Construction unit costs in Virginia
Median awarded unit prices for the 37 most-bid items on Virginia public projects, from winning bids in agency bid tabulations.
| Item | Per | Median | Middle half | Winning bids |
|---|---|---|---|---|
| Flagger Service | hour | $36.00 | $30.00 – $47.03 | 611 |
| Type B Class I Pvmt Line Mrkg 4" | linear foot | $1.10 | $0.85 – $1.90 | 426 |
| Temp. Pvmt Mrkg, TY. A, 4" | linear foot | $0.16 | $0.09 – $0.24 | 414 |
| Type B Class I Pvmt Line Mrkg 6" | linear foot | $1.44 | $1.00 – $2.65 | 347 |
| Type B Class I Pvmt Line Mrkg 24" | linear foot | $15.00 | $10.85 – $22.00 | 338 |
| Inlaid Pavement Marker Asphalt | each | $51.75 | $39.95 – $85.36 | 318 |
| Truck Mounted Attenuator | hour | $30.00 | $13.38 – $57.66 | 276 |
| Port.Changeable Mess. Sign | hour | $9.00 | $4.88 – $14.00 | 267 |
| Agr.Base Mat.Ty.I or II NO. 21A OR21B | ton | $60.00 | $45.00 – $75.00 | 256 |
| Temp. Silt Fence Type A | linear foot | $5.78 | $3.50 – $8.74 | 228 |
| Pvmt Symb Mrkg SGL Turn Arr. TY B CL I | each | $161.15 | $135.00 – $204.25 | 228 |
| Temp. Pvmt Mrkg, TY. A, 6" | linear foot | $0.21 | $0.1 – $0.415 | 227 |
| Eradicate Nonlinear Pvmt Mrkg | square foot | $10.00 | $6.51 – $16.15 | 226 |
| Temp. Pvmt Mrkg TY. A, 12" | linear foot | $2.00 | $0.607 – $3.00 | 224 |
| Temporary Sign | square foot | $33.15 | $24.00 – $45.00 | 214 |
| Type B Class II Pvmt Line Mrkg 24" | linear foot | $30.00 | $22.01 – $45.00 | 214 |
| Rumble Strip Cylindrical Asphalt | linear foot | $0.6 | $0.345 – $1.27 | 195 |
| Sign Panel | square foot | $50.00 | $39.95 – $64.00 | 189 |
| Regular Seed | pound | $16.38 | $8.98 – $22.10 | 174 |
| Lime | ton | $350.00 | $200.00 – $500.00 | 172 |
| Fertilizer Nitrogen - N | pound | $3.98 | $2.29 – $6.78 | 172 |
| Fertilizer Potassium - K | pound | $4.00 | $2.30 – $6.64 | 172 |
| Fertilizer Phosphorous - P | pound | $3.96 | $2.30 – $6.64 | 172 |
| Overseeding | pound | $15.00 | $7.26 – $21.57 | 168 |
| Type A Pvmt Line Mrkg 4" | linear foot | $0.38 | $0.3 – $0.7 | 162 |
| Temporary Seed | pound | $16.23 | $11.54 – $20.00 | 159 |
| Inlet Protection Type A | each | $388.22 | $249.17 – $601.50 | 155 |
| Sign Post STP-1, 2", 14 Gauge | linear foot | $28.00 | $22.49 – $41.05 | 152 |
| Regular Excavation | cubic yard | $85.00 | $51.09 – $142.31 | 142 |
| Hydraulic Erosion Control Product Type 3 | square yard | $1.35 | $1.10 – $2.50 | 142 |
| Remove Existing Guardrail | linear foot | $8.50 | $5.00 – $11.12 | 136 |
| Aggr. Base Matl. TY. I NO. 21B | ton | $68.00 | $50.00 – $90.00 | 130 |
| Borrow Excavation | cubic yard | $56.00 | $35.00 – $85.00 | 121 |
| Flowable Backfill | cubic yard | $545.88 | $360.19 – $750.00 | 79 |
| Structure Excavation | cubic yard | $56.00 | $35.00 – $85.00 | 37 |
| Clearing AND Grubbing | acre | $39,756 | $22,800 – $75,000 | 29 |
| Geotextile Fabric | square yard | $6.15 | $3.45 – $9.06 | 28 |
Agencies in Virginia
- VDOT: 399,909 winning prices