Construction unit costs in Vermont

Median awarded unit prices for the 42 most-bid items on Vermont public projects, from winning bids in agency bid tabulations.

Cost by state › Vermont

ItemPerMedianMiddle halfWinning bids
Flaggershour$50.00$29.50 – $60.00119
Trench Excavation Of Earth, Exploratorycubic yard$75.00$75.00 – $75.00102
Topsoilcubic yard$70.00$50.00 – $85.00100
Uniformed Traffic Officershour$87.50$60.00 – $105.50100
Portable Changeable Message Signeach$4,500$3,000 – $7,15091
Rolled Erosion Control Product, Type Isquare yard$3.73$3.00 – $5.0090
Common Excavationcubic yard$30.00$20.00 – $48.1986
Cpm Scheduleeach$520.00$450.00 – $950.0077
Monitoring Epsc Planhour$50.00$25.00 – $75.0069
Hay Mulchton$1,200$962.50 – $1,55067
Stone Fill, Type Icubic yard$98.00$73.00 – $125.0065
Square Tube Sign Post And Anchorlinear foot$22.00$18.00 – $28.7563
Delineator With Steel Posteach$125.00$113.50 – $148.5063
Granular Backfill For Structurescubic yard$70.00$55.25 – $90.2562
Stabilized Construction Entrancecubic yard$73.50$50.00 – $95.6260
Subbase Of Dense Graded Crushed Stonecubic yard$65.00$51.75 – $81.5059
Barrier Fencelinear foot$4.00$3.00 – $5.0058
Aggregate Shoulders, Rapton$41.25$32.00 – $80.0057
All Purpose Excavator Rental, Type Ihour$125.00$100.00 – $150.0053
Project Demarcation Fencelinear foot$2.00$1.40 – $3.0053
Removal of Guardraillinear foot$1.73$1.00 – $5.0052
Truck Rentalhour$115.00$77.50 – $125.0051
Geotextile Under Stone Fillsquare yard$4.92$3.00 – $9.7550
Resetting Signseach$46.00$40.00 – $70.0049
Line Striping Targetseach$1.00$0.52 – $1.5048
Water Repellent, Silanegallon$131.50$100.00 – $182.5048
Structure Excavationcubic yard$48.33$30.00 – $75.0046
Silt Fence, Type Iilinear foot$6.67$5.00 – $10.0044
Steel Beam Guardraillinear foot$30.00$26.75 – $33.5043
Trench Excavation Of Earthcubic yard$40.00$25.00 – $54.0043
Bridge Expansion Joint, Asphaltic Pluglinear foot$176.00$147.75 – $201.2540
Removal Of Existing Delineator And Posteach$1.00$1.00 – $1.0540
Bituminous Concrete Pavement Surfaceton$215.00$150.00 – $272.5038
Temporary 24 Inch Stop Bar, Paintlinear foot$5.05$4.00 – $6.0036
Silt Fence, Type Ilinear foot$5.00$3.75 – $6.0036
Fertilizerpound$5.00$4.58 – $8.8032
Seedpound$15.00$10.00 – $17.8132
Detectable Warning Surfacesquare foot$59.00$50.00 – $65.0031
Agricultural Limestoneton$1,000$800.00 – $1,15021
Removal and Disposal of Guardraillinear foot$1.60$1.02 – $2.3319
Granular Borrowcubic yard$50.50$43.75 – $62.7516
Temporary Traffic Barrierlinear foot$29.00$20.00 – $57.5014