| Construction Sign, Type A | each | $221.00 | $200.00 – $235.00 | 45 | Sep 2, 2026, Sep 2, 2026 letting ↗ |
| Computer System Equipment | each | $500.00 | $400.00 – $1,081 | 41 | Sep 2, 2026, Sep 2, 2026 letting ↗ |
| Construction Sign, Type B | each | $116.00 | $104.00 – $126.50 | 36 | Sep 2, 2026, Sep 2, 2026 letting ↗ |
| Liquid asphalt seal | linear foot | $0.225 | $0.15 – $0.588 | 34 | Feb 12, 2025, Feb 12, 2025 letting ↗ |
| Grooving for pavement marking | linear foot | $0.71 | $0.64 – $0.81 | 29 | Jul 8, 2026, Jul 8, 2026 letting ↗ |
| Road Closure Sign Assembly | each | $288.50 | $255.25 – $308.00 | 28 | Jul 8, 2026, Jul 8, 2026 letting ↗ |
| Flashing Arrow Sign | day | $15.00 | $15.00 – $16.00 | 28 | Sep 2, 2026, Sep 2, 2026 letting ↗ |
| Barricade, Type Iii-a | linear foot | $15.52 | $15.06 – $15.99 | 27 | Sep 2, 2026, Sep 2, 2026 letting ↗ |
| Barricade, Type Iii-b | linear foot | $15.39 | $15.00 – $16.04 | 27 | Jul 8, 2026, Jul 8, 2026 letting ↗ |
| Construction Sign, a | each | $198.00 | $190.00 – $223.50 | 27 | May 10, 2023, May 10, 2023 letting ↗ |
| Line, Remove | linear foot | $0.525 | $0.51 – $0.617 | 26 | Jul 8, 2026, Jul 8, 2026 letting ↗ |
| Detour Route Marker Assembly | each | $160.00 | $152.00 – $169.00 | 25 | Jul 8, 2026, Jul 8, 2026 letting ↗ |
| Temporary Traffic Barrier, Type 2 | linear foot | $33.00 | $20.00 – $47.24 | 25 | Jul 8, 2026, Jul 8, 2026 letting ↗ |
| Asphalt for Tack Coat | ton | $1,625 | $1,228 – $2,500 | 24 | Sep 2, 2026, Sep 2, 2026 letting ↗ |
| Compaction aggregate no. 53 | ton | $51.00 | $47.62 – $91.25 | 24 | Sep 2, 2026, Sep 2, 2026 letting ↗ |
| Curb AND Gutter, Concrete | linear foot | $52.00 | $37.00 – $77.50 | 24 | Jul 8, 2026, Jul 8, 2026 letting ↗ |
| Riprap, Revetment | ton | $120.00 | $93.33 – $150.00 | 22 | Jul 8, 2026, Jul 8, 2026 letting ↗ |
| Casting, Manhole, Adjust to Grade | each | $743.00 | $512.50 – $1,125 | 22 | Jul 8, 2026, Jul 8, 2026 letting ↗ |
| Barricade, Iii-a | linear foot | $17.16 | $14.85 – $18.12 | 21 | May 10, 2023, May 10, 2023 letting ↗ |
| Construction Sign, B | each | $122.50 | $97.50 – $146.25 | 20 | May 10, 2023, May 10, 2023 letting ↗ |
| Reinforced bars, epoxy coated | pound | $1.77 | $1.50 – $2.12 | 20 | Jul 8, 2026, Jul 8, 2026 letting ↗ |
| Temporary Traffic Barrier, Anchored, Type 2 | linear foot | $54.61 | $46.56 – $75.75 | 20 | Mar 11, 2026, Mar 11, 2026 letting ↗ |
| Saw cut for roadway loop detector and seal | linear foot | $13.00 | $11.71 – $16.22 | 20 | Jul 8, 2026, Jul 8, 2026 letting ↗ |
| Sign, Sheet, With Legend, 0.080 IN. | square foot | $31.34 | $28.24 – $35.66 | 20 | Sep 2, 2026, Sep 2, 2026 letting ↗ |
| Retrofitted Tie Bars | each | $47.50 | $41.50 – $57.75 | 20 | Mar 11, 2026, Mar 11, 2026 letting ↗ |
