Construction unit costs in California

Median awarded unit prices for the 52 most-bid items on California public projects, from winning bids in agency bid tabulations.

Cost by state › California

ItemPerMedianMiddle halfWinning bids
Hot MIX Asphalt (Type A)ton$232.00$150.00 – $539.24688
Tack Coatton$1,100$750.00 – $2,100672
Temporary Drainage Inlet Protectioneach$277.27$200.00 – $400.00636
Pavement Marker (Retroreflective)each$7.50$5.00 – $13.00629
6" Thermoplastic Traffic Stripe (Enhanced Wet Night Visibility)linear foot$1.45$1.05 – $2.50582
Roadside Sign - One Posteach$500.00$400.00 – $700.00514
Furnish Single Sheet Aluminum Sign (0.063"-UNFRAMED)square foot$18.00$14.00 – $24.50509
Treated Wood Wastepound$1.00$0.5 – $2.00496
Temporary Fiber Rolllinear foot$6.00$4.79 – $8.00478
Stationary Impact Attenuator Vehicleday$635.00$367.50 – $1,300476
Thermoplastic Pavement Marking (Enhanced Wet Night Visibility)square foot$10.00$6.25 – $15.00476
Remove Pavement Markereach$2.10$1.05 – $5.00441
Furnish Single Sheet Aluminum Signsquare foot$19.50$14.28 – $26.00439
Roadway Excavationcubic yard$140.00$70.00 – $245.00422
Remove Thermoplastic Traffic Stripelinear foot$1.20$0.6 – $2.50411
Remove Thermoplastic Pavement Markingsquare foot$5.00$3.00 – $10.00394
Furnish Single Sheet Aluminum Sign (0.080"-UNFRAMED)square foot$17.00$14.00 – $21.35385
8" Thermoplastic Traffic Stripe (Enhanced Wet Night Visibility)linear foot$2.25$1.73 – $4.00355
Class 2 Aggregate Base (Cy)cubic yard$170.00$103.19 – $300.00352
Channelizer (Surface Mounted)each$60.00$48.00 – $80.00318
Temporary Barrier Systemlinear foot$40.00$24.88 – $60.00316
Remove Roadside Signeach$150.00$117.00 – $220.00305
Portable Changeable Message Sign (Ea)each$4,000$2,070 – $7,500305
Miscellaneous Iron and Steelpound$5.00$3.50 – $7.00303
Temporary Construction Entranceeach$5,000$3,500 – $7,500286
Remove Guardraillinear foot$11.77$8.00 – $20.00285
Roadside Sign - Two Posteach$950.00$700.00 – $1,210270
Compost (Cy)cubic yard$105.00$75.00 – $175.55269
Structural Concrete, Drainage Inletcubic yard$4,282$3,214 – $5,865260
Move-in/Move-out (Erosion Control)each$1,145$800.00 – $1,849258
Temporary Traffic Stripe (Paint)linear foot$1.00$0.5 – $2.00243
Remove Culvert (Lf)linear foot$65.00$30.00 – $110.00236
Temporary High-visibility Fencelinear foot$7.00$5.00 – $10.70235
Detectable Warning Surfacesquare foot$54.00$41.00 – $70.00225
Wood Mulchcubic yard$111.00$75.00 – $204.06225
Rubberized Hot MIX Asphalt (Gap Graded)ton$175.00$149.95 – $226.00225
Shoulder Backington$83.06$58.95 – $150.75222
Vegetation Control (Minor Concrete)square yard$110.00$85.00 – $150.00205
Type III Barricadeeach$135.00$100.00 – $200.00174
Temporary Silt Fencelinear foot$6.00$4.00 – $9.50125
Remove Concrete (Curb and Gutter)linear foot$32.00$16.69 – $55.25104
Structural Concrete, Bridgecubic yard$3,100$2,095 – $5,71279
Remove Fencelinear foot$11.50$7.40 – $23.0073
Structural Concretecubic yard$1,950$1,125 – $4,35327
Changeable Message Signeach$2,605$2,400 – $4,00025
Structure Excavationcubic yard$262.50$130.25 – $362.5020
Traffic Coneeach$30.00$14.88 – $50.0020
Remove Signeach$75.00$57.00 – $143.7518
Structural Steelpound$20.00$10.00 – $30.1218
6" Thermoplastic Traffic Stripelinear foot$2.00$1.23 – $3.2515
Embankmentcubic yard$96.66$44.25 – $162.5012
Rock Excavationcubic yard$82.50$63.25 – $196.2512