167 kVA single-phase pole-mount transformer: bid prices

Median bid $5,403 per unit (25th to 75th percentile $4,109 to $6,350) from 84 bids by 4 utilities in 7 documents.

Quoted lead time: median 19 weeks across 36 quotes.

By year

YearMedian25th75thBidsUtilities
2025$5,867$5,303$6,562493

By secondary voltage

SecondaryMedianBids
120/240$6,02131
240/480$5,31226
277$5,30327

Who bid

BidderBidsMedianUtilities
AR Transformers Inc.6$6,4801
United Utility Supply6$5,4031
KLLEN Group America6$4,3811
Irby6$6,2981
General Pacific6$5,2281
Anixter-Wesco3$5,8671
Amek ANS Inc.3$5,1861
American Wire Group (AWG)3$8,7701
Anixter Power Solutions3$4,0251
Resco3$2,7491
Border States Industries3$5,8921
Anixter/WESCO3$6,2091

Rows, newest first

Showing 80 of 84. Pro downloads them all as CSV.

OpenedUtilityBidderUnit priceQtyLeadDocument
2026-03-23Geneva Electric, ILRESCO$6,6071source
2026-03-23Geneva Electric, ILAnixter/WESCO$6,3241awardedsource
2026-03-23Geneva Electric, ILKLLEN Group America$3,6321source
2026-03-23Geneva Electric, ILAR Transformers Inc.$4,5591source
2026-03-23Geneva Electric, ILUnited Utility Supply$6,3301awardedsource
2026-03-23Geneva Electric, ILRESCO$9,4201source
2026-03-23Geneva Electric, ILAnixter/WESCO$6,2091awardedsource
2026-03-23Geneva Electric, ILKLLEN Group America$3,6321source
2026-03-23Geneva Electric, ILAR Transformers Inc.$3,7851source
2026-03-23Geneva Electric, ILUnited Utility Supply$4,8261awardedsource
2026-03-23Geneva Electric, ILRESCO$6,1631source
2026-03-23Geneva Electric, ILAnixter/WESCO$6,1311awardedsource
2026-03-23Geneva Electric, ILKLLEN Group America$3,6321source
2026-03-23Geneva Electric, ILAR Transformers Inc.$3,7671source
2026-03-23Geneva Electric, ILUnited Utility Supply$5,0241awardedsource
2025-06-26Cowlitz PUD, WAAnixter-Wesco$7,143130 wksource
2025-06-26Cowlitz PUD, WAAnixter-Wesco$5,491230 wksource
2025-06-26Cowlitz PUD, WAAnixter-Wesco$5,867130 wksource
2025-06-26Cowlitz PUD, WABorder States$7,808134 wksource
2025-06-26Cowlitz PUD, WABorder States$6,002233 wksource
2025-06-26Cowlitz PUD, WABorder States$6,412133 wksource
2025-06-26Cowlitz PUD, WAEaglerise Renewable (Thailand) (Firm)$4,465113 wksource
2025-06-26Cowlitz PUD, WAEaglerise Renewable (Thailand) (Firm)$4,287213 wksource
2025-06-26Cowlitz PUD, WAEaglerise Renewable (Thailand) (Firm)$4,489113 wksource
2025-06-26Cowlitz PUD, WAGeneral Pacific$7,7841awardedsource
2025-06-26Cowlitz PUD, WAGeneral Pacific$6,5392awardedsource
2025-06-26Cowlitz PUD, WAGeneral Pacific$6,4681awardedsource
2025-06-26Cowlitz PUD, WAIrby$6,636114 wksource
2025-06-26Cowlitz PUD, WAIrby$6,278214 wksource
2025-06-26Cowlitz PUD, WAIrby$6,318114 wksource
2025-06-26Cowlitz PUD, WAIrby$7,298133 wksource
2025-06-26Cowlitz PUD, WAIrby$5,610233 wksource
2025-06-26Cowlitz PUD, WAIrby$5,994133 wksource
2025-06-26Cowlitz PUD, WAKllen$4,137116 wksource
2025-06-26Cowlitz PUD, WAKllen$4,137216 wksource
2025-06-26Cowlitz PUD, WAKllen$4,137116 wksource
2025-04-07Geneva Electric, ILBorder States Industries$7,786121 wkawardedsource
2025-04-07Geneva Electric, ILTRS Electric SA/United TRS Electric, Inc.$5,3031source
