Home › Grid › Transformers › 25 kVA single-phase pole-mount transformer
25 kVA single-phase pole-mount transformer: bid prices
Median bid $1,677 per unit (25th to 75th percentile $1,016 to $2,500) from 273 bids by 8 utilities in 37 documents.
Quoted lead time: median 14 weeks across 197 quotes.
By year
| Year | Median | 25th | 75th | Bids | Utilities |
|---|---|---|---|---|---|
| 2018 | $786 | $764 | $918 | 9 | 2 |
| 2019 | $961 | $915 | $1,042 | 27 | 2 |
| 2022 | $3,637 | $2,930 | $4,022 | 20 | 2 |
| 2023 | $3,081 | $2,615 | $4,301 | 17 | 3 |
| 2024 | $2,508 | $2,318 | $3,223 | 34 | 3 |
| 2025 | $1,901 | $1,623 | $2,425 | 69 | 5 |
| 2026 | $1,771 | $1,444 | $2,257 | 33 | 3 |
By secondary voltage
| Secondary | Median | Bids |
|---|---|---|
| 120/208 | $2,507 | 3 |
| 120/240 | $1,112 | 112 |
| 120/240V | $4,028 | 8 |
| 240/120 | $2,256 | 21 |
| 240/480 | $1,724 | 29 |
| 240/480V | $5,801 | 4 |
| 277 | $1,621 | 16 |
| 277/480 | $1,694 | 12 |
| 277/480V | $3,911 | 4 |
| not stated | $1,845 | 64 |
Who bid
| Bidder | Bids | Median | Utilities |
|---|---|---|---|
| Wesco Distribution, Inc. | 20 | $1,106 | 1 |
| Anixter, Inc. | 14 | $848 | 1 |
| Richardson & Associates | 10 | $3,264 | 1 |
| National Transformer Sales, Inc. | 9 | $774 | 1 |
| Richardson Associates | 9 | $945 | 1 |
| Border States | 8 | $1,284 | 2 |
| General Pacific | 7 | $1,065 | 1 |
| National Transformer Sales | 7 | $926 | 1 |
| Richardson Associates (Amorph) | 6 | $1,066 | 1 |
| Irby | 6 | $1,963 | 1 |
| Resco | 6 | $3,455 | 2 |
| AR Transformers, Inc. | 6 | $1,834 | 1 |
Rows, newest first
Showing 80 of 273. Pro downloads them all as CSV.
| Opened | Utility | Bidder | Unit price | Qty | Lead | Document | |
|---|---|---|---|---|---|---|---|
| 2026-10-07 | Reading Municipal Light Department, MA | TECHNOLOGY INTERNATIONAL INC. | $2,500 | 3 | source | ||
| 2026-10-07 | Reading Municipal Light Department, MA | HOWARD INDUSTRIES c/O POWER SALES GROUP | $2,298 | 3 | source | ||
| 2026-10-07 | Reading Municipal Light Department, MA | IRBY PROPOSAL #1 | $2,256 | 3 | source | ||
| 2026-10-07 | Reading Municipal Light Department, MA | IRBY PROPOSAL #2 | $2,435 | 3 | source | ||
| 2026-10-07 | Reading Municipal Light Department, MA | SWITCHGEARUS, LLC c/o HIRELI | $2,210 | 3 | source | ||
| 2026-10-07 | Reading Municipal Light Department, MA | WESCO DISTRIBUTION | $2,257 | 3 | source | ||
| 2026-09-01 | Greenville Utilities Commission, NC | Kllen Group America,Inc. | $1,310 | 6 | 18 wk | awarded | source |
| 2026-09-01 | Greenville Utilities Commission, NC | AR Transformers, Inc. | $1,444 | 6 | 14 wk | source | |
| 2026-09-01 | Greenville Utilities Commission, NC | Howard Industries, Inc. | $1,815 | 6 | 8 wk | source | |
| 2026-09-01 | Greenville Utilities Commission, NC | Eaglerise Distribution, Inc. | $1,300 | 6 | 16 wk | source | |
| 2026-09-01 | Greenville Utilities Commission, NC | Crib Procure, Inc. | $2,138 | 6 | 18 wk | source | |
| 2026-09-01 | Greenville Utilities Commission, NC | MVA Power, Inc. | $2,841 | 6 | 20 wk | source | |
| 2026-09-01 | Greenville Utilities Commission, NC | Bell Electrical Supply Co. | $5,711 | 6 | 18 wk | source | |
| 2026-07-21 | Greenville Utilities Commission, NC | Kllen Group America, Inc. | $1,370 | 25 | 16 wk | awarded | source |
| 2026-07-21 | Greenville Utilities Commission, NC | EagleRise Distribution, Inc. | $1,296 | 25 | 16 wk | source | |
