Cost by state
Construction unit costs in Oregon
Median awarded unit prices for the 40 most-bid items on Oregon public projects, from winning bids in agency bid tabulations.
| Item | Per | Median | Middle half | Winning bids |
|---|---|---|---|---|
| Temporary Signs | square foot | $26.00 | $17.00 – $32.00 | 185 |
| Temporary Barricades, Type III | each | $190.00 | $150.00 – $222.50 | 176 |
| Temporary Plastic Drums | each | $54.00 | $45.00 – $65.00 | 173 |
| Flaggers | hour | $77.00 | $70.00 – $85.00 | 169 |
| Portable Changeable Message Signs | each | $6,000 | $3,000 – $10,000 | 148 |
| Aggregate Base | ton | $57.00 | $38.30 – $80.00 | 123 |
| Temporary Barricades, Type II | each | $70.00 | $60.00 – $90.75 | 123 |
| Sign Support Footings | cubic yard | $4,321 | $3,087 – $5,926 | 119 |
| Flagger Station Lighting | each | $1,700 | $775.00 – $3,200 | 115 |
| Sequential Arrow Signs | each | $2,000 | $1,000 – $4,050 | 104 |
| Signs, Standard Sheeting, Sheet Aluminum | square foot | $33.50 | $28.00 – $44.00 | 104 |
| Inlet Protection, Type 3 | each | $100.00 | $75.00 – $150.00 | 102 |
| Temporary Impact Attenuator, Truck Mounted | each | $10,000 | $5,500 – $15,749 | 98 |
| Pavement Bar, Type B-hs | square foot | $18.00 | $14.00 – $21.88 | 95 |
| Bridge Identification Markers | each | $280.00 | $220.00 – $350.00 | 94 |
| Perforated Steel Square Tube Slip Base Sign Supports | pound | $9.13 | $6.67 – $12.24 | 90 |
| Pedestrian Channelizing Devices | linear foot | $27.00 | $18.50 – $35.00 | 87 |
| Contaminated Soil Disposal | ton | $120.00 | $85.00 – $156.75 | 84 |
| Sediment Barrier, Type 3 | linear foot | $6.95 | $5.00 – $10.00 | 80 |
| General Excavation | cubic yard | $49.25 | $29.98 – $80.00 | 78 |
| Perforated Steel Square Tube Anchor Sign Supports | pound | $8.25 | $6.13 – $12.35 | 78 |
| Bar Removal | square foot | $8.96 | $6.06 – $16.50 | 78 |
| Concrete Walks | square foot | $11.75 | $10.00 – $17.00 | 77 |
| Traffic Control Supervisor | each | $700.00 | $355.00 – $950.00 | 77 |
| Permanent Seeding | acre | $10,500 | $5,000 – $24,000 | 73 |
| Temporary Striping | linear foot | $0.4 | $0.2 – $1.00 | 72 |
| Pavement Legend, Type B-hs: Arrows | each | $425.00 | $380.00 – $537.50 | 70 |
| Subgrade Geotextile | square yard | $2.00 | $1.50 – $3.15 | 68 |
| Concrete Curbs, Curb and Gutter | linear foot | $52.00 | $44.00 – $65.00 | 65 |
| Mainline Video Inspection | linear foot | $15.00 | $9.90 – $28.25 | 64 |
| Concrete Curbs, Standard Curb | linear foot | $45.00 | $36.00 – $62.25 | 64 |
| Extra for Asphalt Approaches | each | $1,500 | $860.00 – $1,921 | 62 |
| Topsoil | cubic yard | $100.00 | $54.00 – $210.00 | 57 |
| Extra for New Curb Ramps | each | $1,263 | $850.00 – $2,500 | 53 |
| Truncated Domes on New Surfaces | square foot | $45.00 | $38.00 – $50.00 | 53 |
| Asphalt Pavement Sawcutting | linear foot | $4.25 | $3.45 – $6.50 | 51 |
| Temporary Barrier | linear foot | $31.00 | $22.12 – $49.50 | 38 |
| Structure Excavation | cubic yard | $89.17 | $63.05 – $289.28 | 36 |
| Removal of Guardrail | linear foot | $5.77 | $3.69 – $8.01 | 26 |
| Embankment in Place | cubic yard | $44.15 | $29.25 – $80.82 | 16 |
Agencies in Oregon
- ODOT: 62,015 winning prices