75 kVA single-phase pad-mount transformer: bid prices
Median bid $4,146 per unit (25th to 75th percentile $2,187 to $7,634) from 153 bids by 8 utilities in 27 documents.
Quoted lead time: median 16 weeks across 122 quotes.
By year
| Year | Median | 25th | 75th | Bids | Utilities |
|---|---|---|---|---|---|
| 2018 | $1,856 | $1,748 | $1,892 | 5 | 2 |
| 2019 | $2,188 | $1,990 | $5,128 | 16 | 2 |
| 2022 | $11,179 | $7,899 | $14,062 | 10 | 2 |
| 2023 | $9,720 | $8,348 | $11,482 | 14 | 3 |
| 2024 | $10,726 | $7,085 | $12,726 | 11 | 3 |
| 2025 | $4,779 | $3,909 | $5,579 | 36 | 3 |
| 2026 | $4,002 | $3,692 | $6,985 | 24 | 2 |
By secondary voltage
| Secondary | Median | Bids |
|---|---|---|
| 120/240 | $4,000 | 22 |
| 208/120 | $6,139 | 5 |
| 240/120 | $2,359 | 66 |
| 240/120V | $12,021 | 8 |
| not stated | $4,172 | 52 |
Who bid
| Bidder | Bids | Median | Utilities |
|---|---|---|---|
| Anixter, Inc. | 11 | $1,800 | 1 |
| Wesco Distribution, Inc. | 6 | $1,924 | 1 |
| National Transformer Sales, Inc. | 5 | $1,660 | 1 |
| Richardson Associates | 5 | $1,856 | 1 |
| Richardson Associates (Amorph) | 4 | $2,325 | 1 |
| AR Transformers, Inc. | 4 | $3,465 | 1 |
| Border States | 4 | $3,316 | 2 |
| Richardson & Associates | 3 | $10,095 | 1 |
| Wesco Distribution, Inc. (Bid #1) | 3 | $3,912 | 1 |
| National Transformer Sales | 3 | $1,699 | 1 |
| General Pacific | 3 | $4,865 | 1 |
| Resco | 3 | $12,690 | 2 |
Rows, newest first
Showing 80 of 153. Pro downloads them all as CSV.
| Opened | Utility | Bidder | Unit price | Qty | Lead | Document | |
|---|---|---|---|---|---|---|---|
| 2026-09-01 | Greenville Utilities Commission, NC | Kllen Group America, Inc. | $3,500 | 20 | 16 wk | awarded | source |
| 2026-09-01 | Greenville Utilities Commission, NC | Howard Industries, Inc. | $4,756 | 20 | 30 wk | source | |
| 2026-09-01 | Greenville Utilities Commission, NC | AR Transformers, Inc. | $4,979 | 20 | 14 wk | source | |
| 2026-09-01 | Greenville Utilities Commission, NC | JST Power Equipment, Inc. | $10,470 | 20 | 30 wk | source | |
| 2026-09-01 | Greenville Utilities Commission, NC | Eaglerise Distribution, Inc. | $3,480 | 20 | 16 wk | source | |
| 2026-09-01 | Greenville Utilities Commission, NC | Crib Procure, Inc. | $4,002 | 20 | 18 wk | source | |
| 2026-09-01 | Greenville Utilities Commission, NC | CES Transformers | $6,769 | 20 | 22 wk | source | |
| 2026-09-01 | Greenville Utilities Commission, NC | MVA Power, Inc. | $7,695 | 20 | 20 wk | source | |
| 2026-09-01 | Greenville Utilities Commission, NC | Bell Electrical Supply Co. | $13,140 | 20 | 18 wk | source | |
| 2026-05-26 | Greenville Utilities Commission, NC | Wesco Distribution, Inc. (Bid #2) | $3,200 | 25 | 16 wk | awarded | source |
| 2026-05-26 | Greenville Utilities Commission, NC | Kllen Group America, Inc. | $3,476 | 25 | 16 wk | source | |
| 2026-05-26 | Greenville Utilities Commission, NC | EagleRise Distribution, Inc. | $3,158 | 25 | 16 wk | source | |
| 2026-05-26 | Greenville Utilities Commission, NC | AR Transformers, Inc. | $3,700 | 25 | 14 wk | source | |
| 2026-05-26 | Greenville Utilities Commission, NC | Wesco Distribution, Inc. (Bid #1) | $3,912 | 25 | 11 wk | source | |
| 2026-05-26 | Greenville Utilities Commission, NC | Howard Industries, Inc. | $5,440 | 25 | 48 wk | source | |
| 2026-05-26 | Greenville Utilities Commission, NC | JST Power Equipment | $7,634 | 25 | 30 wk | source | |