| 2026-07-21 | Greenville Utilities Commission, NC | Technology International, Inc. | $2,100 | 25 | 20 wk | source | |
| 2026-07-21 | Greenville Utilities Commission, NC | Wesco Distribution, Inc. | $2,163 | 25 | 8 wk | source | |
| 2026-07-21 | Greenville Utilities Commission, NC | Howard Industries | $2,375 | 25 | 8 wk | source | |
| 2026-05-26 | Greenville Utilities Commission, NC | Kllen Group America, Inc. | $1,370 | 50 | 16 wk | awarded | source |
| 2026-05-26 | Greenville Utilities Commission, NC | EagleRise Distribution, Inc. | $1,350 | 50 | 16 wk | source | |
| 2026-05-26 | Greenville Utilities Commission, NC | AR Transformers, Inc. | $1,500 | 50 | 14 wk | source | |
| 2026-05-26 | Greenville Utilities Commission, NC | Wesco Distribution, Inc. (Bid #1) | $1,789 | 50 | 8 wk | source | |
| 2026-05-26 | Greenville Utilities Commission, NC | Wesco Distribution, Inc. (Bid #2) | $1,771 | 50 | 21 wk | source | |
| 2026-05-26 | Greenville Utilities Commission, NC | Howard Industries, Inc. | $2,396 | 50 | 8 wk | source | |
| 2026-05-26 | Greenville Utilities Commission, NC | MVA Power, Inc. | $2,757 | 50 | 30 wk | source | |
| 2026-03-23 | Geneva Electric, IL | Anixter/WESCO | $1,565 | 1 | awarded | source | |
| 2026-03-23 | Geneva Electric, IL | KLLEN Group America | $1,724 | 1 | source | ||
| 2026-03-23 | Geneva Electric, IL | AR Transformers Inc. | $1,289 | 1 | source | ||
| 2026-03-23 | Geneva Electric, IL | United Utility Supply | $1,581 | 1 | awarded | source | |
| 2026-03-23 | Geneva Electric, IL | Anixter/WESCO | $1,542 | 1 | awarded | source | |
| 2026-03-23 | Geneva Electric, IL | KLLEN Group America | $1,724 | 1 | source | ||
| 2026-03-23 | Geneva Electric, IL | AR Transformers Inc. | $1,306 | 1 | source | ||
| 2026-03-23 | Geneva Electric, IL | United Utility Supply | $1,597 | 1 | awarded | source | |
| 2025-12-09 | Greenville Utilities Commission, NC | AR Transformers, Inc. | $1,372 | 20 | 14 wk | awarded | source |
| 2025-12-09 | Greenville Utilities Commission, NC | Kllen Group America | $1,572 | 20 | 18 wk | source | |
| 2025-12-09 | Greenville Utilities Commission, NC | Wesco Distribution, Inc. (Bid #1) | $1,659 | 20 | 8 wk | source | |
| 2025-12-09 | Greenville Utilities Commission, NC | EagleRise Distribution, Inc. | $1,730 | 20 | 16 wk | source | |
| 2025-12-09 | Greenville Utilities Commission, NC | Technology International, Inc. | $2,500 | 20 | 30 wk | source | |
| 2025-12-09 | Greenville Utilities Commission, NC | CJ Electric Co.,Ltd. | $2,105 | 20 | 12 wk | source | |
| 2025-08-12 | Greenville Utilities Commission, NC | Wesco Distribution Inc. (Bid #1) | $1,445 | 40 | 10 wk | awarded | source |
| 2025-08-12 | Greenville Utilities Commission, NC | Kllen Group America | $1,677 | 40 | 14 wk | source | |
| 2025-08-12 | Greenville Utilities Commission, NC | TEMA, Inc. | $1,950 | 40 | 14 wk | source | |
| 2025-08-12 | Greenville Utilities Commission, NC | Richardson & Associates | $2,425 | 40 | 26 wk | source | |
| 2025-08-12 | Greenville Utilities Commission, NC | CJ Electric Co.,Ltd. | $2,140 | 40 | 20 wk | source | |
| 2025-08-12 | Greenville Utilities Commission, NC | Border States Electric | $2,304 | 40 | 14 wk | source | |
| 2025-08-12 | Greenville Utilities Commission, NC | Nexgen Power, Inc. | $3,333 | 40 | 20 wk | source | |
| 2025-08-12 | Greenville Utilities Commission, NC | Uttam (Bharat) Electrical Pvt. Ltd. | $5,255 | 40 | 20 wk | source | |
| 2025-06-26 | Cowlitz PUD, WA | Anixter-Wesco | $1,589 | 75 | 12 wk | source | |
