Construction unit costs in South Dakota

Median awarded unit prices for the 40 most-bid items on South Dakota public projects, from winning bids in agency bid tabulations.

Cost by state › South Dakota

ItemPerMedianMiddle halfWinning bids
Traffic Control Signssquare foot$4.00$2.00 – $6.60407
Flagginghour$36.03$36.03 – $36.03301
Type 3 Barricadeeach$130.00$100.00 – $186.66272
Unclassified Excavationcubic yard$12.00$5.58 – $24.50199
Type B Drainage Fabricsquare yard$5.80$4.41 – $7.50174
Asphalt Concrete Compositeton$189.62$148.02 – $250.00168
Pilot Carhour$52.75$52.75 – $58.77165
Base Courseton$32.82$22.33 – $45.38164
12" Diameter Erosion Control Wattlelinear foot$4.64$3.50 – $6.30164
Remove Asphalt Concrete Pavementsquare yard$10.00$5.24 – $16.15156
Type C Advance Warning Arrow Boardeach$1,100$525.00 – $1,750154
Repair Silt Fencelinear foot$1.00$0.5 – $2.06152
Placing Topsoilcubic yard$7.75$4.44 – $12.40147
Engineer Directed Surveying/Stakinghour$175.00$175.00 – $175.00144
Contractor Furnished Borrow Excavationcubic yard$24.50$14.44 – $38.74126
Class B Riprapton$84.70$68.50 – $99.71126
Remove Silt Fencelinear foot$1.07$0.55 – $2.00125
High Build Waterborne Pavement Marking Paint, Whitegallon$32.00$29.44 – $35.19124
High Build Waterborne Pavement Marking Paint, Yellowgallon$32.00$29.00 – $36.61122
Reinforcing Steelpound$3.00$2.27 – $4.00115
Temporary Pavement Markingmile$405.00$179.50 – $850.00106
Low Flow Silt Fencelinear foot$4.00$3.20 – $5.25106
Remove and Reset Erosion Control Wattlelinear foot$1.60$1.00 – $3.08106
Reset Signeach$150.00$65.83 – $250.00103
Water for Granular Materialthousand gallons$35.00$30.00 – $47.50103
Grade Stakingmile$6,700$3,225 – $10,832103
High Flow Silt Fencelinear foot$4.34$3.25 – $5.79102
Remove Sign for Reseteach$53.85$32.00 – $100.00101
Slope Stakingmile$5,550$3,235 – $9,992100
Remove Fencelinear foot$2.00$1.00 – $3.4998
Detour and Restriction Signingsquare foot$29.50$22.00 – $35.2598
Type III Field Laboratoryeach$15,000$8,548 – $22,00090
Type 2 Object Marker Back to Backeach$61.00$40.00 – $80.0086
Cold Milling Asphalt Concretesquare yard$1.75$1.10 – $5.0085
SS-1H or CSS-1H Asphalt for Flush Sealton$1,100$950.00 – $1,31383
2 Post Paneleach$300.84$212.50 – $409.0082
SS-1H or CSS-1H Asphalt for Tackton$833.50$766.25 – $950.0078
Hydrated Limeton$290.00$260.00 – $337.5870
Epoxy Coated Reinforcing Steelpound$4.00$3.00 – $5.0360
Remove Pipe Culvertlinear foot$50.45$21.50 – $75.0051