Other · awarded bid prices · Lake County
Ss Cleaned 12: cost per linear foot in Lake County, IL
The median awarded price is $3.00 per linear foot, from 25 winning bids on 25 public projects in Lake County, IL (2022–2026). Half of the awarded prices fall between $2.25 and $6.00.
Cost by state › Illinois › Lake County › Ss Cleaned 12
$3.00median per linear foot
$2.25 – $6.00middle half (25th–75th percentile)
25winning bids, 25 source documents
2022–2026lettings covered (last 5 years)
Winning bids only, as printed in the agencies' bid tabulations (IDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $3.00 in 2019 to $4.20 in 2025 (+40%).
| Year | Median per linear foot | Winning bids |
|---|---|---|
| 2019 | $3.00 | 9 |
| 2020 | $4.00 | 5 |
| 2021 | $3.00 | 7 |
| 2022 | $2.85 | 8 |
| 2023 | $7.50 | 6 |
| 2025 | $4.20 | 6 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Feb 27, 2026 | IDOT | 375 FOOT | $1.00 | Open bid tab, 80B75 ↗ |
| Jan 16, 2026 | IDOT | 103 FOOT | $1.50 | Open bid tab, 80B29 ↗ |
| Jan 16, 2026 | IDOT | 400 FOOT | $2.00 | Open bid tab, 80B50 ↗ |
| Jun 13, 2025 | IDOT | 885 FOOT | $3.40 | Open bid tab, 62P73 ↗ |
| Jun 13, 2025 | IDOT | 90 FOOT | $10.00 | Open bid tab, 62V58 ↗ |
See every awarded price for this item on the Ss Cleaned 12 item page.
Related items in Lake County
- Temp Info Signing: $18.00 per square foot
- Bit Matls Tack Ct: $0.01 per pound
- Thpl Pvt Mk Line 4: $1.15 per linear foot
- Thpl Pvt Mk Line 12: $3.32 per linear foot
- Non Spl Waste Disposl: $80.12 per cubic yard
- Soil Disposal Analy: $1,265 per each
- Thpl Pvt Mk Line 24: $6.05 per linear foot
- Thpl Pvt Mk Line 6: $1.65 per linear foot