| Line, Multi-component, Solid, Yellow, 6 IN. | linear foot | $0.9 | $0.778 – $1.12 | 20 | Jul 8, 2026, Jul 8, 2026 letting ↗ |
| Snowplowable Raised Pavement Marker | each | $41.50 | $35.52 – $47.50 | 19 | Jul 8, 2026, Jul 8, 2026 letting ↗ |
| Guardrail, Remove | linear foot | $5.00 | $4.00 – $7.75 | 18 | Jul 8, 2026, Jul 8, 2026 letting ↗ |
| Snowplowable Raised Pavement Marker, Remove | each | $19.93 | $16.54 – $21.68 | 18 | Jul 8, 2026, Jul 8, 2026 letting ↗ |
| Line, Multi-component, Solid, White, 6 IN. | linear foot | $0.88 | $0.78 – $0.94 | 18 | Jul 8, 2026, Jul 8, 2026 letting ↗ |
| Portable Changeable Message Sign | each | $4,211 | $2,957 – $5,456 | 17 | Apr 8, 2026, Apr 8, 2026 letting ↗ |
| Barrier, Delineator | each | $22.82 | $22.55 – $27.41 | 16 | Apr 8, 2026, Apr 8, 2026 letting ↗ |
| D-1 Contraction Joint | linear foot | $30.00 | $24.25 – $35.16 | 16 | Mar 11, 2026, Mar 11, 2026 letting ↗ |
| Temporary Pavement Marking, Removable, 6 IN. | linear foot | $1.78 | $1.66 – $2.00 | 16 | Sep 2, 2026, Sep 2, 2026 letting ↗ |
| Line, Multi-component, Broken, White, 6 IN. | linear foot | $1.11 | $0.9 – $1.68 | 16 | Mar 11, 2026, Mar 11, 2026 letting ↗ |
| Joint Adhesive, Surface | linear foot | $0.99 | $0.5 – $1.38 | 15 | May 7, 2025, May 7, 2025 letting ↗ |
| Threaded Tie Bar Assembly, Epoxy Coated | each | $55.00 | $48.00 – $60.00 | 15 | Jul 8, 2026, Jul 8, 2026 letting ↗ |
| Curb AND Gutter, Remove | linear foot | $15.00 | $12.13 – $30.00 | 15 | Jul 8, 2026, Jul 8, 2026 letting ↗ |
| Guardrail, MGS W-beam, 6 FT 3 IN. Spacing | linear foot | $26.50 | $24.25 – $27.88 | 14 | Jul 8, 2026, Jul 8, 2026 letting ↗ |
| Sign Post, Square, Type 1, Reinforced Anchor Base | linear foot | $32.00 | $31.00 – $36.00 | 13 | Sep 2, 2026, Sep 2, 2026 letting ↗ |
| Sign, Sheet, With Legend, 0.100 IN. | square foot | $35.00 | $30.97 – $37.00 | 13 | Jul 8, 2026, Jul 8, 2026 letting ↗ |
| Transverse Marking, Thermoplastic, Stop Line, White, 24 IN. | linear foot | $13.41 | $13.01 – $14.22 | 13 | Jul 8, 2026, Jul 8, 2026 letting ↗ |
| Joint Adhesive, Intermediate | linear foot | $0.725 | $0.4 – $1.75 | 12 | May 7, 2025, May 7, 2025 letting ↗ |
| Temporary Pavement Marking, Removable, 4 IN. | linear foot | $1.40 | $1.32 – $1.46 | 12 | Jul 8, 2026, Jul 8, 2026 letting ↗ |
| Signal Detector Housing | each | $1,331 | $1,269 – $1,425 | 12 | Jul 8, 2026, Jul 8, 2026 letting ↗ |
| Pavement Message Marking, Thermoplastic Lane Indication Arrow | each | $219.00 | $194.75 – $225.75 | 12 | Jul 8, 2026, Jul 8, 2026 letting ↗ |
| Signal Cable, Roadway Loop, Copper, 1C/14 Gauge | linear foot | $1.06 | $1.00 – $1.19 | 12 | Jul 8, 2026, Jul 8, 2026 letting ↗ |