | $2.57 – $4.99 | 212 |
| Traffic Bound Surface Course Type E | ton | $45.00 | $35.50 – $57.15 | 192 |
| Class C Concrete | cubic yard | $440.96 | $375.00 – $738.91 | 192 |
| Sealer Crack Preparation | linear foot | $4.30 | $3.52 – $5.00 | 192 |
| Solid Slab Sodding | square yard | $3.30 | $2.65 – $5.00 | 185 |
| Temporary Silt Dike | linear foot | $15.88 | $11.95 – $25.00 | 167 |
| Unclassified Borrow | cubic yard | $10.75 | $8.62 – $17.66 | 166 |
| Traffic Stripe(MULTI-POLY.)(6" Wide) | linear foot | $0.9 | $0.663 – $1.65 | 166 |
| Cold Milling Pavement | square yard | $4.00 | $2.24 – $7.24 | 160 |
| Vegetative Mulching | acre | $1,100 | $756.62 – $3,500 | 157 |
| Aggregate Base Type A | cubic yard | $75.11 | $61.75 – $83.00 | 157 |
| Water Repellent (Visually Inspected) | square yard | $4.65 | $4.00 – $5.64 | 145 |
| Clsm Backfill | cubic yard | $220.00 | $181.37 – $297.00 | 141 |
| Sheet Aluminum Signs | square foot | $36.88 | $30.00 – $50.06 | 137 |
| Tack Coat | gallon | $3.70 | $3.02 – $5.00 | 135 |
| Class A Concrete | cubic yard | $775.97 | $628.71 – $1,005 | 135 |
| Superpave, Type S4(PG 64-22 OK) | ton | $132.51 | $113.06 – $161.97 | 134 |
| Pavement Mrkng.removal(traf.strp) | linear foot | $0.58 | $0.32 – $1.40 | 129 |
| Superpave, Type S3(PG 64-22 OK) | ton | $113.72 | $100.12 – $138.00 | 125 |
| Traffic Stripe(MULTI-POLY.)(24" Wide) | linear foot | $11.75 | $5.92 – $20.00 | 123 |
| Type I-A Plain Riprap | ton | $62.00 | $52.00 – $65.00 | 121 |
| Substructure Excavation Common | cubic yard | $20.00 | $12.00 – $30.00 | 118 |
| Removal of Asphalt Pavement | square yard | $7.90 | $5.25 – $10.54 | 116 |
| Epoxy Coated Reinforcing Steel | pound | $1.70 | $1.50 – $1.85 | 110 |
| Structural Excavation Unclassified | cubic yard | $33.47 | $26.54 – $44.01 | 102 |
| Traffic STRIPE(MULTI-POLY.)(4" Wide) | linear foot | $0.7 | $0.492 – $1.90 | 102 |
| Structural Steel | pound | $4.20 | $3.00 – $6.00 | 101 |
| Sawing Pavement | linear foot | $4.00 | $3.00 – $7.31 | 101 |
| 6" Perforated Pipe Underdrain Round | linear foot | $32.74 | $27.09 – $43.66 | 99 |
| Saw-cut Grooving | square yard | $5.10 | $4.55 – $6.04 | 99 |
| Deliver Portable Longitudinal Barrier | linear foot | $25.00 | $18.31 – $34.50 | 99 |
| Sealed Expansion Joints | linear foot | $372.50 | $339.39 – $448.25 | 96 |
| 6" Non-perf.Pipe Underdrain Rnd. | linear foot | $30.00 | $24.51 – $40.40 | 95 |
| Rapid Cure Joint Sealant | linear foot | $30.00 | $22.70 – $35.00 | 93 |
| Beam Guardrail W-beam Single | linear foot | $32.04 | $28.75 – $39.25 | 91 |
| Elastomeric Coating | square foot | $19.25 | $16.00 – $22.00 | 89 |
| Removal of Guardrail | linear foot | $5.00 | $4.00 – $6.03 | 79 |
| Mowing | acre | $300.00 | $195.00 – $420.00 | 77 |
| Structural Concrete | cubic yard | $1,100 | $570.73 – $1,725 | 58 |
| Removal of Fence | linear foot | $2.50 | $1.75 – $5.40 | 25 |
Prices by county in Oklahoma
- Oklahoma County: 4 items
- Tulsa County: 3 items
Agencies in Oklahoma
- Oklahoma DOT: 357,299 winning prices