Construction unit costs in Minnesota

Median awarded unit prices for the 55 most-bid items on Minnesota public projects, from winning bids in agency bid tabulations.

Cost by state › Minnesota

ItemPerMedianMiddle halfWinning bids
Remove Bituminous Pavementsquare yard$5.25$3.90 – $8.42497
Seedingacre$499.24$230.00 – $1,000409
Sawing Bituminous Pavement (Full Depth)linear foot$2.50$2.00 – $5.00408
Storm Drain Inlet Protectioneach$175.00$132.38 – $209.38398
Common Embankment (Cv)cubic yard$10.00$6.00 – $20.00364
Excavation Commoncubic yard$15.00$9.38 – $24.70351
Soil Bed Preparationacre$318.47$200.00 – $621.50347
Fertilizer Type 3pound$1.00$0.95 – $1.45345
Silt Fence, Type MSlinear foot$2.50$2.00 – $3.21340
Remove Pipe Culvertslinear foot$15.00$11.00 – $20.00329
Remove Signeach$50.00$28.00 – $75.00313
6" Solid Line Multi-component Ground IN (wr)linear foot$1.47$1.16 – $2.42277
Rolled Erosion Prevention Category 25square yard$2.00$1.80 – $2.50268
Signsquare foot$85.00$70.00 – $102.00265
Truncated Domessquare foot$65.00$57.75 – $75.00262
Casting Assemblyeach$1,145$917.56 – $1,339260
6" Concrete Walksquare foot$11.00$9.00 – $13.88258
Culvert End Controlseach$150.00$99.00 – $200.00252
Random Riprap Class IIIcubic yard$105.00$85.12 – $135.00247
Grubbingacre$8,500$4,788 – $12,525240
Salvage Signeach$50.00$36.99 – $75.00231
Sawing Concrete Pavement (Full Depth)linear foot$5.50$4.00 – $6.88223
Bituminous Material For Tack Coatgallon$2.88$2.00 – $3.50216
Install Signeach$590.25$340.00 – $903.08212
Excavation Common **P**cubic yard$11.50$6.95 – $16.00209
4" Solid Line Paintlinear foot$0.13$0.11 – $0.4204
Select Granular Embankment (Cv)cubic yard$26.00$19.48 – $38.00203
Sediment Control Log Type Compostlinear foot$3.50$3.00 – $4.42202
Aggregate Surfacing Class 5ton$23.00$19.00 – $33.34202
Interim Pavement Markinglinear foot$0.22$0.15 – $0.34199
Grubbingeach$250.00$150.00 – $500.00198
Drill and Grout Reinf Bar (Epoxy Coated)each$15.00$11.00 – $20.00196
6" Solid Line Paintlinear foot$0.16$0.14 – $0.3193
Remove Curb and Gutterlinear foot$6.50$4.04 – $10.00191
Rolled Erosion Prevention Category 20square yard$2.00$1.65 – $2.55189
Traffic Barrier Design Type 31linear foot$34.00$30.00 – $40.40181
Connect to Existing Storm Sewereach$1,300$950.00 – $1,781180
Fine Aggregate Bedding (Cv)cubic yard$45.00$35.00 – $58.00173
24" RC Pipe Aproneach$1,324$1,142 – $1,800171
Reinforcement Bars (Epoxy Coated)pound$1.75$1.60 – $2.00167
4" Concrete Walksquare foot$8.50$7.01 – $10.99138
Pavement Marking Removallinear foot$1.00$0.8 – $1.80137
Portable Changeable Message Signeach$3,000$2,148 – $3,950118
Motor Graderhour$200.00$132.50 – $220.00108
Mowingacre$150.00$86.06 – $247.5090
Sign Panelsquare foot$49.62$38.25 – $62.5090
Waterthousand gallons$40.00$25.00 – $59.3886
Pavement Marking Removalsquare foot$3.75$3.00 – $5.5065
Pavement Message Paintsquare foot$7.50$6.00 – $11.0063
Remove Fencelinear foot$5.00$3.00 – $9.9049
Remove Catch Basineach$500.00$311.25 – $785.0032
Structural Concretecubic yard$124.62$118.77 – $139.3422
Concrete Collareach$1,101$700.00 – $1,81521
Remove Guardraillinear foot$7.90$5.15 – $11.0019
Cementton$225.00$212.50 – $233.9515