2025-04-07Geneva Electric, ILPulse MAC Solutions LLC$5,655119 wksource
2025-04-07Geneva Electric, ILULS Corporate Inc.$6,0211source
2025-04-07Geneva Electric, ILKLLEN Group America$5,129119 wkawardedsource
2025-04-07Geneva Electric, ILAmerican Wire Group (AWG)$8,9191source
2025-04-07Geneva Electric, ILAR Transformers Inc.$8,400113 wkawardedsource
2025-04-07Geneva Electric, ILUnited Utility Supply$6,562113 wkawardedsource
2025-04-07Geneva Electric, ILAmek ANS Inc.$5,3101source
2025-04-07Geneva Electric, ILBorder States Industries$5,892121 wkawardedsource
2025-04-07Geneva Electric, ILTRS Electric SA/United TRS Electric, Inc.$5,3031source
2025-04-07Geneva Electric, ILPulse MAC Solutions LLC$5,785119 wksource
2025-04-07Geneva Electric, ILULS Corporate Inc.$6,0211source
2025-04-07Geneva Electric, ILKLLEN Group America$5,129119 wkawardedsource
2025-04-07Geneva Electric, ILAmerican Wire Group (AWG)$8,7701source
2025-04-07Geneva Electric, ILAR Transformers Inc.$8,400113 wkawardedsource
2025-04-07Geneva Electric, ILUnited Utility Supply$5,322113 wkawardedsource
2025-04-07Geneva Electric, ILAmek ANS Inc.$5,1861source
2025-04-07Geneva Electric, ILBorder States Industries$5,575121 wkawardedsource
2025-04-07Geneva Electric, ILTRS Electric SA/United TRS Electric, Inc.$5,3031source
2025-04-07Geneva Electric, ILPulse MAC Solutions LLC$5,850119 wksource
2025-04-07Geneva Electric, ILULS Corporate Inc.$6,0211source
2025-04-07Geneva Electric, ILKLLEN Group America$5,129119 wkawardedsource
2025-04-07Geneva Electric, ILAmerican Wire Group (AWG)$8,5901source
2025-04-07Geneva Electric, ILAR Transformers Inc.$8,400113 wkawardedsource
2025-04-07Geneva Electric, ILUnited Utility Supply$5,484113 wkawardedsource
2025-04-07Geneva Electric, ILAmek ANS Inc.$5,0911source
2025-03-27Benton PUD, WAKerec$4,6005awardedsource
2024-04-23North Little Rock Electric, ARIntellogic Engineering Inc$6,69025 wksource
2024-04-23North Little Rock Electric, ARWesco$8,96433 wksource
2024-04-23North Little Rock Electric, ARAR Electric Coop$7,27018 wksource
2019-05-29Cowlitz PUD, WAAnixter Power Solutions$4,2823source
2019-05-29Cowlitz PUD, WAAnixter Power Solutions$3,8101source
2019-05-29Cowlitz PUD, WAAnixter Power Solutions$4,0251source
2019-05-29Cowlitz PUD, WAGeneral Pacific$3,9893source
2019-05-29Cowlitz PUD, WAGeneral Pacific$3,7311source
2019-05-29Cowlitz PUD, WAGeneral Pacific$3,6301source
2019-05-29Cowlitz PUD, WAHees$3,4893source
2019-05-29Cowlitz PUD, WAHees$2,9411source
2019-05-29Cowlitz PUD, WAHees$2,9371source
2019-05-29Cowlitz PUD, WAMcKaig Evergeen$3,0653source
2019-05-29Cowlitz PUD, WAMcKaig Evergeen$3,0131source
2019-05-29Cowlitz PUD, WAMcKaig Evergeen$2,9061source
2018-06-11Geneva Electric, ILResco$3,1651awardedsource

Prices are the unit prices each utility printed for the bidder, as bid. Where a tab prints only a total, the unit price is that total divided by the quantity and labelled. Loss-evaluated (ownership) cost is never shown as a price. Units above 10 MVA are kept apart. A median needs 5 or more bids from 2 or more utilities; below that the page says so instead of showing a number. Every row links to the utility's own document. Not a quote, not an estimate.