Skip to content
Hubstake

Cost by county

Construction unit costs in Horry County, SC

Median awarded unit prices for 39 items on public projects in Horry County, from winning bids in agency bid tabulations. Each item page lists its source documents.

Cost by state › South Carolina › Horry County

ItemPerMedianMiddle halfWinning bidsLatest source document
4 inchyellow solid line(pvt.edge&no passing zone)-fast dry paintlinear foot$0.11$0.1 – $0.14328Mar 10, 2026, Open bid tab, contract 2673540 ↗
4 inch white solid line (pvt. edge line)-fast dry paintlinear foot$0.11$0.1 – $0.14328Mar 10, 2026, Open bid tab, contract 2673540 ↗
4 inch white broken line -(gaps excluded)-fast dry paintlinear foot$0.11$0.1 – $0.1226Mar 10, 2026, Open bid tab, contract 2673540 ↗
4 inch yellow broken line(gaps excavation) - fast dry paintlinear foot$0.11$0.1 – $0.1325Mar 10, 2026, Open bid tab, contract 2673540 ↗
Permanent construction sign (ground mounted)square foot$6.15$5.85 – $7.3525Mar 10, 2026, Open bid tab, contract 2657420 ↗
Full deep asphalt. pavement. patch 8 inch unifsquare yard$75.15$68.70 – $86.6525Mar 10, 2026, Open bid tab, contract 2673540 ↗
4 inch yellow broken line(gaps excavation)thermoplastic - 90 mil.linear foot$0.47$0.438 – $0.51224Mar 10, 2026, Open bid tab, contract 2673540 ↗
Liquid Asphalt Binder PG64-22ton$655.00$602.50 – $692.5023Mar 10, 2026, Open bid tab, contract 2657420 ↗
Furnish & install 1.0 inch schedule 80 pvc conduitlinear foot$20.00$18.38 – $25.0023Mar 10, 2026, Open bid tab, contract 2673540 ↗
Furnish & install 2.0 inch schedule 80 pvc conduitlinear foot$16.88$14.00 – $20.0023Mar 10, 2026, Open bid tab, contract 2673540 ↗
F&i-13 inchx24 inchx18 inchd.electrical.flush undgrd.enclos- (str.poly.concrete.)hdeach$715.00$688.50 – $810.3423Mar 10, 2026, Open bid tab, contract 2673540 ↗
Permanent yellow pavement markers bi-dir.- 4 inchx4 incheach$5.38$4.62 – $8.0022Mar 10, 2026, Open bid tab, contract 2657420 ↗
Concrete sidewalk(4 inch uniform)square yard$70.10$61.25 – $100.0722Mar 10, 2026, Open bid tab, contract 2657420 ↗
Hot MIX Asphalt Surface Course Type Bton$94.25$79.85 – $124.5021Nov 13, 2024, Open bid tab, contract 2669350 ↗
Permanent Grassing for Non-permitted Resurfacing Projectsacre$4,000$3,250 – $4,25021Mar 10, 2026, Open bid tab, contract 2673540 ↗
Borrow Excavationcubic yard$62.50$45.75 – $85.6521Mar 10, 2026, Open bid tab, contract 2664350 ↗
Milling Existing Asphalt Pavement (Variable)square yard$15.00$9.91 – $20.6520Mar 10, 2026, Open bid tab, contract 2657420 ↗
24 inch white solid line (stop/diag line)-thermoplastic.-125 millinear foot$9.35$7.69 – $12.1020Mar 10, 2026, Open bid tab, contract 2657420 ↗
Pedestrian Ramp Constructionsquare yard$117.75$101.50 – $183.0020Mar 10, 2026, Open bid tab, contract 2657420 ↗
Detectable Warning Materialsquare foot$39.10$33.38 – $55.0020Mar 10, 2026, Open bid tab, contract 2657420 ↗
Concrete curb and gutter(2'-0 inch) vertical facelinear foot$41.15$25.15 – $57.1720Mar 10, 2026, Open bid tab, contract 2673540 ↗
6 inch white solid line (pvt. edge line) thermoplastic.- 90 mil.linear foot$0.8$0.68 – $1.0020Mar 10, 2026, Open bid tab, contract 2664350 ↗
Driveway Paving-surface Type Dton$165.25$143.75 – $191.2520Mar 10, 2026, Open bid tab, contract 2673540 ↗
Maintenance Stoneton$105.00$95.67 – $130.0019Mar 10, 2026, Open bid tab, contract 2657420 ↗
Permanent clear pavement markers- mono-dir.- 4 inchx4 incheach$5.25$5.00 – $7.5019Mar 10, 2026, Open bid tab, contract 2657420 ↗
White single arrows (lt, strght, rt) thermoplastic.-125 mil.each$125.00$76.15 – $187.5019Mar 10, 2026, Open bid tab, contract 2657420 ↗
White Word Message"Only" - Thermoplastic - 125 Mil.each$130.00$85.00 – $197.5018Mar 10, 2026, Open bid tab, contract 2657420 ↗
4 inch white solid line (pvt. edge line) thermoplastic.- 90 mil.linear foot$0.5$0.41 – $0.7517Mar 10, 2026, Open bid tab, contract 2657420 ↗
4 inch white broken line(gaps excl.)thermoplastic- 90 mil.linear foot$0.7$0.44 – $1.0017Mar 10, 2026, Open bid tab, contract 2657420 ↗
4 inch yellow solid line(pvt.edge line) thermoplastic-90 mil.linear foot$0.5$0.41 – $0.7517Mar 10, 2026, Open bid tab, contract 2657420 ↗
Silt Fencelinear foot$3.62$3.48 – $4.5416Mar 10, 2026, Open bid tab, contract 2657420 ↗
Milled-in Rumble Stripmile$500.00$500.00 – $526.2516Mar 10, 2026, Open bid tab, contract 2664350 ↗
Construction stakes, line & gradeseach$54,200$23,750 – $84,41616Mar 10, 2026, Open bid tab, contract 2657420 ↗
Stabilized Construction Entrancesquare yard$36.00$29.27 – $40.1016Mar 10, 2026, Open bid tab, contract 2657420 ↗
Unclassified Excavationcubic yard$46.00$38.45 – $59.1214Mar 10, 2026, Open bid tab, contract 2664350 ↗
8 inch white solid line thermoplastic - 125 mil.linear foot$2.95$2.75 – $3.7714Mar 10, 2026, Open bid tab, contract 2657420 ↗
Milling existing asphalt pavement 2.0 inchsquare yard$3.65$1.89 – $5.4414Mar 10, 2026, Open bid tab, contract 2657420 ↗
Flat Sheet, Type Iii, Fixed SZ. & Msg. Signsquare foot$22.50$13.00 – $27.0013Mar 10, 2026, Open bid tab, contract 2657420 ↗
Remove & disposal of existing pavementsquare yard$35.80$21.93 – $42.1612Mar 10, 2026, Open bid tab, contract 2657420 ↗

Other counties in South Carolina