| 2026-05-26 | Greenville Utilities Commission, NC | MVA Power, Inc. | $8,219 | 25 | 30 wk | source | |
| 2026-05-26 | Greenville Utilities Commission, NC | CribProcure, Inc. | $14,250 | 25 | 16 wk | source | |
| 2026-03-23 | Geneva Electric, IL | RESCO | $3,881 | 1 | source | ||
| 2026-03-23 | Geneva Electric, IL | Anixter/WESCO | $3,901 | 1 | awarded | source | |
| 2026-03-23 | Geneva Electric, IL | Wesco Distribution Inc. | $3,997 | 1 | source | ||
| 2026-03-23 | Geneva Electric, IL | KLLEN Group America | $4,146 | 1 | source | ||
| 2026-03-23 | Geneva Electric, IL | AR Transformers Inc. | $4,003 | 1 | source | ||
| 2026-03-23 | Geneva Electric, IL | United Utility Supply | $3,666 | 1 | awarded | source | |
| 2025-12-09 | Greenville Utilities Commission, NC | Wesco Distribution, Inc. (Bid #2) | $3,193 | 40 | 12 wk | awarded | source |
| 2025-12-09 | Greenville Utilities Commission, NC | AR Transformers, Inc. | $3,230 | 40 | 14 wk | source | |
| 2025-12-09 | Greenville Utilities Commission, NC | Kllen Group America | $3,462 | 40 | 18 wk | source | |
| 2025-12-09 | Greenville Utilities Commission, NC | EagleRise Distribution, Inc. | $3,582 | 40 | 16 wk | source | |
| 2025-12-09 | Greenville Utilities Commission, NC | Wesco Distribution, Inc. (Bid #1) | $3,969 | 40 | 18 wk | source | |
| 2025-12-09 | Greenville Utilities Commission, NC | Technology International, Inc. | $5,500 | 40 | 30 wk | source | |
| 2025-12-09 | Greenville Utilities Commission, NC | JST Power Equipment, Inc. | $6,935 | 40 | 22 wk | source | |
| 2025-12-09 | Greenville Utilities Commission, NC | CJ Electric Co.,Ltd. | $4,243 | 40 | 16 wk | source | |
| 2025-06-26 | Cowlitz PUD, WA | Anixter-Wesco | $4,728 | 15 | 30 wk | source | |
| 2025-06-26 | Cowlitz PUD, WA | Anixter Power Solutions | $4,181 | 15 | 12 wk | source | |
| 2025-06-26 | Cowlitz PUD, WA | Border States | $5,109 | 15 | 36 wk | source | |
| 2025-06-26 | Cowlitz PUD, WA | Border States | $4,181 | 15 | 13 wk | source | |
| 2025-06-26 | Cowlitz PUD, WA | Eaglerise Renewable (Thailand) (Firm) | $6,384 | 15 | 15 wk | source | |
| 2025-06-26 | Cowlitz PUD, WA | General Pacific | $4,865 | 15 | awarded | source | |
| 2025-06-26 | Cowlitz PUD, WA | Irby | $5,163 | 15 | 18 wk | source | |
| 2025-06-26 | Cowlitz PUD, WA | Irby | $4,830 | 15 | 36 wk | source | |
| 2025-06-26 | Cowlitz PUD, WA | Kllen | $3,578 | 15 | 16 wk | source | |
| 2025-04-22 | Greenville Utilities Commission, NC | AR Transformers, Inc. | $3,205 | 10 | 12 wk | awarded | source |
| 2025-04-22 | Greenville Utilities Commission, NC | Wesco Distribution, Inc. (Bid #1) | $3,580 | 10 | 25 wk | source | |
| 2025-04-22 | Greenville Utilities Commission, NC | TEMA, Inc. | $3,730 | 10 | 16 wk | source | |
| 2025-04-22 | Greenville Utilities Commission, NC | Wesco Distribution, Inc. (Bid #2) | $4,100 | 10 | 10 wk | source | |
| 2025-04-22 | Greenville Utilities Commission, NC | Kllen Group America | $5,200 | 10 | 18 wk | source | |
| 2025-04-22 | Greenville Utilities Commission, NC | Richardson & Associates | $10,095 | 10 | 72 wk | source | |
| 2025-04-22 | Greenville Utilities Commission, NC | Bolt Electrical, LLC | $4,863 | 10 | 10 wk | source | |
| 2025-04-22 | Greenville Utilities Commission, NC | Technology International, Inc. | $5,388 | 10 | 52 wk | source | |
| 2025-04-22 | Greenville Utilities Commission, NC | AMEK A&S, Inc. | $6,267 | 10 | 20 wk | source | |
