Construction unit costs in Arkansas
Median awarded unit prices for the 42 most-bid items on Arkansas public projects, from winning bids in agency bid tabulations.
| Item | Per | Median | Middle half | Winning bids |
|---|---|---|---|---|
| Signs | square foot | $8.00 | $6.00 – $13.35 | 598 |
| Achm Patching of Existing Roadway | ton | $231.00 | $175.00 – $300.00 | 480 |
| Aggregate Base Course (Class 7) | ton | $50.00 | $37.50 – $65.00 | 403 |
| Cold Milling Asphalt Pavement | square yard | $6.00 | $3.10 – $14.12 | 378 |
| Mineral Aggregate in Achm Surface Course (1/2") | ton | $117.78 | $92.77 – $143.94 | 346 |
| Raised Pavement Markers (Type II) | each | $5.50 | $4.00 – $8.00 | 304 |
| Construction Pavement Markings | linear foot | $0.24 | $0.16 – $0.4 | 281 |
| Asphalt Binder (PG 64-22) in Achm Surface Course (1/2") (Minimum Bid $120. 00) | ton | $120.00 | $120.00 – $177.50 | 259 |
| Thermoplastic Pavement Marking Yellow (6") | linear foot | $0.75 | $0.64 – $1.07 | 224 |
| Thermoplastic Pavement Marking White (6") | linear foot | $0.77 | $0.65 – $1.07 | 223 |
| Mineral Aggregate in Achm Surface Course (3/8") | ton | $122.00 | $100.20 – $160.25 | 215 |
| Asphalt Binder (PG 64-22) in Achm Surface Course (3/8") (Minimum Bid $120. 00) | ton | $120.00 | $120.00 – $197.24 | 196 |
| Reflectorized Paint Pavement Marking Yellow (4") | linear foot | $0.195 | $0.14 – $0.39 | 182 |
| Traffic Drums | each | $31.25 | $25.00 – $49.50 | 173 |
| Water | thousand gallons | $10.00 | $5.38 – $10.00 | 163 |
| Silt Fence | linear foot | $3.60 | $3.25 – $4.25 | 161 |
| Mineral Aggregate in Achm Binder Course (1") | ton | $123.18 | $93.50 – $153.07 | 152 |
| Lime | ton | $105.00 | $83.75 – $150.00 | 147 |
| Mulch Cover | acre | $1,124 | $971.00 – $1,556 | 147 |
| Seeding | acre | $1,500 | $1,333 – $2,444 | 146 |
| Guardrail Type A | linear foot | $32.10 | $30.00 – $36.75 | 145 |
| Reinforcing Steel-roadway (Grade 60) | pound | $2.50 | $2.00 – $3.00 | 145 |
| Removal and Disposal of Guardrail | linear foot | $9.47 | $7.01 – $12.16 | 142 |
| Guardrail Terminal (Type 2) | each | $3,150 | $2,987 – $3,544 | 141 |
| Unclassified Excavation | cubic yard | $23.73 | $16.54 – $52.83 | 136 |
| Asphalt Concrete Patching for Maintenance of Traffic | ton | $245.26 | $150.00 – $353.21 | 135 |
| Thermoplastic Pavement Marking (Words) | each | $313.50 | $285.00 – $385.00 | 133 |
| Thermoplastic Pavement Marking White (12") | linear foot | $7.50 | $6.00 – $10.77 | 132 |
| Thermoplastic Pavement Marking (Arrows) | each | $290.00 | $250.00 – $322.03 | 131 |
| Compacted Embankment | cubic yard | $29.80 | $20.50 – $58.98 | 130 |
| Temporary Seeding | acre | $786.47 | $700.00 – $1,000 | 125 |
| Thrie Beam Guardrail Terminal | each | $2,150 | $2,000 – $2,700 | 121 |
| Rumble Strips in Asphalt Shoulders | linear foot | $0.19 | $0.14 – $0.33 | 113 |
| Asphalt Binder (PG 64-22) in Achm Binder Course (1") (Minimum Bid $120.00) | ton | $120.00 | $120.00 – $303.74 | 106 |
| Solid Sodding | square yard | $7.92 | $5.62 – $13.84 | 106 |
| Second Seeding Application | acre | $381.00 | $300.00 – $566.45 | 104 |
| Approach Gutters | cubic yard | $1,850 | $1,391 – $2,262 | 104 |
| Standard Sign | square foot | $25.00 | $22.00 – $30.86 | 99 |
| Grubbing | station | $1,500 | $952.50 – $2,109 | 90 |
| Clearing | station | $1,802 | $1,093 – $3,076 | 90 |
| Mailboxes | each | $56.65 | $43.80 – $85.44 | 67 |
| Mailbox Supports (Single) | each | $165.00 | $112.50 – $201.22 | 66 |
Prices by county in Arkansas
- Benton County: 5 items
- Craighead County: 6 items
- Independence County: 1 items
- Lonoke County: 2 items
- Mississippi County: 5 items
- Pulaski County: 4 items
- Sebastian County: 4 items
- Various County: 2 items
- Washington County: 4 items
Agencies in Arkansas
- ARDOT: 121,966 winning prices