The median awarded price is $18.27 per each, from 12 winning bids on 12 public projects in St. Clair County, IL (2024–2026). Half of the awarded prices fall between $15.33 and $20.25.
Cost by state › Illinois › St. Clair County › Tie Bars 3/4
$18.27median per each
$15.33 – $20.25middle half (25th–75th percentile)
12winning bids, 12 source documents
2024–2026lettings covered (last 3 years)
Winning bids only, as printed in the agencies' bid tabulations (IDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $20.00 in 2023 to $17.43 in 2026 (-13%).
| Year | Median per each | Winning bids |
|---|---|---|
| 2023 | $20.00 | 5 |
| 2026 | $17.43 | 6 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Sep 18, 2026 | IDOT | 31 EACH | $20.00 | Open bid tab, 97892 ↗ |
| Apr 24, 2026 | IDOT | 742 EACH | $18.00 | Open bid tab, 76V07 ↗ |
| Apr 24, 2026 | IDOT | 528 EACH | $10.75 | Open bid tab, 97808 ↗ |
| Feb 27, 2026 | IDOT | 99 EACH | $25.00 | Open bid tab, 76V02 ↗ |
| Feb 27, 2026 | IDOT | 1179 EACH | $16.85 | Open bid tab, 97886 ↗ |
See every awarded price for this item on the Tie Bars 3/4 item page.
Related items in St. Clair County
- Bit Matls Tack Ct: $2.32 per pound
- Short Term Pavt Mking: $2.86 per linear foot
- Thpl Pvt Mk Line 4: $1.31 per linear foot
- Raised Refl Pavt Mkr: $80.00 per each
- Thpl Pvt Mk Line 12: $9.04 per linear foot
- Thpl Pvt Mk Ltr & Sym: $15.00 per square foot
- Thpl Pvt Mk Line 24: $19.50 per linear foot
- Nitrogen Fert Nutr: $4.00 per pound