| 2025-04-07 | Geneva Electric, IL | Border States Industries | $4,702 | 1 | 21 wk | awarded | source |
| 2025-04-07 | Geneva Electric, IL | TRS Electric SA/United TRS Electric, Inc. | $4,398 | 1 | source | ||
| 2025-04-07 | Geneva Electric, IL | Pulse MAC Solutions LLC | $7,560 | 1 | 19 wk | source | |
| 2025-04-07 | Geneva Electric, IL | Wesco Distribution Inc. | $5,550 | 1 | 9 wk | source | |
| 2025-04-07 | Geneva Electric, IL | ULS Corporate Inc. | $7,063 | 1 | source | ||
| 2025-04-07 | Geneva Electric, IL | KLLEN Group America | $5,666 | 1 | 19 wk | awarded | source |
| 2025-04-07 | Geneva Electric, IL | American Wire Group (AWG) | $8,030 | 1 | 28 wk | source | |
| 2025-04-07 | Geneva Electric, IL | AR Transformers Inc. | $4,670 | 1 | 13 wk | awarded | source |
| 2025-04-07 | Geneva Electric, IL | United Utility Supply | $3,666 | 1 | 13 wk | awarded | source |
| 2025-04-07 | Geneva Electric, IL | Amek ANS Inc. | $6,160 | 1 | source | ||
| 2024-07-01 | Geneva Electric, IL | WESCO/Anixter Power Solutions | $10,986 | 1 | 61.5 wk | awarded | source |
| 2024-04-10 | Reading Municipal Light Department, MA | United Utility Supply c/o E.L. Flowers & Associates | $6,619 | 25 | 58 wk | source | |
| 2024-04-10 | Reading Municipal Light Department, MA | ULS Corporate Inc. | $12,425 | 25 | 21 wk | source | |
| 2024-04-10 | Reading Municipal Light Department, MA | Howard Industries, Inc. c/o Power Sales Group | $26,193 | 25 | 72 wk | source | |
| 2024-04-10 | Reading Municipal Light Department, MA | SwitchgearUS LLC | $13,027 | 25 | 46.5 wk | source | |
| 2024-04-10 | Reading Municipal Light Department, MA | WESCO Distribution, Inc. (Submission 2) | $10,726 | 25 | 181 wk | source | |
| 2024-03-21 | Benton PUD, WA | General Pacific/Ermco | $5,393 | 20 | awarded | source | |
| 2024-03-21 | Benton PUD, WA | Irby Utility/Central Moloney | $6,825 | 20 | 44 wk | source | |
| 2024-03-21 | Benton PUD, WA | MVA Power Inc. | $7,344 | 20 | 28 wk | source | |
| 2024-03-21 | Benton PUD, WA | Border States/First Philec | $9,339 | 20 | 21 wk | source | |
| 2024-03-21 | Benton PUD, WA | Howard Industries | $14,494 | 20 | 72 wk | source | |
| 2023-11-15 | Dover Electric, DE | NexGen Power, INC | $9,300 | 20 | 40 wk | source | |
| 2023-11-15 | Dover Electric, DE | Technology International | $19,500 | 20 | 58.5 wk | source | |
| 2023-11-15 | Dover Electric, DE | Wesco/Anixter | $8,763 | 20 | 34 wk | source | |
| 2023-11-15 | Dover Electric, DE | ECB Solutions | $9,345 | 20 | 16 wk | source | |
| 2023-11-15 | Dover Electric, DE | ULS Corporation | $11,952 | 20 | 22 wk | source | |
| 2023-11-15 | Dover Electric, DE | Irby Utilities | $14,515 | 20 | 43.3 wk | source | |
| 2023-11-15 | Dover Electric, DE | HA Rawls | $7,852 | 20 | 72 wk | source | |
| 2023-11-15 | Dover Electric, DE | PulseMAX Solutions | $7,878 | 20 | 18 wk | awarded | source |
| 2023-03-23 | Greenville Utilities Commission, NC | Alpha Plotter, LLC. | $6,080 | 40 | 20 wk | awarded | source |
Prices are the unit prices each utility printed for the bidder, as bid. Where a tab prints only a total, the unit price is that total divided by the quantity and labelled. Loss-evaluated (ownership) cost is never shown as a price. Units above 10 MVA are kept apart. A median needs 5 or more bids from 2 or more utilities; below that the page says so instead of showing a number. Every row links to the utility's own document. Not a quote, not an estimate.