Construction unit costs in Oregon

Median awarded unit prices for the 40 most-bid items on Oregon public projects, from winning bids in agency bid tabulations.

Cost by state › Oregon

ItemPerMedianMiddle halfWinning bids
Temporary Signssquare foot$26.00$17.00 – $32.00185
Temporary Barricades, Type IIIeach$190.00$150.00 – $222.50176
Temporary Plastic Drumseach$54.00$45.00 – $65.00173
Flaggershour$77.00$70.00 – $85.00169
Portable Changeable Message Signseach$6,000$3,000 – $10,000148
Aggregate Baseton$57.00$38.30 – $80.00123
Temporary Barricades, Type IIeach$70.00$60.00 – $90.75123
Sign Support Footingscubic yard$4,321$3,087 – $5,926119
Flagger Station Lightingeach$1,700$775.00 – $3,200115
Sequential Arrow Signseach$2,000$1,000 – $4,050104
Signs, Standard Sheeting, Sheet Aluminumsquare foot$33.50$28.00 – $44.00104
Inlet Protection, Type 3each$100.00$75.00 – $150.00102
Temporary Impact Attenuator, Truck Mountedeach$10,000$5,500 – $15,74998
Pavement Bar, Type B-hssquare foot$18.00$14.00 – $21.8895
Bridge Identification Markerseach$280.00$220.00 – $350.0094
Perforated Steel Square Tube Slip Base Sign Supportspound$9.13$6.67 – $12.2490
Pedestrian Channelizing Deviceslinear foot$27.00$18.50 – $35.0087
Contaminated Soil Disposalton$120.00$85.00 – $156.7584
Sediment Barrier, Type 3linear foot$6.95$5.00 – $10.0080
General Excavationcubic yard$49.25$29.98 – $80.0078
Perforated Steel Square Tube Anchor Sign Supportspound$8.25$6.13 – $12.3578
Bar Removalsquare foot$8.96$6.06 – $16.5078
Concrete Walkssquare foot$11.75$10.00 – $17.0077
Traffic Control Supervisoreach$700.00$355.00 – $950.0077
Permanent Seedingacre$10,500$5,000 – $24,00073
Temporary Stripinglinear foot$0.4$0.2 – $1.0072
Pavement Legend, Type B-hs: Arrowseach$425.00$380.00 – $537.5070
Subgrade Geotextilesquare yard$2.00$1.50 – $3.1568
Concrete Curbs, Curb and Gutterlinear foot$52.00$44.00 – $65.0065
Mainline Video Inspectionlinear foot$15.00$9.90 – $28.2564
Concrete Curbs, Standard Curblinear foot$45.00$36.00 – $62.2564
Extra for Asphalt Approacheseach$1,500$860.00 – $1,92162
Topsoilcubic yard$100.00$54.00 – $210.0057
Extra for New Curb Rampseach$1,263$850.00 – $2,50053
Truncated Domes on New Surfacessquare foot$45.00$38.00 – $50.0053
Asphalt Pavement Sawcuttinglinear foot$4.25$3.45 – $6.5051
Temporary Barrierlinear foot$31.00$22.12 – $49.5038
Structure Excavationcubic yard$89.17$63.05 – $289.2836
Removal of Guardraillinear foot$5.77$3.69 – $8.0126
Embankment in Placecubic yard$44.15$29.25 – $80.8216