| 2025-06-26 | Cowlitz PUD, WA | Anixter-Wesco | $1,533 | 5 | 12 wk | source | |
| 2025-06-26 | Cowlitz PUD, WA | Anixter-Wesco | $1,647 | 1 | 12 wk | source | |
| 2025-06-26 | Cowlitz PUD, WA | Border States | $1,737 | 75 | 15 wk | source | |
| 2025-06-26 | Cowlitz PUD, WA | Border States | $1,676 | 5 | 15 wk | source | |
| 2025-06-26 | Cowlitz PUD, WA | Border States | $1,799 | 1 | 15 wk | source | |
| 2025-06-26 | Cowlitz PUD, WA | Eaglerise Renewable (Thailand) (Firm) | $1,412 | 75 | 13 wk | source | |
| 2025-06-26 | Cowlitz PUD, WA | Eaglerise Renewable (Thailand) (Firm) | $1,367 | 5 | 13 wk | source | |
| 2025-06-26 | Cowlitz PUD, WA | Eaglerise Renewable (Thailand) (Firm) | $1,505 | 1 | 13 wk | source | |
| 2025-06-26 | Cowlitz PUD, WA | General Pacific | $1,881 | 75 | awarded | source | |
| 2025-06-26 | Cowlitz PUD, WA | General Pacific | $1,901 | 5 | awarded | source | |
| 2025-06-26 | Cowlitz PUD, WA | General Pacific | $1,920 | 1 | awarded | source | |
| 2025-06-26 | Cowlitz PUD, WA | Irby | $2,295 | 75 | 14 wk | source | |
| 2025-06-26 | Cowlitz PUD, WA | Irby | $2,244 | 5 | 14 wk | source | |
| 2025-06-26 | Cowlitz PUD, WA | Irby | $2,468 | 1 | 14 wk | source | |
| 2025-06-26 | Cowlitz PUD, WA | Irby | $1,623 | 75 | 16 wk | source | |
| 2025-06-26 | Cowlitz PUD, WA | Irby | $1,566 | 5 | 14 wk | source | |
| 2025-06-26 | Cowlitz PUD, WA | Irby | $1,682 | 1 | 16 wk | source | |
| 2025-06-26 | Cowlitz PUD, WA | Kllen | $1,385 | 75 | 16 wk | source | |
| 2025-06-26 | Cowlitz PUD, WA | Kllen | $1,385 | 5 | 16 wk | source | |
| 2025-06-26 | Cowlitz PUD, WA | Kllen | $1,385 | 1 | 16 wk | source | |
| 2025-04-23 | Reading Municipal Light Department, MA | AMEK A&S, Inc. | $2,835 | 15 | source | ||
| 2025-04-23 | Reading Municipal Light Department, MA | AR Transformers Inc. | $1,724 | 15 | source | ||
| 2025-04-23 | Reading Municipal Light Department, MA | Bluefin ESI | $4,891 | 15 | source | ||
| 2025-04-23 | Reading Municipal Light Department, MA | GD Partners, Inc. | $1,987 | 15 | source | ||
| 2025-04-23 | Reading Municipal Light Department, MA | Graybar Electric Company | $1,635 | 15 | source | ||
| 2025-04-23 | Reading Municipal Light Department, MA | Howard Industries, Inc. c/o Power Sales Group | $2,573 | 15 | source | ||
| 2025-04-23 | Reading Municipal Light Department, MA | Stuart C. Irby Company - Proposal #1 | $1,433 | 15 | source | ||
| 2025-04-23 | Reading Municipal Light Department, MA | Stuart C. Irby Company - Proposal #2 | $1,608 | 15 | source | ||
| 2025-04-23 | Reading Municipal Light Department, MA | Jonah's Enterprises, Inc. | $4,596 | 15 | source | ||
| 2025-04-23 | Reading Municipal Light Department, MA | Kllen Group America, Inc. | $2,303 | 15 | source | ||
| 2025-04-23 | Reading Municipal Light Department, MA | PanAmerica Supply, Inc. | $1,600 | 15 | source | ||
| 2025-04-23 | Reading Municipal Light Department, MA | SwitchgearUS LLC c/o HiReli | $2,232 | 15 | source |
Prices are the unit prices each utility printed for the bidder, as bid. Where a tab prints only a total, the unit price is that total divided by the quantity and labelled. Loss-evaluated (ownership) cost is never shown as a price. Units above 10 MVA are kept apart. A median needs 5 or more bids from 2 or more utilities; below that the page says so instead of showing a number. Every row links to the utility's own document. Not a quote, not an estimate.